What an older house adds to a remodel budget in Seattle and on the Eastside

A whole house renovation here runs $300 to $550 per square foot, and the age of the building usually moves you up inside that band rather than past it. The costly items are not the ones owners fear: filing the asbestos notification on your own house costs $25.

By David Meade, AIA, NCARBUpdated 25 November 202611 min read

On this page

    Short answer: the age of the building rarely shows up as a line item on a bid. It moves you up inside the band. A whole house renovation here runs $300 to $550 per square foot and an addition $350 to $650, and a 1960s to 1990s house tends to land in the upper half rather than above it. The money is in what changes the drawings: a cripple wall to brace, footings too narrow for a new floor, a side yard a demolition can erase. The items owners fear most are cheap: the asbestos notification on your own house costs $25 (Puget Sound Clean Air Agency). I am David Meade. The first basic feasibility check is free and takes about a day, and design and permit is a fixed fee set by project budget and location. Piper Cole Architects designs and administers construction; it does not build.

    Key takeaways

    • On an owner occupied single family remodel you may do your own asbestos survey, and the notification is $25. A demolition needs an AHERA inspector.
    • Labor and Industries can fine the owner, not just the contractor, $600 a day for starting work without asbestos testing.
    • Foam may not be used with knob and tube wiring, and other insulation only after a written electrical certification (WAC 296-46B-394).
    • Seattle’s free prescriptive retrofit plan set removes the need for a design professional and earns a reduced permit fee.
    • SDCI requires a licensed survey before demolition. That survey is what preserves a nonconforming yard, lot coverage or height.

    Who this page is for

    You own a house built roughly between 1960 and 1990 in Seattle or on the Eastside, and you are planning a whole house remodel or a major addition. I read every source linked here on 25 November 2026, and where there is no official figure I say what it depends on rather than guess. Washington law does not require an architect for a house: RCW 18.08.410(5) exempts residential buildings of up to four dwelling units.

    What the age adds, and what it does not

    Place yourself in this table.

    What the house has What it adds What it changes on the drawings
    Asbestos in flooring, mastic or siding $25 notification plus abatement Abatement drawn before demolition
    Paint from before 1978 Testing, then lead safe practices A note on components tested clean
    Knob and tube wiring Electrical certification, plus rewiring Foam ruled out
    Galvanized supply pipe Depends on fixtures and open access Repipe drawn with the framing
    Unbraced cripple wall Reduced permit fee, or engineering Anchors and sheathing on the foundation plan
    Basement or garage you will heat Full energy code compliance A separate compliance path
    A 12 inch footing under a new floor Underpinning by the linear foot Each run marked keep or replace

    Now the arithmetic. Take a 2,600 square foot house from 1975: a whole house renovation is 2,600 x $300 = $780,000 to 2,600 x $550 = $1,430,000. New custom home construction runs $400 to $900 per square foot, so the same area built new is $1,040,000 to $2,340,000, with demolition typically $20,000 to $50,000. Most of what the age costs you is inside the renovation band already, because a remodel number assumes an existing house with surprises in it. SDCI’s Tip 314 confirms the Existing Building Code triggers that pull a whole building up to current code stop at 7,000 square feet.

    Asbestos: the survey, the fee and the sequence

    Labor and Industries requires owners, their agents and contractors to identify asbestos containing materials before construction begins, usually through an accredited AHERA building inspector doing a good faith inspection. The penalty is $600 a day for work done without that testing, or for not sharing the results with exposed workers, and it reaches the owner as well as the contractor (L and I).

    The exemption is narrow. L and I says work in your own residence, not used commercially, is exempt from the general survey requirements, but you must still give the results to any contractor you bring in. The Clean Air Agency agrees from the other side: an AHERA inspector is not required to survey an owner occupied single family remodel, but is required for a demolition (Regulation III, Article 4). Suspect materials in this vintage: vinyl asbestos tile and its mastic, duct wrap, pipe insulation, textured paint, joint compound and cement siding.

    Project Waiting period Fee
    Single family residence, asbestos project Prior written notification $25
    Single family residence, demolition 10 days $65
    Under 10 linear feet of pipe or 48 square feet per year None No notification
    Not single family, 1,000 linear feet or 5,000 square feet and above 10 days $640

    Nonfriable material needs no notification, while every demolition over 120 square feet of roof area needs one even with no asbestos present. Only an owner living in the house may remove it; rental owners must hire a certified contractor (homeowner page). Figures are as of November 2026.

    The sequence matters more than the fee. Section 4.04(a) makes it unlawful to carry out work that may disturb friable asbestos containing material without first removing it, so abatement sits on the critical path, with a 10 day wait before a demolition. I have no official figure for abatement; what moves it is how much friable material there is, containment, access and disposal.

