Key takeaways
- A correction notice means SDCI finished its reviews and has items to fix or explain. You cannot respond until every review in the cycle is complete and your record reads Corrections Required.
- You answer each comment inside the marked-up plan set SDCI sends, cloud your drawing changes, and upload two sets through Make Changes in the Seattle Services Portal: the response set and a clean updated plan set.
- SDCI’s published target for reviewing corrected plans is two weeks. Its other times are initial review targets or City-control figures, and they do not all agree, so treat them as targets.
- SDCI does not rank causes of extra cycles. Its pages name these problems: missing sheets or responses, single sheets uploaded alone, wrong files, an unfinished upload and an insufficient response.
Short answer: in Seattle, a correction notice means the city reviewers want something changed or explained before they will issue the permit. When your record shows Corrections Required, you respond to every item in the plan set SDCI gives you, describe each change or cite the code or documentation for one you did not make, and upload the response set with a clean updated set. SDCI says it reviews corrected plans on a two week target, and a permit can go through more than one round.
Piper Cole designs and administers construction; I do not build. This page covers a house, addition or remodel permit. The sources for this page were read on 9 November 2026. SDCI changes its pages and portal, so follow the notice you received and confirm anything that differs.
What a correction notice is
SDCI says that multiple teams at the City review each application, and that it can take several rounds of back and forth to finish. Each round works the same way: the City reviews and issues a correction notice, you update your plans and resubmit, and the loop repeats until the issues are resolved. SDCI’s performance page says each additional cycle improves application quality but takes time from both the City and the applicant.
In your record on the Seattle Services Portal, the notice shows up under the Attachments tab. SDCI’s help article names two document types to look for:
- Correction Letter: one for each individual reviewer’s comments.
- Plan Set Consolidated Summary Report: all comments, each linked to its place in the plan set.
The Attachments tab is view only; SDCI warns that your reviewer will not receive anything you attach there. The record status tells you where you are:
| Status | What SDCI’s Help Center says it means | What it means for you |
|---|---|---|
| Reviews In Process | SDCI has started at least one review, but all reviews are not finished. | Nothing to submit yet. |
| Corrections Required | SDCI is waiting for corrections from the applicant to review again. | This is the status in which you respond. |
| Corrections Submitted | The applicant has submitted corrections and SDCI has not started evaluating them. | Your upload went through; the corrected review is queued. |
SDCI assigns reviews in the order they are submitted, based on review resources. Drainage is one review type; see Seattle’s stormwater code.
How the review cycle runs
- Intake. SDCI accepts the application.
- Reviews. SDCI says it notifies the project’s primary contact when all reviews in the cycle are complete.
- Corrections Required. Only now can you respond, upload or submit any correction responses.
- You respond in the plan set and upload through the portal.
- Another review. If items remain, the loop starts again.
SDCI’s permit pages say a project may require multiple correction rounds. For how review fits into a whole project, see how long a whole house remodel takes.
How to respond, step by step
These steps follow SDCI’s “How to Respond to Review Comments” page and its Help Center article “How to View and Respond to Corrections.”
- Wait for every review to finish. The project status must be Corrections Required.
- Open the notice. Log in, go to My Records, open the record and use the Attachments tab to find the Correction Letter and the Plan Set Consolidated Summary Report.
- Answer each item in the plan set. SDCI says to use the Reply function in Bluebeam or the Comment panel in Adobe Acrobat on the Consolidated Summary Report Plan Set. Describe the change you made, or if you did not make a requested change, give a code citation or documentation that explains why.
- Correct the drawings. Cloud or circle every change. You may add new sheets. Combine all sheets into a single PDF; only photographs may be uploaded as JPG files. SDCI says plans are not accepted for review if they are not oriented correctly (landscape), are on the wrong sheet size, or have missing sheets or responses.
- Upload with Make Changes. From the My Records page choose Make Changes, then Upload Documents. If you do not see Upload Documents, the record is not at a point where corrections are required.
- Upload both sets. A Plan Set that carries the drawing changes, and a Correction Response Plan Set (for construction projects; the Land Use version is for master use permits) that carries your responses. With no Consolidated Summary Report, SDCI says to upload individual Correction Response documents for each reviewer.
- Finish the upload. Click Continue Application until the Thank You screen appears, or SDCI says your plans will not be uploaded.
SDCI points to Tip 106, General Standards for Plans and Drawings, for plan requirements. Our renovation permit checklist covers the first submittal.

Free feasibility check
Planning a custom home or a remodel of $750,000 or more?
Send me the address and a few lines about what you want. The first feasibility check is free and usually takes about a day.
