Second story addition in Bellevue: what the lot allows before you design

How Bellevue's floor area ratio, height rule and nonconforming-structure rule decide a second floor, what the existing house has to carry, and what the city asks for. Worked on one hypothetical lot, with the arithmetic shown.

By David Meade, AIA, NCARBUpdated 3 November 202611 min read

On this page

    A second story addition on a Bellevue house is decided first by floor area. Since 2025 the city caps a single house at a floor area ratio of 0.5 on a lot of 10,000 square feet or less, the ratio counts every story and, as I read the definition, the garage, and it applies to an addition that enlarges the house by 20 percent or more. A full second floor clears that 20 percent line easily, so the first question is how many square feet your lot has left after the floor area you already have. Height is the second test. My first basic feasibility check is free and very quick, usually about a day, and it asks that question about your lot. Below is the arithmetic on one hypothetical Bellevue lot, each rule read in the city’s ordinance copies or on its pages on 3 November 2026.

    Key takeaways

    • On my hypothetical lot (7,500 square feet, zone SR-4, a 1,950 square foot one story house) the floor area cap is 3,750 square feet (7,500 x 0.5), which leaves 1,800 for a second floor. A 1,500 square foot floor fits with 300 to spare; carrying it over the garage too is 150 over.
    • Washington’s residential code says that where an addition adds a story, the old house and the new work together must meet the code for new construction, unless an engineering evaluation shows they carry the combined loads (R4505.3).
    • If the old walls sit inside today’s yards, the Ordinance 6906 text I read has no sentence that lets a new floor stand on them. Plan as if it must stay out until the city says otherwise in writing.
    • The first basic check is free and very quick, usually about a day.

    Who this page is for

    This page is for the owner of an older Bellevue house who wants a second floor and has a project budget of $750,000 or more. A small addition is below my minimum. My firm designs and administers construction; we do not build. Bellevue’s code site sat behind a bot check and I did not bypass it, so I read the ordinance copies the city posts, its permit pages and the state code. Rules move, so confirm with the city. This is general information, not legal advice. If you also plan to remodel most of the house, my addition and whole house remodel page works that budget.

    Request your free feasibility check

    Send me the address, what you want upstairs and a rough budget. I will reply to you personally.

      Your details go to David only. See the privacy policy. The first basic feasibility check is free.

      Prefer to talk? Call 425 753 6452 or message David on WhatsApp.

      Sunlit corner living room with a fireplace, oak floor and windows facing the lake
      Huang Residence, Piper Cole Architects. A sunlit corner living room with a fireplace, oak floor and windows facing the lake.

      Free feasibility check

      Planning a custom home or a remodel of $750,000 or more?

      Send me the address and a few lines about what you want. The first feasibility check is free and usually takes about a day.

      What size of second floor reaches $750,000

      I use this site’s planning range for additions, $350 to $650 per square foot. It is not a quote, and it leaves out design fees, permits, tax and contingency; a builder’s bid on finished drawings is the real number. $750,000 divided by the top of the range is 750,000 / 650 = 1,154 square feet (rounded up), and by the bottom 750,000 / 350 = 2,143.

      Second floor Arithmetic Planning range Reaches $750,000?
      800 sq ft 800 x 350 and 800 x 650 $280,000 to $520,000 No, at any point of the range (it would need $938 per sq ft)
      1,500 sq ft 1,500 x 350 and 1,500 x 650 $525,000 to $975,000 At $500 per sq ft and up (750,000 / 1,500)
      1,800 sq ft 1,800 x 350 and 1,800 x 650 $630,000 to $1,170,000 At $417 per sq ft and up (750,000 / 1,800)

      So a second floor of 1,154 square feet or more can reach my minimum, and one of 2,143 or more does at any price in the range. Whether your lot allows that much is the next question.

      Second story addition in Bellevue: what the lot allows

      I worked one hypothetical lot, not a real property or a client’s: 60 feet wide and 125 deep, 7,500 square feet (60 x 125), flat, no critical areas, zone SR-4, the name Bellevue’s 2025 rename gave the old R-5 (my Bellevue zoning guide has the name table). A one story house of 1,950 square feet stands on it, an attached garage of 450 included. The limits come from Ordinance 6851, adopted June 24, 2025 (the Legistar copy is unsigned and omits the chart’s unamended footnotes; ask the city whether any applies).