    Remodeled kitchen with a large island, pendant lights and full height cabinetry
    Bellevue remodel, Piper Cole Architects. Opening a kitchen is where the asbestos survey, the wiring certification and the energy code all meet.

    Free feasibility check

    Planning a custom home or a remodel of $750,000 or more?

    Send me the address and a few lines about what you want. The first feasibility check is free and usually takes about a day.

    Lead paint, and why testing is the cheap move

    EPA says lead based paint for homes was banned in 1978 and that roughly three quarters of pre-1978 United States homes still contain some (EPA). A 1960s or 1970s house is in scope; a 1980s or 1990s house is not, which is the clearest reason the age band matters to your budget. Washington runs its own EPA authorized program, so the rule is chapter 365-230 WAC, which applies to renovations performed for compensation in target housing (WAC 365-230-300).

    The cheap move is in the rule, which lets you out component by component. Three things do it: a written determination by a certified inspector or risk assessor, a certified renovator testing each component with an EPA recognized test kit, or a paint chip sample to an EPA recognized laboratory. The regulated level is 1.0 milligram per square centimeter or 0.5 percent by weight. So test early and name the clean components in the scope, rather than pricing containment across the whole house because it is old.

    Knob and tube wiring and galvanized pipe

    Knob and tube wiring was largely out of use by the 1950s, so in this band it turns up where part of the structure is older than the house: an earlier cottage, a detached garage, a rewired section. It changes the wall assemblies, not just the panel. WAC 296-46B-394 says NEC Article 394 does not prohibit loose or rolled thermal insulation in spaces with existing knob and tube wiring, provided all three of these hold:

    • A licensed electrical contractor surveys the wiring and certifies in writing that it is in good condition, with no improper overcurrent protection, no insulation failure or deterioration, and no improper splices.
    • The insulation meets Class I specifications, flame spread 25 or less to ASTM E84-81a. Foam insulation may not be used with knob and tube wiring.
    • Every circuit has overcurrent protection per NEC Table 310.16, 60 degree column, as breakers or Type S fuses.

    Opening a wall invites you to fill the cavity. This rule says you may not foam it, and may not insulate at all until an electrician certifies the wiring. So I want that survey before design development.

    Galvanized supply pipe. I found no official figure for a repipe, so there is none here. It depends on fixtures, floors, slab or crawl space, and above all whether the walls on the route are already open. One drawn with the framing costs a fraction of one chased into finished walls later.

    Cripple walls and the earthquake retrofit

    SDCI says most earthquake damage to houses comes from the house jumping off its foundation or a weak pony wall collapsing, and states the fix as an ABC: anchor the home to the foundation, brace the wall below the first floor, connect that wall to the first floor framing (SDCI).

    Seattle’s program keeps this cheap. Since 1998 the city has run what is now the Earthquake Home Retrofit Permit, previously Project Impact, using a prescriptive plan set developed with the Federal Emergency Management Agency. SDCI says the plan sets eliminate the need to hire a design professional, that qualifying projects pay a reduced permit fee, and that initial review typically takes two weeks (retrofit permit).

    Whether you get that deal turns on the eligibility checklist, Table 1 on Sheet S0: light wood frame and light roof construction, not irregularly shaped, a sound concrete or reinforced masonry foundation, up to three stories, on a level lot. A house that fails it is still a candidate, SDCI says, but an architect or structural engineer must develop the plans. Construction cost turns on crawl space headroom, how much perimeter needs sheathing, and whether the concrete is sound. My retrofit guide walks the eligibility questions.

    The energy code switch that opening a wall throws

    The rule that keeps a remodel affordable is WAC 51-11R-50300, section R503.1: alterations comply with the code for new construction without requiring the unaltered portions of the house to comply. Two limits sit beside it. The altered house may be no less conforming than before, and it may use no more energy than before, which bites when a solid wall becomes glass.

    At each wall you open, exception 2 lets a cavity exposed during construction be filled instead of meeting new construction values, at a minimum of R-15 in a 2×4 framed wall and R-21 in a 2×6. A cavity you never expose needs nothing. Replacement windows meet the U-factor in Table R402.1.3, averaged across the units you replace.

    The expensive one is WAC 51-11R-50200, section R502.2: any nonconditioned or low energy space altered to become conditioned space must be brought into full compliance. Not partial, and not the exposed cavity allowance. That is the unheated basement, the garage and the enclosed porch, and it is where an older house budget most often breaks. More in my energy code guide.

    The setback your house enjoys and a remodel can lose

    This is the item with no invoice and the largest number behind it. A house built before the current rules may stand closer to a line, cover more of the lot, or rise higher than the zone allows. That position has value, and it belongs to the building, not to you.

