Short answer: on a $1,800,000 new custom home in Kirkland on a sloped, treed lot, the consultants and the city come to roughly $51,000 to $100,000 before construction starts, and none of it is the builder or me. The city side is $25,798.95 by my arithmetic from Kirkland’s published 2026 schedule, worked below. The consultants are the surveyor, the geotechnical engineer, the structural engineer, the arborist, the civil engineer and the energy consultant, plus a land use attorney where needed. My fee is separate: a fixed fee for design and permit, about $10,000 to $200,000 by scope and location, never a percentage of construction. On a flat lot outside a critical area the list costs about half. Piper Cole does not build.
Key takeaways
- Six consultants are normal on a seven figure house. You sign the contract with most of them; I scope, sequence and coordinate them.
- The trigger is a site fact: a slope, a critical area, a shoreline, a significant tree, a second storey, a new footprint, a driveway in the right of way.
- Cities bill the third party reviewer through to you. Seattle charges the contract cost plus staff hours, 75 percent due before award (Fee Subtitle 22.900D.145.E). Kirkland lists its pre-submittal conference for an owner’s own single family project at no fee.
How to read the fees here. City fees are quoted from the published 2026 schedules linked beside them. Nobody publishes consultant fees, so every consultant figure is a labelled estimate [EST]. Basis: written proposals I have seen as the owner’s architect on Seattle and Eastside houses in 2025 and 2026. Not quotes. Get each in writing.
I read every schedule linked here on 25 November 2026, and they change on 1 January in most of these cities, so confirm each figure. Washington law does not require an architect for a house: RCW 18.08.410 exempts residential buildings of up to four dwelling units.
Who you pay, and who I coordinate
These fees do not come through me on most projects. You hold the agreement and pay. My part is deciding what each one must produce, ordering them correctly, and building the results into the drawings and the plan review responses, inside my fixed fee. The structural engineer varies: sometimes inside the architect’s agreement, sometimes contracted directly. Ask any architect you interview, me included, in writing.
| Consultant | Contract held by | My part |
|---|---|---|
| Land surveyor | You | Scope it, set the base drawing, test the envelope |
| Geotechnical engineer | You | Set the questions, pass results to structural |
| Structural engineer | Either, ask first | Coordinate framing, carry city comments |
| Arborist | You | Fit tree protection before the footprint is fixed |
| Civil engineer | You | Coordinate grading and drainage with the design |
| Energy consultant | Often inside my scope | Choose the compliance path early |
| Land use attorney | You | Supply drawings and the code reading |
| Architect (me) | You | Design and permit, fixed fee $10,000 to $200,000 |

The land surveyor
What you get. A boundary survey fixes the lot lines and corners. A topographic survey fixes elevations, structures, utilities and trees. Both are land surveying under RCW 18.43.020(7), so a Washington licensed professional land surveyor signs and seals them. Check the licence on the state’s licence lookup.
When, and what triggers it. First, before I draw. Every setback, coverage calculation and floor elevation sits on it. Triggered by any new footprint, any addition near a setback, any slope, and any city asking for a site plan to scale, which at this size is all of them. Bellevue wants one under five years old.
Cost. $4,000 to $9,000 [EST] combined, toward the top on a large, wooded or steeply sloped lot. If it must be recorded, King County’s recorder lists $303.50 for the first page of all other documents plus $1 per page after (King County Recorder); plats have their own schedule.
The geotechnical engineer
What you get. Subsurface conditions with design recommendations: bearing capacity, foundation type, drainage, slope setbacks, and the special inspections the city will require. In Seattle, Director’s Rule 5-2016 has a Washington licensed Professional Engineer (Civil) with at least four years of experience stamp it.
When, and what triggers it. Second, after the topographic survey and before the structural engineer sizes anything. Out of order, you pay the structural engineer twice. Triggered by a steep slope, a potential or known slide area, liquefaction, landfill or peat settlement prone ground, and in several cities any new foundation on a slope. My survey and geotechnical guide names the page that decides.
