A second story addition on a Kirkland house is sized by floor area, by height above average building elevation, and by whether older walls sit inside today’s yards. A second floor adds floor area and, built inside the existing footprint, no lot coverage. On the worked lot below (7,500 square feet, a 1,900 square foot one story house) floor area leaves 1,850 square feet, and a 1,420 square foot floor fits with 430 to spare. At this site’s planning range for additions ($350 to $650 per square foot) that floor is $497,000 to $923,000, so a second floor can reach my $750,000 minimum. My first basic feasibility check is free and very quick, usually about a day; an in depth analysis is $1,500, takes 2 to 3 weeks and goes further. Piper Cole Architects designs and administers construction and does not build.
Key takeaways
- On the worked lot (7,500 square feet, RS 7.2) floor area allows 3,750 square feet (7,500 x 0.5), the house uses 1,900, so 1,850 are left; coverage does not change. These 50 percent figures are from the 2022 planning packet; the city’s current code controls.
- With 9 foot ceilings and a 4 in 12 roof the example reaches 26.33 feet above average building elevation. I could not read Kirkland’s current height limit; older City documents say 25 feet for RS zones, so ask Planning.
- KZC 162.35(7), as printed in Ordinance O-4905: structurally altering a roof or exterior wall that misses the height or required yard standards means that nonconformance must be brought into conformance. Ask the city how it reads a new floor on that wall.
- Where an addition adds a story, the old house and the new work together must meet the code for new construction, unless an engineering evaluation shows they carry the loads (WAC 51-51-4505, R4505.3).
Who this page is for
This page is for the owner of a Kirkland house who wants a second floor on a project budget of $750,000 or more; a smaller addition is below my minimum. For a ground level addition see my Kirkland home addition page; for an addition with a whole house remodel, my addition and whole house remodel page.
I read these sources on 3 November 2026: the city’s pages and PDFs, a published ordinance copy and the state code. The Kirkland Zoning Code site sits behind a bot check, answered my one request with HTTP 403, and I did not try to get around it. The yard, coverage and floor area ratio figures are from the 2022 planning packet (the density table in a City Planning Commission packet dated August 18, 2022); the city’s current code controls, and I could not read its current table, the height definition, KZC 95.15 and 162.45, the local building code amendments or the Building Valuation Data Table. KZC 115.42, 115.90 and 162.35 are from Ordinance O-4905, signed June 17, 2025. Confirm each number with Planning (425 587 3600). This is general information, not legal advice. Washington law does not require an architect for a house of up to four units (RCW 18.08.410(5)).
Request your free feasibility check
Send me the address, what you want upstairs and a rough budget. I will reply to you personally.
Prefer to talk? Call 425 753 6452 or message David on WhatsApp.

Free feasibility check
Planning a custom home or a remodel of $750,000 or more?
Send me the address and a few lines about what you want. The first feasibility check is free and usually takes about a day.
What size of second floor reaches $750,000
$350 to $650 per square foot is a planning range, not a quote; plan design fees, permits, tax and contingency on top. 750,000 / 650 = 1,154 square feet (rounded up) and 750,000 / 350 = 2,143, so a floor of 1,154 or more can reach my minimum and one of 2,143 or more does at any point.
| Second floor | Planning range | Reaches $750,000? |
|---|---|---|
| 900 sq ft | 900 x 350 to 900 x 650 = $315,000 to $585,000 | No, it would need $834 per sq ft |
| 1,420 sq ft | $497,000 to $923,000 | At $529 per sq ft and up (750,000 / 1,420) |
Second story addition in Kirkland: what the lot allows
RS 7.2 means a 7,200 square foot minimum lot. My hypothetical lot, not a real property or a client’s, is 75 by 100 feet, 7,500 square feet, flat, zone RS 7.2, no shoreline. A one story house of 1,900 square feet (50 x 38) stands on it, with a 480 square foot attached garage (20 x 24) at the right front corner, so the living area is 1,420 (1,900 minus 480). The left wall is 4 feet from the left side line; the right side has 21 feet (75 minus 50 minus 4). The driveway is 400 square feet (16 x 25), the walk 100 and the patio 250.