    SDCI’s Tip 337, updated 27 March 2024, says you may rebuild the same type of building you are demolishing even if your residential structure does not conform to the development standards of the zone, giving required yards, lot coverage and height as the examples. Then the condition: SDCI will require a survey by a licensed surveyor documenting current conditions before demolition, citing SMC 23.42.112. Note the order. The survey comes first, because it is the evidence of the nonconformity. Take the house down first and the evidence goes with it.

    A demolition permit is required for structures over 120 square feet of roof area, so the garage is in scope, and SDCI says greater restrictions may apply in environmentally critical areas. Seattle’s code host blocks automated requests, which I did not bypass, so I rely on that tip and its cite rather than today’s codified text. Confirm with SDCI, or with your own city outside Seattle. See my remodel or tear down guide and lot coverage and setbacks guide.

    Footings, and what a second floor asks of them

    A second story addition gets expensive below the floor, not above it. The 2021 Seattle Residential Code, chapter 4, sets a minimum footing of 12 inches wide and 6 inches deep, sized against the soil’s load bearing value, and puts exterior footings at least 12 inches below the undisturbed ground surface (chapter 4). Add a floor and your house changes row in Table R403.1(1), light frame, at 20 psf roof live load or 25 psf ground snow load:

    Story and type Soil at 1,500 psf Soil at 2,000 psf
    1 story with crawl space 12 x 6 inches 12 x 6 inches
    2 story with crawl space 15 x 6 inches 12 x 6 inches
    2 story plus basement 19 x 6 inches 14 x 6 inches
    3 story plus basement 22 x 7 inches 16 x 6 inches

    Work it on your own house. A one story over a crawl space on soil rated 1,500 pounds per square foot is served by a 12 inch footing. As a two story it wants 15 inches, which is 15 to 12 = 3 extra inches on every linear foot of bearing wall you load. On soil rated 2,000 psf the same change asks for nothing. That is the difference between widening footings around the house and leaving them alone, which is why the geotechnical report is not optional here.

    Then everything between the new floor and that footing. A second floor needs a continuous load path: posts and beams, bearing walls stacked over bearing walls, and braced walls that a 1960s plan of small rooms often has and a 1980s open plan often does not. So: survey and geotechnical report, then test pits to measure what the footing actually is, then a foundation plan marking every run keep, widen or replace. Underpinning is priced by the linear foot and I have no official figure for it. See my notes on the survey and geotechnical report and when a remodel needs a structural engineer.

    How I work on an older house, and what I charge

    The first check is a basic feasibility study: free, about a day, and all it needs is the address and your intentions. An in depth analysis costs $1,500 and takes 2 to 3 weeks, and design to permit submission is typically 2 to 4 months. My fee for design and permit is a fixed fee, set by project budget and location and stated in writing before we start. Percentage priced firms quote a share of construction cost instead, so their fee rises with every surprise the building hands you. Mine does not. My order of work:

    1. Survey and geotechnical report, fixing the property lines, the nonconformity and the soil bearing value.
    2. Asbestos good faith inspection, and on a pre-1978 house, component lead testing.
    3. The retrofit eligibility checklist, and an electrical survey where knob and tube is suspected.
    4. Design, with every assembly marked altered or unaltered for the energy code.

    I have been an architect since 1996, an AIA member since 1992 and an NCARB member since 1996, and I hold three Masonry Excellence Awards for commercial projects. Piper Cole designs and administers construction. I do not build.

    Selected work

    Projects from the practice, for a sense of what the budget buys.

    See the full portfolio

    Before you take bids

    Ask for the free first feasibility check

    Send me the address and what you want to change, by phone or on WhatsApp. The first basic check is free and takes about a day, and design and permit is a fixed fee quoted in writing.

    Questions

    How much does the age of a house add to a remodel budget in Seattle?

    There is no single figure, because the age of a house moves you up inside the cost band rather than adding a separate line. A whole house renovation in Seattle and on the Eastside runs $300 to $550 per square foot and an addition $350 to $650, and a house from the 1960s to the 1990s tends to land in the upper half. The paperwork itself is small: an asbestos notification on your own single family house is $25 with the Puget Sound Clean Air Agency. The costly items are a cripple wall retrofit, footings that have to be widened for a new floor, and the loss of a nonconforming yard if you demolish without a survey first. One worry you can drop: SDCI’s Tip 314, updated 28 April 2026, confirms the Seattle Existing Building Code substantial alteration triggers do not apply to buildings of 7,000 square feet or less.

    Do I have to test for asbestos before remodeling my own house?

    Labor and Industries requires owners, their agents and contractors to identify asbestos containing materials before any construction activity begins, usually through an accredited AHERA building inspector doing a good faith inspection. If you are working in your own residence, not used commercially, L and I says you are exempt from the general survey requirements but must still give the information to any contractors and workers you bring in. The Puget Sound Clean Air Agency likewise does not require an AHERA inspector for the renovation of an owner occupied single family residence, but does require one for a demolition. L and I can fine the owner as well as the contractor $600 a day for starting work without testing, or for not sharing the results.