Cost. $5,000 to $12,000 [EST] with borings on a slope; monitoring wells or a slope stability analysis push it higher. Then the city bills you for reading it. Seattle’s Fee Subtitle 22.900D.145.E sets third party review at the contract cost to the Department plus staff hours at the SDCI hourly rate, 75 percent of the estimate due before award (2026 Fee Subtitle). Mercer Island charges $691 for single family geotechnical review plus actual cost of peer review, and Medina’s Critical Areas Review is $135.00 plus consultant costs.
Free feasibility check
Planning a custom home or a remodel of $750,000 or more?
Send me the address and a few lines about what you want. The first feasibility check is free and usually takes about a day.
The structural engineer
What you get. Calculations, stamped structural sheets and responses to the city’s structural comments. On a new house or second storey the engineer sizes the lateral system to the geotechnical recommendations.
When, and what triggers it. Third, in design development, once the geotechnical report is in hand and the framing will not move. Triggered by a second storey, a new footprint, removing load bearing support, a long span, a cantilever, a retaining wall, or a foundation on a slope.
Cost. $8,000 to $25,000 [EST] for a whole house remodel or new custom home, lower for a single addition. Ask whether site visits, comment responses and revisions are inside the fee or billed hourly: that is where proposals differ most. My structural engineer guide sets out what to ask for.
The arborist
What you get. A tree inventory with species, trunk size and condition, plus a protection plan showing what stays, which root zones must be fenced, and how close the excavation may come.
When, and what triggers it. Early, in schematic design, because a retained tree moves the footprint, and a footprint that moves after the engineer starts costs money. Triggered by a significant or exceptional tree on or beside the work, any clearing, and in some cities any permit on a treed lot.
Cost. $1,500 to $5,000 [EST], higher with many trees, a critical area, or a removal that needs justifying. The city’s arborist then reviews yours and charges: Mercer Island lists $427 for arborist review of a construction permit (Mercer Island 2026 schedule), Medina $360.00 per tree for a Hazard Tree Evaluation (Resolution 460), Seattle $551 an hour.
The civil engineer
What you get. Grading and drainage design, stormwater calculations, erosion control, and the right of way and driveway work that public works reviews separately.
When, and what triggers it. Alongside design development, because the finished floor elevation and the driveway slope are one decision. Triggered by crossing a city’s land disturbance or impervious surface threshold, a slope, a new driveway, a detention or infiltration requirement, or work in the right of way. In Kirkland it lands in the clearing and grading permit and a separate public works fee schedule.
Cost. $6,000 to $20,000 [EST] including the resubmittals that normally follow. A detention vault or a shared private road pushes it past that.
The energy consultant
What you get. Washington State Energy Code compliance documentation: the compliance path, credit selections, envelope and mechanical calculations, sometimes performance modelling. The current edition is the 2021 code, effective 15 March 2024, and local jurisdictions enforce it (SBCC energy code page).
When, and what triggers it. In design development. Picking the path late is a common cause of redesign at permit stage, because the credits change windows, insulation depth and the heating system. Any new conditioned floor area and most whole house remodels need it; the only question is whether an outside consultant prepares it or it sits inside my scope, as it often does.
Cost. $1,000 to $3,000 [EST] where a separate consultant prepares it, more with performance modelling. Kirkland charges on top: its energy code compliance fee is $101.00 plus $0.01 per square foot of heated, cooled or artificially illuminated space (Kirkland Building Services Fees).
The land use attorney, where needed
What you get, and when. An opinion on a nonconforming structure, a vested right, an easement, a plat condition or a covenant; representation at a hearing; or the drafting behind a variance or reasonable use exception. Needed before you buy, or as soon as a discretionary approval appears, never after a denial. Triggered by a variance, a reasonable use exception, a shoreline variance, an appeal, a disputed boundary, or a lot whose buildability turns on how a city reads its code. Most houses never need one.