| Limit | What the source says | On the worked lot |
|---|---|---|
| Yards (KZC 15.30, 2022 packet) | RS: front 20 feet, rear 10, each side at least 5 and the two sides at least 15 together. | Left side 4 is under 5, so that wall is nonconforming. |
| Floor area ratio (2022 packet, KZC 115.42) | 50 percent of lot size in RS 7.2, counting the area inside the exterior walls on every level, garage included. A ceiling over 16 feet counts a room twice. One 100 square foot exemption applies if the house has an internal staircase or a ceiling over 16 feet. The city checklist says to ask a planner whether FAR applies in Houghton. | 7,500 x 0.5 = 3,750 square feet |
| Lot coverage (2022 packet, KZC 115.90) | 50 percent in RS. It counts all structures and any other hardscape. A floor built inside the existing footprint adds no ground area, so as I read the section it adds none. | Today 1,900 + 400 + 100 + 250 = 2,650 of 3,750, and a second floor leaves it there. |
| Height (city handout; two older City documents) | Measured above average building elevation, the weighted average of the ground before development. The handout says to call Planning for your zone’s maximum, and the height cell is cut off in the 2022 packet. Two older City documents give RS zones 25 feet, a April 4, 2019 staff memo to the Planning Commission and a June 10, 2022 staff memo (DRV22-00371). Neither is the current code. | I assume 25 feet above average building elevation, only to show the arithmetic. |
Floor area sets the size: 3,750 minus 1,900 = 1,850 square feet.
| Plan | Arithmetic | Total floor area | Against the 3,750 cap |
|---|---|---|---|
| 1. Floor over the living area | 1,900 + 1,420 | 3,320 | 430 under |
| 2. Floor over everything | 1,900 + 1,900 | 3,800 | 50 over; 50 under (3,700) if the 100 square foot stair exemption applies |
| 3. Plan 1, stepped in at the old wall | 1,420 minus (38 x 1) = 1,382; 1,900 + 1,382 | 3,282 | 468 under |
KZC 115.42(4), as printed in Ordinance O-4905, adds five percent F.A.R. above the zone maximum if at least two of three elements are used: roof forms peaked near the center at 4 in 12 or steeper; every structure 7.5 feet or more from the side lines; or each upper floor at least 15 percent smaller than the ground floor in area. The worked left wall fails the second; Plan 1 passes the third (1,900 x 0.15 = 285, so 1,615 at most) and a 4 in 12 gable passes the first. The text does not say whether five percent means 5 points of lot size (375 square feet) or 5 percent of the cap, so I ask the city.
Height and the survey
These figures are my assumptions, not measurements. The lot is flat, so average building elevation is the existing grade. The first floor sits 1 foot above grade, ceilings are 9 feet and floor framing is 1 foot. The roof is a gable across the 38 foot depth, a half span of 19 feet, measured to the ridge; the city’s height form asks a surveyor for the highest point of the roof. A 4 in 12 roof rises 19 x 4 / 12 = 6.33 feet, a 3 in 12 roof 19 x 3 / 12 = 4.75.
| Design | Arithmetic | Height above ABE | Against 25 feet, the older figure |
|---|---|---|---|
| 9 foot ceilings, 4 in 12 roof | 1 + 9 + 1 + 9 + 6.33 | 26.33 feet | 1.33 over |
| 9 foot ceilings, 3 in 12 roof | 1 + 9 + 1 + 9 + 4.75 | 24.75 feet | 0.25 under, inside the 1 foot band |
The 4 in 12 roof that helps the floor area bonus is also the taller one, so a designer trades floor area against height. The city’s Survey Policy (2015) sets the survey. A boundary survey is required for additions unless three conditions are all met, the first being that the structure is at least two feet from all assumed setback lines; the worked wall is 1 foot inside the 5 foot yard, so as I read it the exception fails. A 2 foot contour topographic survey is required unless the lot is essentially level, the design is 2 or more feet under the maximum height, or the footprint changes under 25 percent and the addition stays within the existing roof line and is not on lower ground, which a second floor does not; the worked lot is flat, so it would be waived. A height table goes in with the application, and a licensed surveyor’s height letter is due at roof sheathing for a roof within 1 foot of the maximum, as the 24.75 foot design would be against a 25 foot maximum.

