City of Redmond building permit fees for a $750,000 remodel

Redmond publishes its fee schedules, so on a seven-figure remodel you can do the arithmetic yourself. Here is the 2026 schedule worked at $750,000, what sits outside it, and what I could not confirm.

By David Meade, AIA, NCARBUpdated 22 October 202612 min read

On this page

    Key takeaways

    • On a $750,000 remodel that adds no floor area, the City of Redmond’s schedule effective February 1, 2026 gives a building permit fee of $8,828.71, plan review of $5,738.66 and a $796.48 fire fee. With the 4 percent surcharge and the $6.50 state fee the building line is $15,984.90, about 2.13 percent of the value.
    • Electrical, mechanical and plumbing are separate permits; on my assumed counts they add $2,733.91. Tree, shoreline, drainage and land use charges apply only if your lot triggers them. Impact fees do not apply to a remodel that adds no dwelling unit, by the city’s code.
    • In the Neighborhood Residential zone, a remodel that adds no floor area owes no affordable housing payment. Added floor area owes $15 per net new square foot in 2026 and $30 in 2027, set by the date of a complete application.
    • City fees are separate from my fixed fee for design and permit, about $10,000 to $200,000 depending on scope, and from construction cost.

    Short answer: on a $750,000 remodel that adds no floor area, Redmond’s building permit, plan review and fire fees come to $15,363.85, and $15,984.90 once the 4 percent technology surcharge and the $6.50 state fee are added. That is an estimate: the city’s schedule applied to $750,000. Trades, trees, drainage and land use fees come on top, depending on your lot.

    Piper Cole Architects is based in Kirkland. I design and administer construction, and I do not build. My fixed fee for design and permit, about $10,000 to $200,000 depending on scope, is a separate line from the city’s fees. Every figure below comes from a City of Redmond document I read on October 15, 2026. The $750,000 value, the trade counts and the 600 square foot addition are my assumptions. I found no fee estimator: the city’s residential permits page says to email the permit technicians, so none of this is a city estimate. Confirm every amount before you budget. See also my Redmond zoning guide and Redmond remodel architect page.

    How Redmond sets the building permit fee

    The city’s Development Services Fees page links separate 2026 schedules for residential building, electrical, mechanical, plumbing and fire fees, each effective February 1, 2026. The land use sheet says the next update takes effect February 1, 2027. The residential schedule gives four steps:

    1. Find the project value in the building permit fee table.
    2. Add plan review: 65 percent of the permit fee, plus any Fire, Planning and Public Works fees that apply.
    3. Add a 4 percent technology surcharge, which the schedule says is applied to the total permit fees.
    4. Add the $6.50 state building code surcharge.

    Plan review, planning, public works, fire and surcharge fees are collected at submittal; the permit fee, state fee, adjusted plan review and impact fees at issuance. The schedule does not split the surcharge, so I show one total. The bands that matter at this size:

    Value of construction Permit fee
    $100,000.01 to $500,000 $1,984.02 for the first $100,000 plus $11.20 for each additional $1,000 or fraction
    $500,000.01 to $1,000,000 $6,456.21 for the first $500,000 plus $9.49 for each additional $1,000 or fraction
    $1,000,000.01 and up $11,197.86 for the first $1,000,000 plus $7.29 for each additional $1,000 or fraction

    The bands do not join exactly: $500,000 gives $6,464.02 in the lower band against a $6,456.21 base in the next, and $1,000,000 gives $11,201.21 against $11,197.86. I report the table as printed. The state fee is $6.50 on each residential building permit under RCW 19.27.085. Paying by card adds 2.99 percent.

    I could not find the ordinance or resolution behind the 2026 building, trade, fire and land use amounts. The city’s 2025 and 2026 resolution lists show none amending development services fees, and council resolutions on the city’s user fee schedules say directors may raise fees administratively each year by up to the consumer price index. So for those amounts I cite the schedules and no ordinance.