Cost. I do not quote legal fees. What I can show is the published city fee that comes with the approval an attorney is usually there for. Mercer Island’s Reasonable Use Exception carries a 115 hour minimum at its 2026 staff rate of $182.00 an hour, so $20,930, plus peer review at cost; its Variance has a 65 hour minimum, so $11,830. Seattle’s Variance is $6,858.75 at intake (2026 Land Use Application Fees).
The city’s own fees before construction
These are published, so they are the one part of the number you can check yourself today. Seattle adds a technology fee of five percent (Fee Subtitle 22.900A.100) and Kirkland 3.5 percent, so these are before surcharges.
| City fee, 2026 | What it costs | Source read 25 November 2026 |
|---|---|---|
| Seattle rates and pre-application | Base fee $292. Other hourly fees $292. Land use review $551 an hour. A conference not required by code is 1.5 x base, so $438. Pre-application site inspection 3/4 hour, $219. | 22.900B.010, 22.900D.010.I, Table D-SR |
| Seattle geotechnical and critical areas | Third party geotechnical or shoring review: contract cost plus staff hours at $292, 75 percent due before award. Exemption review 1/2 hour, so $146, charged whatever the outcome. Critical areas Exception or Variance $6,858.75. | 22.900D.145, Land Use Fees |
| Kirkland pre-submittal and plan review | Pre-submittal Tier 1, an owner’s own single family project: no fee. Tier 2 $1,258.00, Tier 3 $2,892.00. Plan review 65 percent of the permit fee. Outside consultants at actual cost. Hourly $179.00. | Building Services Fees |
| Mercer Island critical area, geotech, arborist | Pre-application Type 1 $1,092, Type 2 $2,184. Critical Area Review Type 1 $1,456, Type 2 $3,640, plus peer review at cost. Geotechnical review, single family, $691. Arborist review $427. SEPA $1,456. Staff rate $182.00. | 2026 Fee Schedule |
| Medina site plan, critical areas, SEPA | Site Plan Review $1,150.00 plus consultant fees. Critical Areas Review $135.00 plus consultant costs. SEPA threshold determination $700.00 plus consultant fee. Building official hourly $71.16. | Resolution 460 |
Bellevue bills deposit permits monthly for hours worked at its stated hourly rate, and publishes $145 an hour for building inspection outside normal hours (permit fees, inspection fees); its full 2026 descriptions sit in an ordinance behind a bot check I did not bypass. For the permit itself, see my fee pages for Seattle, Kirkland and Mercer Island.
A worked example: a Kirkland custom home
Hypothetical lot, not a real property and not a client’s: a Kirkland lot with a slope and six significant trees. A new custom home, 4,000 square feet of heated space at $450 per square foot, so 4,000 x 450 = $1,800,000 of construction, inside the $400 to $900 planning range I use for new custom homes. About 800 cubic yards of grading, no critical area determination, no variance.