      Rule What the ordinance says On the hypothetical lot
      Floor area ratio, LUC 20.20.390 0.5 for one dwelling unit on a lot of 10,000 square feet or less. Gross floor area counts every story of every building on the lot, and a space 18 feet or taller counts twice. Carports, porches, decks, unfinished attics and lower levels less than 5 feet above finished grade are left out. Garages are not on that list, so I count the garage and ask the city to confirm. 7,500 x 0.5 = 3,750 square feet
      When it applies to an addition To additions to an existing detached single-family house that increase gross square feet by 20 percent or more (20.20.390.A.2). 1,950 x 0.20 = 390 square feet reaches the line
      Coverage by structures, Chart 20.20.010 40 percent in SR-4. A second floor stacked inside the footprint adds none. 7,500 x 0.40 = 3,000; the house covers 1,950, which is 26 percent
      Yards Front 20 feet, rear 20, each side at least 5, the two sides at least 15 together. Width 60 minus 15 = 45; depth 125 minus 40 = 85
      Height, notes 44 and 45 30 feet to a flat roof or 35 to a pitched ridge, from the average elevation of the existing grade. No facade of a new house or addition may exceed 40 feet from existing grade at its wall. 35 feet to a pitched ridge on flat ground

      The 20 percent line has two wordings. Ordinance 6851 says a 20 percent or greater increase in gross square feet. Ordinance 6931, the July 2026 omnibus text as posted for the 28 July council meeting, says 20 percent or more of the gross floor area permitted under the original approval. The city says council approved a package of ordinances that day without naming numbers, and I have not seen a signed copy. A 1,500 square foot floor on this house is 1,500 / 1,950 = 77 percent, over the line either way.

      Plan 1, floor over the living area. The house keeps its 1,950 square feet, and the new floor sits over the 1,500 that is not garage (1,950 minus 450). Total floor area is 1,950 + 1,500 = 3,450, which is 300 under the 3,750 cap. Coverage is unchanged. It fits.

      Plan 2, floor over everything. A 1,950 square foot second floor makes 1,950 + 1,950 = 3,900, which is 150 over. The lot allows 3,750 minus 1,950 = 1,800 upstairs, so 150 square feet has to come off. A room open to 18 feet or more counts twice, so a tall stair hall uses floor area that a flat ceiling would not.

      Height. These figures are my assumptions, not measurements. Say the existing ridge is 16 feet above average existing grade and a second floor with 9 foot ceilings puts the new ridge at 27. That is 35 minus 27 = 8 feet under the limit, and on flat ground the facade is 27, under 40. A slope changes both. The averaging method is worked on my existing conditions page.

      Building up over an older house

      An older house may stand closer to a line than today’s yards allow. Say the north wall of my example house is 4 feet from the side line, where the minimum is 5, and runs 45 feet. That makes it a nonconforming structure.

      Bellevue rewrote its nonconforming rule, LUC 20.20.561, in Ordinance 6906. I read the text the city posted for council; the city says council approved the amendments on March 17, 2026 (city page). I could not read the codified section or its effective date. Four points matter to a second floor.

      • The house may stay. A nonconforming structure may remain unless the section limits it.
      • New work must conform. Alterations to a nonconforming structure are allowed if the alterations conform to the applicable development regulations (E.2.a). The text has no sentence that expressly lets a new floor stand on a wall inside a required yard, so I ask the city.
      • A value test can pull in the whole site. In SR-4 and the other districts from LL-1 through LDR-1, when the value of alterations exceeds the replacement value of all primary structures, the structure and site come into full compliance (E.3.c.ii, E.3.e). Alterations in the preceding three years count as one (E.3.b.i).
      • You show the house was lawful. The city asks for proof it was permitted when established and maintained: permits, utility bills, dated aerial photos (B).