    How Redmond values a remodel

    The building and trade schedules define valuation as the value of the work being performed, including materials and labor. The city’s building valuation data table prices new square footage; the one the fees page links is ICC’s August 2019 data, which says it is not intended for alterations or repairs. For a remodel the number is the value of the work, in practice your builder’s bid. For an addition, the table’s R-3 one and two family row for type VB reads $121.24 per square foot, so 600 square feet × $121.24 = $72,744.00, an illustration on a 2019 table. I found no page saying how reviewers test a remodel value they think is low, so bring the bid and ask the permit technicians in writing what they accept.

    Worked example: a $750,000 remodel

    Assumptions: one house, one dwelling unit, a remodel that adds no floor area, a $750,000 value the city accepts, regular plan review. The planning list has a Residential Addition line but none for a remodel, so I charge no planning or public works fee. The arithmetic:

    Step Where it comes from Arithmetic Amount
    1. Project value Assumed $750,000
    2. Building permit fee Residential schedule, $500,000.01 to $1,000,000 band $750,000 − $500,000 = $250,000, which is 250 thousands; $6,456.21 + (250 × $9.49) = $6,456.21 + $2,372.50 $8,828.71
    3. Plan review fee 65% of the permit fee $8,828.71 × 0.65 = $5,738.6615, rounded $5,738.66
    4. Fire fee Residential schedule, Fire, line that lists Remodel Flat $796.48
    5. Subtotal $8,828.71 + $5,738.66 + $796.48 $15,363.85
    6. Technology surcharge 4% of total permit fees $15,363.85 × 0.04 = $614.554, rounded $614.55
    7. State fee RCW 19.27.085 $6.50
    8. Building line $15,363.85 + $614.55 + $6.50 $15,984.90

    Two reads change the total. If the surcharge applies only to permit and plan review, it is $582.69 and the line is $15,953.04. If the project adds floor area, the $324.01 Residential Addition planning fee joins the subtotal: $15,687.86 + $627.51 + $6.50 = $16,321.87. The same method at other values:

    Project value Permit fee Plan review (65%) Building line with fire, surcharge, state fee Share of value
    $500,000 $6,464.02 $4,201.61 $11,927.09 2.39%
    $750,000 $8,828.71 $5,738.66 $15,984.90 2.13%
    $1,000,000 $11,201.21 $7,280.79 $20,056.12 2.01%
    $1,500,000 $14,842.86 $9,647.86 $26,305.19 1.75%

    For scale, my Kirkland, Bellevue and Seattle fee pages give $11,897.56, $14,919.50 and $13,885.40 at the same value, but each city builds its lines differently.

    Free feasibility check

    Planning a custom home or a remodel of $750,000 or more?

    Send me the address and a few lines about what you want. The first feasibility check is free and usually takes about a day.

    Electrical, mechanical and plumbing

    Each is a separate permit on its own 2026 schedule: electrical, mechanical and plumbing. Residential electrical is priced by the items you install, with no link to the value of the work. Each adds the 4 percent surcharge.

    Permit What the city charges Plan review, due at submittal
    Electrical Base $140.71. Circuits 0 to 3 $96.02, over 3 $192.03. Service $192.03. Subpanel $96.02. Low voltage and fire alarm $39.63 20% of the permit fee
    Mechanical Base $140.71. $48.25 per furnace or air handler, exhaust fan, or outdoor heat pump. Ductwork $38.60 per vent 25% of the permit fee, plus $105.04 planning plan review
    Plumbing Base $140.71. $48.55 per fixture. Water piping repair or replacement $97.08 per fixture 65% of the permit fee

    My assumed scope, not a quote: one altered service, one subpanel, more than three circuits and one low voltage line; one air handler, one outdoor heat pump and four exhaust fans; 12 plumbing fixtures. I read each base fee as charged once per permit on top of the items, and “circuits over 3” as a flat line. The schedules do not say, so confirm both.