| Line | Basis | Arithmetic | Amount |
|---|---|---|---|
| Boundary and topographic survey | [EST] | Sloped, treed lot | $4,000 to $9,000 |
| Geotechnical report | [EST] | Borings on a slope | $5,000 to $12,000 |
| Structural engineer | [EST] | New custom home | $8,000 to $25,000 |
| Arborist report and protection plan | [EST] | Six trees | $1,500 to $5,000 |
| Civil engineer | [EST] | Grading and drainage | $6,000 to $20,000 |
| Energy consultant | [EST] | If not in my scope | $1,000 to $3,000 |
| Land use attorney | Not needed here | No variance | $0 |
| Consultants, subtotal | Estimates added | Low and high | $25,500 to $74,000 |
| Kirkland building permit fee | KMC Table 3 | 9,837 + (800 x 6.16) | $14,765.00 |
| Kirkland plan review, at submittal | 65 percent of permit fee | 14,765 x 0.65 | $9,597.25 |
| Kirkland clearing and grading | KMC Tables 11, 12 | 121 + 121 + (7 x 25.68) | $421.76 |
| Kirkland energy code compliance | $101 plus $0.01 per sq ft | 101 + (4,000 x 0.01) | $141.00 |
| State Building Code Council surcharge | Residential, first unit | Flat | $6.50 |
| Kirkland technology fee | 3.5 percent of those fees | 0.035 x 24,784.01 | $867.44 |
| Kirkland pre-submittal conference | Tier 1, owner’s own project | No fee | $0.00 |
| City of Kirkland, subtotal | Published 2026 schedule | Rows above | $25,798.95 |
| Total before construction, before my fee | Consultants plus city | 25,500 + 25,799 and 74,000 + 25,799 | about $51,300 to $99,800 |
| My fee, design and permit | Fixed fee by budget and location | Not a percentage | $10,000 to $200,000 |
Two caveats. Kirkland assesses fire and public works fees separately and they are not in that subtotal, so the city line is a floor. And I read the 3.5 percent technology fee as covering the permit, plan review and grading fees: 14,765 + 9,597.25 + 421.76 = $24,784.01, x 0.035 = $867.44.
Why your number is probably smaller
That range is the loaded case: a slope, trees, grading and a new footprint. Most projects do not trigger all six consultants, and this page would be dishonest if it let you think so.
- A flat lot outside a critical area drops the geotechnical report and most of the civil engineering, taking the consultant subtotal to roughly $13,000 to $14,000 [EST] at the low end. An interior remodel can drop the survey and arborist too.
- These are one time costs against a seven figure build. The high end here is 5.5 percent of the $1,800,000 budget: 99,800 / 1,800,000 = 0.055. A foundation redesigned because the geotechnical report arrived late costs more than the report did.
- Sequence beats shopping. Survey, geotechnical report, structural: the right order saves more than the cheapest proposal.
How it works with me
The first basic feasibility check is free and very quick, usually about a day. Send the address and what you are considering, and I will tell you which consultants your lot is likely to trigger and which it is not. An in depth analysis is $1,500 and takes 2 to 3 weeks.
- Design to permit submission. Typically 2 to 4 months, for a fixed fee set by project budget and location, about $10,000 to $200,000 by scope. Percentage priced firms quote a share of construction; I quote the fixed number in writing before we start.
- Consultant coordination. I write the scopes, sequence the work and carry the results into the drawings and the permit responses, inside my fee.
- Construction. I administer the construction contract. Piper Cole does not build.
I have been an architect since 1996, an AIA member since 1992 and an NCARB member since 1996.
Selected work
Projects from the practice, for a sense of what the budget buys.
Before you commission anything
Ask for the free first feasibility check
Send the address and what you are considering. I will tell you which consultants your lot triggers.
Questions
How much do consultants cost before construction on a Seattle or Eastside house?
On my worked example, a $1,800,000 new custom home in Kirkland on a sloped lot with trees, the consultants come to about $25,500 to $74,000 and the City of Kirkland’s published 2026 fees come to $25,798.95, so roughly $51,300 to $99,800 in total before construction starts. The consultant figures are labelled estimates based on proposals I have seen as the owner’s architect in 2025 and 2026, not quotes. The city figures are from Kirkland’s Building Services Fees schedule effective 1 January 2026, read on 25 November 2026. On a flat lot outside a critical area the consultant side drops to around $13,000 to $14,000.
Which consultants does a homeowner contract directly, and which does the architect handle?
On most of my projects you hold the agreement with the surveyor, the geotechnical engineer, the arborist, the civil engineer and any land use attorney, and you pay them directly. The energy code documentation often sits inside my scope. The structural engineer varies: on some projects the engineer is inside the architect’s agreement and on others the owner contracts directly, so ask for that in writing before you sign. My work is to set each scope, sequence them, read what comes back and build it into the drawings and the permit responses, and that coordination is inside my fixed fee.