Keeping your responses organized
SDCI asks for a response to every cited item, in the plan set it sent you. This table sets out what SDCI says to write in each situation.
| If | What SDCI says to do | Where it goes |
|---|---|---|
| You made the change | Describe the change you made, and cloud or circle it on the sheet. | Reply on the comment in the Consolidated Summary Report Plan Set; the change itself appears in the clean Plan Set. |
| You did not make the change | Give a code citation or documentation that explains why. | Reply on the same comment. |
| You changed something no one asked about | Describe voluntary changes in your response letter. | Response letter, with the response set. |
| Several people answer parts of the notice | Consolidate all responses among designers, architects, engineers and owners onto the one Consolidated Summary Report Plan Set. | The single response set. |
| The proposal changed significantly | Complete the Permit Correction Response Letter for significant changes to development standards. | Upload to your record. SDCI says it does not replace the response plan set. |
My suggestion, not an SDCI requirement: keep a running list with one line per comment, showing the sheet, the response and who wrote it, so nothing is missed when consultants answer parts of the notice. See when a remodel needs a structural engineer.
Review times SDCI prints
Seattle’s pages give several review times that measure different things and do not all agree. Each is listed with its page; all were read on 9 November 2026.
| SDCI page | What it prints | Date shown |
|---|---|---|
| How to Respond to Review Comments | The target review time for corrected plans is two weeks. | No date shown |
| Construction Permit Performance | Goal of 30 calendar days in City control for single family addition or alteration, for 75 percent of reviews, effective October 1, 2025. Current 75th percentile shown: 64 days. The total an applicant experiences is roughly twice the City days. | Goal date given; no as-of date for the 64 |
| Construction Permit Performance, Middle Housing | Goal of 60 days; current 75th percentile 117 days. SDCI says this category includes single family homes. | As above |
| Construction Permit pages, addition or alteration and new single family | Initial review of simple applications in two to three weeks and complex permits in eight weeks (addition or alteration); about 2 weeks for a typical new home and about 8 if large or structurally complex (new single family). | No date shown |
| Guide to Initial Plan Review Categories | Targets for all initial reviews: 2 to 4 weeks for small single family additions and alterations; 4 to 8 weeks (an internal target only) for larger ones; 8 to 12 weeks for complex projects. | Updated 2/1/24 |
| Help Center FAQ on target due dates | Targets of 2 business days for Full projects, 2 to 4 weeks for Full + and 8 to 12 weeks for Full Complex; it says Full and Full + include additions and alterations. It adds that targets may be missed when volume is high. | No date shown |
The performance page counts calendar days in City control and leaves out time when the application is with you. The other pages give initial review targets, not the time a correction round takes, so the two week corrected plans target is the only figure here that speaks to a correction round. For the legal clock, Seattle’s 2021 Residential Code, section R105.7.2, gives the building official 120 days after notice that the application is complete to approve, condition or deny, and it excludes the periods in which the applicant has been asked to correct plans. Our PACT guide sets that clock beside the performance goals.
Who does what
SDCI notifies the project’s primary contact, and its help pages say the Make Changes button does not appear unless you are a contact on the record. When someone is added as an Owner, Owner’s Agent or Financially Responsible Party, SDCI says to make sure the contact names and types match the Statement of Financial Responsibility form to avoid a rejected change. Settle before you apply who the primary contact is and who can upload.
SDCI’s instruction is that one plan set gathers the responses of all designers, architects, engineers and owners. In practice the design team changes sheets and cites code, and you decide anything that changes scope or budget. Before you sign a contract, ask your architect or designer who prepares each response and who uploads it; SDCI says it cannot rename or delete uploaded files for you.
What can delay a corrected review
SDCI does not publish a ranked list of causes. Its pages name these problems:
- Incomplete response sets. Plans are not accepted for review if they are missing sheets or responses, or are not oriented correctly or are on the wrong sheet size.
- Single sheets. SDCI says it will not review individual sheets that respond to the corrections; a requested site plan must arrive as part of a complete plan set.
- Wrong or misnamed uploads. SDCI says it cannot correct document names or delete incorrect documents for you.
- An unfinished upload. If you do not reach the Thank You screen, the plans are not uploaded.
- Not following the instructions. SDCI says it may be delayed in starting the corrected review, which can delay your permit, and that it may charge a penalty fee.
- Significant changes after you applied. SDCI asks for a response letter, which lets staff confirm whether a land use permit restarts its clock or whether additional construction permit fees apply.
- A fee for insufficient responses. The 2026 Fee Subtitle (SMC 22.900D.010.J) says that after written notice, a Correction Fee of two times the SDCI base fee may be charged for each additional correction cycle required because of an insufficient response from the applicant.
SDCI’s page for a new single family house also says timing depends on how many corrections you need and how quickly and completely you respond. Changes after the permit issues are a separate process: SDCI’s revision page says to talk with your building inspector first.