    Permit Arithmetic With plan review and surcharge
    Electrical $140.71 + $192.03 + $96.02 + $192.03 + $39.63 = $660.42; plan review $132.08; surcharge $792.50 × 0.04 = $31.70 $824.20
    Mechanical $140.71 + (6 × $48.25) = $430.21; plan review $107.55; planning review $105.04; surcharge $642.80 × 0.04 = $25.71 $668.51
    Plumbing $140.71 + (12 × $48.55) = $723.31; plan review $470.15; surcharge $1,193.46 × 0.04 = $47.74 $1,241.20
    Trades together $2,733.91
    Building line plus trades $15,984.90 + $2,733.91 $18,718.81
    Bathroom with a floating cherry double vanity, white stone counter and clerestory windows
    Cannon Remodel, Piper Cole Architects. A bathroom with a floating cherry double vanity and clerestory windows. Redmond counts plumbing by fixture.

    The schedules list no energy code fee, so I add none.

    Trees, shoreline, drainage and the rest

    These sit outside the building and trade lines, and each applies only if your project triggers it. Amounts come from the 2026 development review schedule, the Development Engineering schedule and the fire fee schedule, all effective February 1, 2026, each with a 4 percent surcharge.

    Item What the city sets When it applies
    Tree removal permit Single family, no exception $208.36; exceptional review $570.91. Replacement tree $626.32 each, landmark $2,505.31 each Any significant tree, 6 inches across. The tree page asks for a preservation plan and arborist report under “all new development”; I could not confirm it reaches a remodel
    Shoreline Exemption permit: no fee. Substantial development permit, single family $16,303.30. Variance, single family $22,608.24 Lots on a regulated shoreline, such as Lake Sammamish. See my shoreline exemption guide
    Critical areas, SEPA, variance Critical area mitigation, single family $1,170.25. Geological hazard alteration $17,958.13 alone, $7,709.80 with another land use permit. SEPA review, single family $4,614.55. Variance, single family $19,347.23 Steep slopes, streams, wetlands. SEPA does not apply to categorically exempt proposals; I did not confirm when a remodel triggers it
    Clear and grade Plan review, single family $1,399.30; inspection, single family $1,023.23 Whether your remodel needs one is the city’s call. The city page says review generally takes 4 to 5 weeks
    Fire sprinkler, NFPA 13D Additions or modifications $550.27; new system, 1 to 40 heads $1,129.24 Only if a residential system is required or altered

    The Development Engineering sheet also lists a citywide stormwater capital facilities charge of $2,310 per 2,000 square feet of impervious area, due at permit issuance. Ordinance 3235, effective January 1, 2026, sets that amount and counts units “proposed to be created by the development,” so I read it as new impervious area, which an addition may add and a remodel inside the walls does not. I do not price it. For lakefront lots see my waterfront remodel guide.

    The affordable housing payment on added floor area

    This is not a building permit fee. In the Neighborhood Residential zone, developments of seven or fewer dwelling units owe a payment in lieu on net new square feet unless one on-site affordable unit is provided. The city’s schedule, effective June 28, 2025, sets a $30 baseline per square foot, charged at 25 percent in 2025, 50 percent in 2026 ($15) and all of it in 2027 ($30). Its own example says a remodel with no change in total square feet owes nothing. The city’s housing page says additions count, and payment is due before the sheetrock nailing inspection can be scheduled.

    A 600 square foot addition: 600 × $15 = $9,000 at the 2026 rate, or 600 × $30 = $18,000 at the 2027 rate. Under Resolution 1607, the rate follows the calendar year in which the city receives a complete application, as long as the building permit issues within one year of that date. My reading: a complete application received by December 31, 2026 keeps the $15 rate, and one received in January 2027 pays $30. A text search of Ordinance 3269 (September 2026) found no change to these payment rules, which matches my zoning guide.

    Impact fees: do they apply to a remodel?