Building up over an older house
KZC 162.35(7), as printed in Ordinance O-4905, says that any structural alteration of a roof or exterior wall that misses the height or required yard standards will require that the nonconforming setback be brought into conformance; repair or maintenance of structural members is excepted. A second floor replaces the roof and loads the worked left wall. Read the hard way, the old wall moves in 1 foot (5 minus 4) along 38 feet, 38 square feet on each floor. Read the soft way, only the new floor’s wall stays 5 feet back, which is Plan 3. I ask the city in writing before I draw.
KZC 162.35(13) corrects any other nonconformance (not yards or height, which (7) covers) when 12 months of work on an improvement that is nonconforming or houses, supports or is supported by the nonconformance costs more than 50 percent of its replacement cost. Suppose, as my assumption, the house’s replacement cost is $700,000, so half is $350,000; the 1,420 square foot floor at the planning range is $497,000 to $923,000, over half at any point. The city values work its own way, which I did not read.
What the existing house has to carry
The state residential code, WAC 51-51-4505, effective March 15, 2024, says in R4505.3 that where an addition adds a story to any part of the existing building or vertically increases its height, the new construction and the existing building together must meet the code for new construction. The exception: if they are evaluated together under accepted engineering practice and shown sufficient for the combined loads, no structural alterations are required. That is the state text; the Building Code Council has proposed a 2024 edition (WSR 26-10-071), so check which edition the city applies. The city’s checklist says to design for the codes the city has adopted, as amended by the State; I did not read the city’s adoption ordinance or any local amendments.
The section gives no loads; what a house can carry is an engineer’s finding from its foundation, framing and walls. The city’s checklist asks for structural drawings and any structural calculations, stamped and signed if a Washington licensed design professional prepared them, and its review table adds time for third-party structural review. See when a remodel needs a structural engineer.
The permit, the documents and the city’s time
The city says building permits are required for construction or modification of a building, applied for through MyBuildingPermit.com, with an optional pre-submittal conference (city process page). Its documents ask this of the worked floor.
| Item | What the city’s document says | On the worked second floor |
|---|---|---|
| Plans and energy (checklist) | Floor area by structure and floor; an average building elevation calculation for the entire structure if the roof line changes (ABE handout); a height table; structural drawings and calculations; an energy code sheet for new heated space; ventilation information above 500 square feet. | Floor area 1,900 + 1,420 = 3,320. The roof line changes. 1,420 is over 500. |
| Trees (KZC 95.30(1)(b); checklist) | A tree retention plan is required unless the proposed improvements are under 50 percent of the existing footprint and nothing is built in the critical root zone of regulated trees. The checklist says it may not be required if all work is within the footprint. | 1,420 / 1,900 = 75 percent, over 50 if floor area counts; the checklist points the other way, so I ask. |
| Street (checklist) | A right-of-way improvements plan by a licensed civil engineer for single family additions valued over $200,000, by the city’s Building Valuation Data Table. | The city’s table sets the value and I did not read it; at my planning range the floor is $497,000 to $923,000, so I expect it to cross $200,000 [estimate]. |
| Review (goals, 9.15.2026) | Single family addition, regular: first review 4 weeks, then 10 business days per revision. Fast Track (10 business days) is for additions up to 50 percent of existing area (city page); the city lists complex structural alterations among its disqualifiers. | 1,420 / 1,900 = 75 percent, so regular. Two revisions add 20 business days (10 x 2), about 8 weeks of goals in all. |
The set starts from the house as it stands; see my existing conditions page, my Kirkland permit fee guide for city charges and my Kirkland waterfront page for lake lots.
How it works with me
First comes the free basic feasibility check, very quick, usually about a day; an in depth analysis is $1,500 over 2 to 3 weeks and goes further. Then I quote a fixed fee for design and permit, set by project budget and location, about $10,000 to $200,000 depending on scope. Design to permit submission typically takes 2 to 4 months. After the permit I administer construction for you. I do not build.
I have been an architect since 1996, and I am a member of the AIA (since 1992) and NCARB (since 1996).
Selected work
Remodels and additions from the practice.
Before you design the new floor
Ask for the free first feasibility check
Send me the address and what you want upstairs through the request form above, or call or message me on WhatsApp. The first basic feasibility check is free and very quick, usually about a day.
Questions
Can I add a second story to my house in Kirkland?