If you disagree with a comment
SDCI has a process for a disagreement about how staff apply the code to your project. You still answer every comment in the plan set, with a code citation or documentation where you do not make a change. The process has three steps:
- A supervisor. SDCI lists supervisors by type of review, such as zoning, drainage, geotechnical, energy and mechanical, and structural. It prefers email and says the supervisor will respond within 24 hours.
- A manager. If you still disagree, you can ask in writing for a review by the appropriate manager.
- The Director. If you are still not satisfied, SDCI lists directors to contact.
If your house is on the Eastside
Seattle’s steps do not carry across city lines. What was read on 9 November 2026:
- Kirkland. The city’s Time to Review Goals, last updated 9.15.2026, list single family addition or alteration, regular review: 4 weeks for first review and 10 business days for a pre-issuance revision. The page says actual times may vary and that third-party structural review or SEPA adds time. See the Kirkland permit guide.
- Bellevue. The city says it may ask for additional information or revisions if plans do not align with code, and that you submit revised plans the same way you applied, by uploading through your MyBuildingPermit plan review dashboard. Its Processing Days report for permits completed 11/2/2025 to 11/2/2026 shows a median of 13 days (average 34) for single family remodel plan review, 75 (153) for single family additions to an existing structure and 176 (283) for single family new structures. The report does not say how days are counted, and it refreshes. See the Bellevue permit guide.
- Other cities. The correction pages for Mercer Island, Redmond, Issaquah and Sammamish were not read for this page. Start with the city’s own permit page; see our Mercer Island guide.

Where I would start
- Check the record status. Do not respond until it reads Corrections Required.
- Download both the Correction Letter and the Plan Set Consolidated Summary Report from the Attachments tab.
- List every comment, who owns the answer and which sheets it touches.
- Answer in the plan set, cloud changes and gather consultant responses onto the one set.
- Upload through Make Changes, click through to the Thank You screen and confirm the record shows Corrections Submitted.
Still before submittal? See the pre-application conference guide and the Seattle permit guide.
Before the next cycle
Talk through your Seattle permit with me
Send me the address and what you want to build. The first basic feasibility check is free and usually takes about a day; the in-depth analysis is $1,500 and takes 2 to 3 weeks.
Questions
What is a correction notice on a Seattle building permit?
It is SDCI’s notice, after a review cycle, that its reviewers have items for you to change or explain before the permit can issue. It reaches you in the Seattle Services Portal as a Correction Letter for each reviewer and a Plan Set Consolidated Summary Report that links each comment to the plan set. SDCI says the process repeats until the issues are resolved.
How do I respond to SDCI plan review comments?
Wait until every review is complete and the record shows Corrections Required. Answer each item in the Consolidated Summary Report Plan Set using the Reply function in Bluebeam or the Comment panel in Adobe Acrobat. Cloud your drawing changes, combine the sheets into one PDF, and upload the response set and a clean updated plan set through Make Changes, clicking Continue Application until the Thank You screen appears.
How long does SDCI take to review my corrections?
SDCI’s response page says the target review time for corrected plans is two weeks. That is a target. SDCI’s other published times are initial review targets, and its performance page puts the total an applicant experiences at roughly twice the calendar days in City control.
Can I upload only the sheets I changed?
No. SDCI says to always upload a complete plan set and that it will not review individual sheets that only respond to the requested corrections. Its example is a requested site plan: if you upload it alone, SDCI will not review it, so the corrected site plan has to be part of a plan set.
What if I disagree with a plan review comment?
Answer the comment in the plan set with a code citation or documentation, as SDCI asks when you do not make a requested change. For a disagreement about how SDCI applies the code, SDCI’s process starts with the supervisor for that type of review, then a manager, then a director. The page says a supervisor will respond within 24 hours.
Why do I not see Upload Documents or Make Changes?
SDCI says that if you do not see Upload Documents, the record is not at a point where corrections are required. All reviews must be complete and the status must read Corrections Required. The Make Changes button also does not appear unless you are a contact on the record.
Can SDCI charge me for extra correction cycles?
SDCI says it may charge a penalty fee if you do not follow its response instructions. The 2026 Fee Subtitle, SMC 22.900D.010.J, also says that after written notice a Correction Fee of two times the SDCI base fee may be charged for each additional correction cycle required because of an insufficient response from the applicant. Check the current Fee Subtitle for how SDCI applies it.
How many rounds of corrections should I expect?
SDCI says your project may require multiple correction rounds, and its performance page says most permits typically involve several review cycles. The SDCI pages used for this guide do not print an average number of cycles for a house, so any figure you hear is an estimate. SDCI says timing depends on how many corrections you need and how quickly and completely you respond.
Do Eastside cities handle corrections the same way?
No. Each city sets its own portal, review goals and revision process. Kirkland’s goals, updated 9.15.2026, list a 4 week first review and 10 business days for a pre-issuance revision for a single family addition or alteration, and Bellevue takes revised plans through its MyBuildingPermit plan review dashboard. Check your own city’s page.