    Redmond charges school, fire, park and transportation impact fees under chapter 3.10 of its municipal code, and the city’s 2026 schedule prices them per housing unit for a house. For a remodel the short answer is that they do not apply if the work adds no dwelling unit. Section 3.10.060(A)(2) exempts the alteration or remodeling of an existing building from all impact fees if no dwelling unit is added, the work creates no additional demand on fire, park, school or transportation systems, and no change in use is proposed.

    I read that in the city’s own copy of chapter 3.10, current through Ordinance 3171 of July 2, 2024; the city’s code site blocked my reader, so I did not check its current text. The later changes to chapter 3.10 on the city’s ordinance lists are Ordinances 3187 (November 2024), 3217 (June 2025) and 3240 (December 2025). I checked all three: 3187 repeats the remodel exemption in the same words, and 3217 and 3240 amend other sections.

    By the text, a remodel inside the walls that adds no unit owes none. An addition with no new unit is less clear, because the exemption also tests “additional demand” and I cannot tell how the city applies it, so ask in writing.

    The cliff is a new unit. One new single family unit on the 2026 schedule is $7,277.00 school, $148.78 fire, $6,914.63 park and $10,107.51 transportation, $24,447.92 outside the city’s centers, before a $65 school administration fee. A one-for-one replacement house may be exempt under RMC 3.10.060.A.2 if it adds no dwelling unit and no additional demand, or credited for the old house under RMC 3.10.130.A.4. Raise either at building permit application and ask the city in writing whether a larger house adds demand. That is one reason to read when a remodel counts as a new house.

    Review times the city publishes

    The city publishes no review goal for a residential building permit. Its Outcome Management Report for 2025 shows completed Residential permits at a median of 39 (167 of 369 received), demolition at 32 and tree removal at 12. The report prints no unit, and a column headed Over 120 Days suggests days. It does not separate new houses from remodels and counts only permits completed in the year, so a median can understate the slower ones. For civil permits the city says clearing and grading review generally takes 4 to 5 weeks, and rough grade review 8 to 10 weeks. On my side, design to permit submission typically takes 2 to 4 months, before the city’s clock starts. My remodel timeline guide covers the cities that publish one.

    What I could not confirm

    • The ordinance or resolution behind the 2026 schedules.
    • The current text of the impact fee exemptions on the city’s code site, which blocked my reader.
    • How a reviewer tests a low remodel value.
    • Whether the surcharge applies to every line, whether a remodel carries a planning fee or the fire fee (the Fire Department’s own schedule lists additions but not remodels on that $796.48 line), and whether the trade base fees and “circuits over 3” work as I read them.
    • When SEPA, clear and grade and the tree plan apply to a house remodel, and whether an addition owes the stormwater charge.

    City fees, my fee and construction cost

    A remodel budget has three separate lines. The city line below leaves out trees, drainage, land use and the payment on added floor area.

    Line What sets it Planning figure
    Construction The builder’s bid on finished drawings Whole house renovation $300 to $550 per sq ft; additions $350 to $650 per sq ft (planning ranges)
    Design and permit documents My fixed fee, set by project budget and location About $10,000 to $200,000 depending on scope
    City permit fees The city’s schedules applied to the value of the work Redmond building line on $750,000: $15,984.90; with the sample trades: $18,718.81; plus the items above

    Your builder’s contract should say in writing whether permit fees sit inside the bid or outside it. The wider budget is in my guide to planning a million dollar remodel.

    Before you budget the permits

    Get a free first feasibility check

    Send me the address, the rough size of the house and what you want to change. In about a day I will tell you which Redmond fees and reviews your lot is likely to trigger, and whether the $1,500 in-depth analysis, 2 to 3 weeks, is worth doing next. I have been an architect since 1996, an AIA member since 1992 and an NCARB member since 1996.

    Questions

    How much are building permit fees in Redmond for a remodel?