It can work when the lot has floor area left, the roof stays under the height limit and the old walls can carry the new floor or be brought into line. Floor area counts every level, and a second floor adds floor area but no lot coverage. On the worked 7,500 square foot RS 7.2 lot, floor area leaves 1,850 square feet. The yard, coverage and floor area figures are from the city’s 2022 planning packet; the city’s current code controls. Send me the address and I will check the lot in my free first feasibility check, usually about a day.
How big can a second story addition be in Kirkland?
It is the floor area cap minus what you have. In RS 7.2 the cap is 50 percent of the lot, so 7,500 x 0.5 = 3,750 square feet; with a 1,900 square foot one story house that leaves 1,850 square feet. Rooms open to more than 16 feet count twice, and the code gives one exemption of 100 square feet if the house has an internal staircase or a ceiling over 16 feet. Check your zone with the city; the table I could read is from 2022.
How tall can a Kirkland house be after a second story?
Height is measured above average building elevation, a weighted average of the ground before development, and the limit depends on the zone. The city’s handout tells you to call Planning for the maximum, and I could not read the table’s height column for a detached house. Two older City documents, from 2019 and 2022, give RS zones 25 feet, but neither is the current code. With 9 foot ceilings on both floors and a 4 in 12 roof my worked example reaches 26.33 feet above that average, so compare it with your zone’s maximum. Vents and chimneys may exceed the limit.
What if my house is closer to the property line than today’s rules allow?
The house may stay, but touching the wall can trigger the rule. KZC 162.35(7), as printed in Ordinance O-4905, says that structurally altering a roof or exterior wall that does not comply with the height or required yard standards means the nonconforming setback must be brought into conformance. Other nonconformances must be corrected when 12 months of work on the improvement costs more than 50 percent of its replacement cost (KZC 162.35(13)). I ask the city in writing how it reads a second floor on that wall before I draw.
Does a second story addition need a structural engineer in Kirkland?
The city’s checklist asks for structural drawings and any structural calculations, stamped and signed if a Washington licensed design professional prepared them. I found no Kirkland document that names an engineer’s stamp as a requirement for a second floor. The state residential code (R4505.3, WAC 51-51-4505) says that where an addition adds a story, the new work and the existing house together must meet the code for new construction unless an engineering evaluation shows the combined structure can carry the combined loads, so plan on an engineering evaluation of the house.
How long does Kirkland take to review a second story permit?
The city’s goals, updated 15 September 2026, are 4 weeks for the first review of a regular single family addition and 10 business days for each revision before issuance. Fast Track is for additions up to 50 percent of existing area. Two revisions on a regular review are about 8 weeks of goals (4 weeks plus 20 business days). The city says actual times vary, and third-party structural review adds time. Design to permit submission typically takes me 2 to 4 months.
How much does a second story addition in Kirkland cost, and where does it reach your minimum?
I use a planning range of $350 to $650 per square foot for additions, which is not a quote. My smallest project is $750,000, which a second floor reaches between 1,154 square feet (750,000 / 650) and 2,143 (750,000 / 350). A 900 square foot floor is $315,000 to $585,000, below my minimum. My fixed fee for design and permit is about $10,000 to $200,000, depending on scope. The first basic feasibility check is free and very quick, usually about a day; an in depth analysis is $1,500, takes 2 to 3 weeks and goes further.
Do I need an architect for a second story addition, and do you build it?
Washington’s architect licensing law does not stop anyone from doing design work for a residential building of up to four dwelling units (RCW 18.08.410(5)), so an architect is your choice. Piper Cole Architects designs the addition and administers construction for you; we do not build.
What if my Kirkland lot is on Lake Washington?
Land within 200 feet of the lake’s ordinary high water mark is under the shoreline chapter of the zoning code. In the program as Ecology approved it on September 21, 2020 (an Ecology-hosted copy of KZC 83, current through Ordinance 4781, so not the current text), KZC 83.550(5)(b)(8) lets a nonconforming detached house built before December 1, 2006 enlarge its footprint inside the shoreline setback by up to 10 percent of its gross floor area, and says other enlargements, such as upper floor additions, may be permitted if consistent with that subsection, which includes a restoration plan. I did not read the current chapter, which controls, so confirm with the city.

Kirkland Waterfront Custom Home
Holmes Point Residence
Lakeview Cottage, Goat Hill