      The effect on my example: if the new wall must stay 5 feet from the line, the second floor steps back 1 foot (5 minus 4) along 45 feet, which costs 45 square feet. A 1,500 floor becomes 1,455, and total floor area is 1,950 + 1,455 = 3,405, still 345 under the cap. For the value test, suppose the replacement value is $600,000. That is my assumption; the definition is the cost to replace the structure, minus deferred maintenance. At the planning range a 1,455 square foot floor is 1,455 x 350 = $509,250 to 1,455 x 650 = $945,750, and the top is over $600,000. The city counts the value with a cost estimator acceptable to the Director, so my range only shows how a large project can cross the line. See when a remodel counts as a new house. Shoreline nonconformities fall under LUC 20.25E, which I could not read.

      What the existing house has to carry

      The state residential code, WAC 51-51-4505, effective March 15, 2024, covers vertical additions in R4505.3. Where an addition adds a story, the new construction and the existing building together must meet the requirements of the code for new construction. The exception: if they are evaluated together under accepted engineering practice and shown sufficient for the combined loads, no structural alterations are required. Bellevue says it adopted the 2021 I-Codes effective March 15, 2024 (city page). I did not read its local amendments. The state building code council’s site lists May 3, 2027 as the effective date of its 2024 codes, so confirm which edition your application falls under.

      The section gives no loads. What a house can carry is an engineer’s finding from the foundation, framing and walls. The city’s minimum documents for an addition include a structural plan and structural and lateral calculations. See when a remodel needs a structural engineer for who prepares them. Washington’s architect licensing law exempts design work on a residential building of up to four dwelling units (RCW 18.08.410(5)), so hiring me is your call.

      Kitchen with cherry cabinets, an island with seating, a skylight and a slate floor
      Cannon Remodel, Piper Cole Architects. A kitchen with cherry cabinets, an island with seating, a skylight and a slate floor.

      The permit, the documents and the city’s time

      Which permit. The city’s BR page covers adding less than 3,000 square feet to an existing house. Its BS page covers an addition greater than 3,000 square feet of new and/or replaced floor area. My example floor is 1,455 new. If you also replace 1,600 square feet of first floor, 1,455 + 1,600 = 3,055 would pass 3,000, if the city counts replaced area that way. Its pages do not say, so ask first.

      Documents. The BR page’s minimum to start includes an architectural plan, a boundary and topographic survey, a residential site plan, structural and lateral calculations, a structural plan, an energy code sheet, stormwater documents and a value of improvements form. The site plan must show grades at 2 foot intervals and each tree (city page). The value of improvements form is dated 2018 and cites the old section, LUC 20.20.560, so ask the planner whether you need it. The BS page adds an arborist report and civil and shoring plans.

      Trees. The city’s trees page lists alterations and additions to existing structures among the projects that must meet minimum tree density, by keeping or planting trees. Ask the Land Use planners whether a floor added on top draws it. My teardown page works the credit arithmetic.

      Permit City first review target Completed 2 Nov 2025 to 2 Nov 2026 Median Average
      BR, addition to existing structure 14 days, 10 per revision 165 75 days 153 days
      BS, structure addition, major 21 days, 14 per revision (BS, single family) 7 189 days 274 days

      These come from the city’s processing report and its review timelines page, which says actual times vary. The report does not say how it counts days. The BR row mixes every small addition, so it is not a second story figure, and the BS row rests on seven permits. Steps are in my permit guide and fees in the fee guide.

      What to settle before you design

      Put these to the city in writing (Land Use, 425-452-4188; Permit Center, 425-452-4898) and keep the answers.

      • Floor area: which floor area the 20 percent test measures from, and how the city counts your lower level and garage.
      • Old walls: whether a floor may stand on a wall inside a required yard, and whether the value test applies to your house.
      • Permit track: whether replaced floor area counts toward 3,000 square feet, and whether the value of improvements form is needed.
      • Records: the house’s permit history and a boundary and topographic survey.
      • Send me the address and what you learn, and I will reply to you personally.

      How it works with me

      First comes the free basic feasibility check, very quick, usually about a day. An in depth analysis is $1,500, takes 2 to 3 weeks and goes further. Then I quote a fixed fee for design and permit, set by project budget and location, about $10,000 to $200,000 depending on scope. Design to permit submission typically takes 2 to 4 months. After the permit I administer construction for you. I do not build.

      I have been an architect since 1996, and I am a member of the AIA (since 1992) and NCARB (since 1996). The Carr residence was featured in Above The Lake and Lux magazines.