    What does the asbestos notification cost in King County?

    Under the Puget Sound Clean Air Agency’s Regulation III, Article 4, an asbestos project at a single family residence costs $25 with prior written notification, and a single family demolition costs $65 with a 10 day waiting period. No notification is needed for under 10 linear feet of friable material on pipes or 48 square feet on other components per structure per calendar year, or for nonfriable material such as roofing, vinyl asbestos tile, mastic and caulking. Larger projects at buildings that are not single family residences run $210 or $640, and an amendment adds $20. These are the figures as of November 2026, so confirm them with the agency.

    Does the lead paint rule apply to my 1970s house?

    Yes, if you are paying someone to disturb the paint. The federal ban on selling lead based paint for homes took effect in 1978, and EPA says about three quarters of pre-1978 United States homes still contain some. Washington runs its own program under chapter 365-230 WAC, which applies to renovations performed for compensation in target housing. EPA says the rule generally does not apply to homeowners doing the work themselves in their own pre-1978 home, unless they rent part of it, run a childcare center in it, or renovate for resale. A house built in the 1980s or 1990s is outside the rule altogether.

    Can I insulate walls and attics that have knob and tube wiring?

    Only on conditions, and foam is out. WAC 296-46B-394 says NEC Article 394 does not prohibit loose or rolled thermal insulation in spaces containing existing knob and tube wiring provided three things are true: an appropriately licensed electrical contractor surveys the wiring and certifies in writing that it is in good condition with no improper overcurrent protection, no conductor insulation failure or deterioration and no improper connections or splices; the insulation meets Class I specifications with a flame spread factor of 25 or less and is not foam; and every knob and tube circuit has overcurrent protection per NEC Table 310.16, 60 degree centigrade column, using breakers or Type S fuses. Get that electrical survey before design development, because it decides the wall assemblies.

    Does Seattle make me do an earthquake retrofit when I remodel?

    SDCI describes these as voluntary earthquake home retrofits, and runs the Earthquake Home Retrofit Permit, previously Project Impact, to make them easy. Whether your particular remodel triggers a structural upgrade is a Seattle Residential Code question for your reviewer, and worth asking at a pre-submittal conversation rather than assumed. What SDCI does offer is a free prescriptive plan set developed with FEMA and the Seattle Office of Emergency Management, which it says eliminates the need to hire a design professional and earns a reduced permit fee, with initial review typically taking two weeks.

    Will I lose my setback if I tear the old house down?

    You can keep it, but only if you document it first. SDCI’s Tip 337, updated 27 March 2024, says you may rebuild the same type of building you are demolishing even where your residential structure does not conform to the zone’s development standards, naming required yards, lot coverage and height, and that SDCI will require a survey by a licensed surveyor documenting the current conditions before demolition, citing SMC 23.42.112. The survey has to come first, because it is the evidence of what the nonconformity was. SDCI also warns that greater restrictions can apply in environmentally critical areas. Outside Seattle, each city runs its own nonconformance chapter, so confirm with yours.

    Does the energy code force me to upgrade the whole house?

    No. WAC 51-11R-50300, section R503.1, says alterations meet the code for new construction without requiring the unaltered portions of the house to comply, with two limits: the house may be no less conforming than before, and it may use no more energy than before. An existing cavity exposed during construction may be filled at a minimum of R-15 in a 2×4 wall and R-21 in a 2×6 rather than meeting new construction values, and a cavity you never open needs nothing. The expensive exception is WAC 51-11R-50200, section R502.2: unheated or low energy space you alter to become conditioned space, such as a basement or garage, must be brought into full compliance.

    Does Washington require an architect for a house remodel?

    No. RCW 18.08.410(5) says the architect licensing law does not prevent anyone from doing design work, including construction documents and administering the construction contract, for a residential building of up to four dwelling units, whatever its size. So hiring me is a choice about risk on an older house, not a legal requirement. What I do is design the house and administer construction. Piper Cole Architects does not build. A separate point worth knowing: SDCI says a house that fails the eligibility checklist for its prescriptive earthquake retrofit plan set will need an architect or structural engineer to develop the plans.


    David Meade, AIA, NCARB
    Principal Architect, Piper Cole Architects · Kirkland, WA

    David Meade is a licensed architect (AIA, NCARB) who has worked as an architect since 1996, with three Masonry Excellence Awards for commercial projects. Learn more about David →

    Gray midcentury house at dusk with lit entry, stone steps, boulders and new landscaping

    Next step

    Have a project in mind?

    Call David Meade directly, or send the address and a few lines about what you want. The first feasibility check is free and usually takes about a day.

    Free feasibility check

    Send the address and what you have in mind. David replies to you personally.