    They follow the value of the work. Under the City of Redmond’s schedule effective February 1, 2026, a $750,000 remodel that adds no floor area pays a $8,828.71 building permit fee, a $5,738.66 plan review fee and a $796.48 fire fee, plus a 4 percent technology surcharge ($614.55) and a $6.50 state fee, for $15,984.90. A $500,000 project comes to $11,927.09 by the same method and a $1,000,000 project to $20,056.12. Electrical, mechanical and plumbing permits, trees, drainage and land use fees are extra.

    How does the City of Redmond calculate building permit fees?

    The city finds the project value in its building permit fee table, which gives a base plus a rate per $1,000 for each band. It adds plan review at 65 percent of the permit fee and any fire, planning and public works fees, then a 4 percent technology surcharge on the total, then the $6.50 state fee. Value means the value of the work being performed, including materials and labor.

    Where is the City of Redmond permit fee schedule?

    On the city’s Development Services Fees page at redmond.gov/504, which links 2026 PDFs for residential building, electrical, mechanical, plumbing, miscellaneous and fire fees, a land use development review schedule, an impact fee schedule and the Neighborhood Residential payment in lieu schedule. Each building schedule is marked effective February 1, 2026. The city says to contact a permit technician for an estimate.

    What are Redmond electrical permit fees for a remodel?

    Redmond’s residential electrical schedule, effective February 1, 2026, has a $140.71 base fee, $96.02 for 0 to 3 new or altered circuits and $192.03 for more than 3, $192.03 for a new, altered or added service, $96.02 for a subpanel and $39.63 for low voltage and fire alarm, plus 20 percent plan review and a 4 percent surcharge. On my sample scope that is $824.20.

    Do Redmond impact fees apply to a remodel?

    By the city’s code, a remodel of an existing building is exempt from all impact fees if it adds no dwelling unit, creates no additional demand on fire, park, school or transportation systems and changes no use. I read that in the city’s copy of the code dated July 2024, so confirm with the city, especially for an addition. A new dwelling unit pays about $24,400 in the four impact fees on the 2026 schedule. A one-for-one replacement house may be exempt or credited for the old house, so raise it at building permit application.

    Will I owe Redmond’s affordable housing fee on a remodel?

    Only on net new floor area. The city’s schedule for the Neighborhood Residential zone charges $15 per net new square foot in 2026 and $30 in 2027, and says a remodel with no change in total square feet counts no square feet. A 600 square foot addition is $9,000 at the 2026 rate and $18,000 at the 2027 rate. The rate follows the date the city receives a complete application, if the permit issues within a year.

    How long does Redmond take to review a remodel permit?

    The city publishes no review goal for a residential building permit. Its 2025 Outcome Management Report shows a median of 39 for completed Residential permits, without separating new houses from remodels. The city says clearing and grading review generally takes 4 to 5 weeks, which applies only to projects that need that permit. Ask the Development Services Center for a current estimate for your scope.

    Are permit fees part of the architect’s fee or the construction cost?

    Neither. City permit fees are a third line, set by the city’s schedules and the value of the work. I quote a fixed fee for design and permit, set by project budget and location, about $10,000 to $200,000 depending on scope. Construction is the builder’s bid; my planning ranges are $300 to $550 per square foot for a whole house renovation and $350 to $650 for additions. Ask your builder whether permit fees are in or out of the bid.


    Authoritative sources

    Regulatory requirements referenced in this guide are set by the official agencies below. Rules change, always confirm current requirements with the source:

    David Meade, AIA, NCARB
    Principal Architect, Piper Cole Architects · Kirkland, WA

    David Meade is a licensed architect (AIA, NCARB) who has worked as an architect since 1996, with three Masonry Excellence Awards for commercial projects. Learn more about David →

    Kitchen with cherry cabinets, marble counters, island seating, skylight and slate floor

    Next step

    Have a project in mind?

    Call David Meade directly, or send the address and a few lines about what you want. The first feasibility check is free and usually takes about a day.

    Free feasibility check

    Send the address and what you have in mind. David replies to you personally.

      What are you planning?
      Your details

      No obligation. Your details go to David only. See the privacy policy.

      Chat with David on WhatsApp