      Selected work

      Remodels and additions from the practice.

      See the full portfolio

      Before you design the new floor

      Ask for the free first feasibility check

      Send me the address and what you want upstairs through the request form above, or call or message me on WhatsApp. The first basic feasibility check is free and very quick, usually about a day. An in depth analysis is $1,500, takes 2 to 3 weeks and goes further.

      Questions

      Can I add a second story to my house in Bellevue?

      Often, if the lot has floor area left. Bellevue caps one house at a floor area ratio of 0.5 on a lot of 10,000 square feet or less, counts every story and the garage, and applies that cap to additions that enlarge the house by 20 percent or more. Height is 35 feet to a pitched ridge from average existing grade. Send me the address and I will check the lot in my free first feasibility check, usually about a day.

      How big can a second story addition be in Bellevue?

      It is the floor area cap minus what you have. On a 7,500 square foot lot the cap is 3,750 square feet (7,500 x 0.5). With a 1,950 square foot one story house that leaves 1,800 square feet (3,750 minus 1,950). Rooms open to 18 feet or more count twice. Confirm the current rule with the city, including how it counts your lower level.

      Does a second story addition need a structural engineer in Bellevue?

      The city’s minimum documents for an addition include a structural plan and structural and lateral calculations. The state residential code (R4505.3, WAC 51-51-4505) says that when an addition adds a story, the new work and the existing house together must meet the code for new construction unless an engineering evaluation shows the combined structure can carry the combined loads. Plan on an engineering evaluation of the house.

      What if my house is closer to the property line than today’s rules allow?

      The house may stay, but new work must conform. In the Ordinance 6906 text the city posted (the city says council approved it on March 17, 2026), alterations to a nonconforming structure must conform to applicable development regulations, and a value test can bring the whole site into compliance. I could not read the codified section, so I ask the city in writing before I draw a floor over a wall inside a yard.

      Which Bellevue permit does a second story addition need, and how long does it take?

      The city’s BR permit covers adding less than 3,000 square feet to a house. An addition greater than 3,000 square feet of new and/or replaced floor area goes under BS. For permits completed 2 November 2025 to 2 November 2026 the city’s report shows a median of 75 days for BR additions to existing structures and 189 for the seven major BS additions. The report does not say how it counts days.

      How much does a second story addition cost in Bellevue?

      I use a planning range for additions of $350 to $650 per square foot, not a quote. A 1,500 square foot second floor is 1,500 x 350 = $525,000 to 1,500 x 650 = $975,000, before design fees, permits, tax and contingency. About 1,154 square feet reaches $750,000 at the top of the range (750,000 / 650), and about 2,143 at the bottom.

      Do I need an architect for a second story addition, and do you build it?

      Washington’s architect licensing law exempts design work on a residential building of up to four dwelling units (RCW 18.08.410(5)), so state law does not require you to hire one for this design work. I design the addition and administer construction for you. I do not build.

      How much does the feasibility check cost?

      The first basic feasibility check is free and very quick, usually about a day. An in depth analysis is $1,500, takes 2 to 3 weeks and goes further. If you go ahead, I quote a fixed fee for design and permit, about $10,000 to $200,000 depending on scope.

      How long does design take before I can apply?

      Design to permit submission typically takes me 2 to 4 months. The city’s review time comes after that, and the report figures above show how long recent permits took.



      David Meade, AIA, NCARB
      Principal Architect, Piper Cole Architects · Kirkland, WA

      David Meade is a licensed architect (AIA, NCARB) who has worked as an architect since 1996, with three Masonry Excellence Awards for commercial projects and a residential practice on the Seattle Eastside. He has designed custom homes, additions, and ADUs in Kirkland, Bellevue, Redmond, and Seattle. Learn more about David →

      Kitchen with long granite island, striped bar stools and sliding doors to a lake view deck

      Next step

      Have a project in mind?

      Call David Meade directly, or send the address and a few lines about what you want. The first feasibility check is free and usually takes about a day.

      Free feasibility check

      Send the address and what you have in mind. David replies to you personally.

        What are you planning?
        Your details

        No obligation. Your details go to David only. See the privacy policy.

        Chat with David on WhatsApp