Does the city charge me for reading my geotechnical report?
Yes, and more than once. Seattle’s 2026 Fee Subtitle section 22.900D.145.E sets the fee for third party review as the contract cost to the Department plus staff hours at the SDCI hourly rate of $292, with 75 percent of the estimated contract amount due before the contract is awarded. Mercer Island’s 2026 schedule lists $691 for geotechnical review of a single family permit plus actual cost of peer review. Medina lists Critical Areas Review at $135.00 plus consultant costs. Kirkland charges actual costs including administrative and overhead costs when it uses outside consultants for plan review. These were read on 25 November 2026; confirm with the city.
What triggers a geotechnical report on a Seattle or Eastside lot?
A site fact, not a preference. Seattle’s permit pages name a steep slope, a potential or known slide area, liquefaction, landfill or peat settlement prone ground, and for additions and alterations that applies to projects with exterior work or foundation changes. Eastside cities print their own triggers and some ask for a report for any new foundation on a sloped lot, and Bellevue wants documents under five years old. My survey and geotechnical report guide sets out which city page decides. Costs for the report itself run about $5,000 to $12,000 as an estimate on a sloped lot, before the city’s review fee.
How much is a land survey, and do I need both a boundary and a topographic survey?
For a seven figure project, usually both, and they are normally ordered together. A boundary survey fixes the lot lines and corners; a topographic survey fixes elevations, structures, utilities and trees. Both are land surveying under RCW 18.43.020(7), so a Washington licensed professional land surveyor signs and seals them. A combined survey on a Seattle or Eastside residential lot is about $4,000 to $9,000 as an estimate, toward the top of that range on a large, wooded or steeply sloped lot. If the document has to be recorded, King County’s recorder lists $303.50 for the first page of all other documents plus $1 per additional page.
Do I need an arborist, and what does the city charge on top?
If there is a significant or exceptional tree on or next to the work, or any clearing, then usually yes, and the report belongs in schematic design because a retained tree moves the footprint. A report with a tree protection and retention plan is about $1,500 to $5,000 as an estimate. The city then charges for its own arborist to review yours: Mercer Island lists $427 for arborist review of a construction permit, Medina lists $360.00 per tree for a Hazard Tree Evaluation and $300.00 plus consultant fees for an administrative tree activity permit where a tree is removed and a building permit is associated, and Seattle charges its land use hourly rate of $551 for tree review on land use or construction permits. Read 25 November 2026.
Is the architect’s fee a percentage of construction cost?
Mine is not. I quote a fixed fee for design and permit, set by project budget and location, about $10,000 to $200,000 depending on scope, and you get that number in writing before we start. Percentage priced firms quote a share of construction cost instead, which means the fee moves whenever the budget moves. The consultant fees on this page are separate from my fee, and on most projects you pay those consultants directly.
Can I skip any of this to save money?
Skipping is usually more expensive than sequencing. The cheapest path is survey first, geotechnical report second, structural engineer third, with the arborist early enough to influence the footprint. Done out of order, you pay the structural engineer twice or move a footprint after the drawings are advanced. On the worked example the whole consultant and city number at the high end is 5.5 percent of the construction budget: 99,800 divided by 1,800,000 is 0.055. Kirkland’s pre-submittal conference for an owner’s own single family remodel, addition or rebuild is listed at no fee, which is the cheapest hour in the process.
What does the free feasibility check cover, and what do I send?
The first basic feasibility check is free and usually takes about a day. Send the address and what you are considering, plus any survey or report you already hold, and I will tell you which of the consultants on this page your lot is likely to trigger, which it is not, and what order to run them in, so you can budget before you commission anything. An in depth analysis is $1,500 and takes 2 to 3 weeks. If you go ahead, I quote a fixed fee for design and permit, about $10,000 to $200,000 depending on scope.