A Kirkland home addition is sized by the lot before anyone draws a line: yards on every side, a floor area cap set as a share of the lot, and a lot coverage cap that counts the driveway and patio along with the roof. On the worked lot below, coverage reaches its cap first and leaves 1,340 square feet for a ground level addition. At this site’s planning range for additions ($350 to $650 per square foot) that is $469,000 to $871,000, so many ground level additions land under $750,000, my smallest project, and this page is for the larger ones. My first basic feasibility check is free and very quick, usually about a day. An in depth analysis is $1,500, takes 2 to 3 weeks and goes further. Piper Cole Architects, a Kirkland home addition architect, designs and administers construction and does not build.
Key takeaways
- On my worked lot (8,800 square feet, a 2,000 square foot one story house) floor area would allow 2,400 more square feet (8,800 x 0.5 = 4,400, minus 2,000), but lot coverage allows 1,340 (4,400 minus the 3,060 the house and paving already cover). Coverage decides. These 50 percent figures are from the 2022 planning packet; the city’s current code controls.
- Kirkland’s site plan guide and checklist ask for floor area and lot coverage calculations, average building elevation calculations when the roof line changes or the addition sits on lower ground, and a survey unless an exception applies. KZC 95.30 requires a tree plan unless the addition is under 50 percent of the existing footprint.
- Structurally altering a roof or exterior wall that sits inside today’s yards means that wall must be brought into conformance (KZC 162.35(7), as printed in Ordinance O-4905); repair and maintenance of structural members is excepted.
- At planning ranges an addition reaches $750,000 between 1,154 and 2,143 square feet. A 1,000 square foot addition is $350,000 to $650,000, below my minimum.
Who this page is for
This page is for the owner of a Kirkland house planning a ground level addition, rear addition or bump out large enough to be a $750,000 project or more. A second floor is a different question; see my Kirkland second story page. If the addition comes with a whole house remodel, my addition and whole house remodel page works that budget.
I read each source on 3 November 2026 on the City of Kirkland’s own pages and PDFs. The Kirkland Zoning Code site refused my request (HTTP 403) and I did not try to get around it, so the yard, coverage and floor area figures come from the density table as printed in a City Planning Commission packet dated August 18, 2022, and the text of KZC 95.30, 115.42, 115.90, 115.115 and 162.35 from Ordinance O-4905, signed June 17, 2025. The yard, coverage and floor area ratio figures are from the 2022 planning packet; the city’s current code controls, and I could not read its current table or height column. Confirm each number with the Planning Department (425 587 3600). This is general information, not legal advice. Washington law does not require an architect for a house of up to four units (RCW 18.08.410(5)), so hiring me is your call.
Request your free feasibility check
Send me the address, where you want the addition and about how big, and the rooms you have in mind. I will reply to you personally.
Prefer to talk? Call 425 753 6452 or message David on WhatsApp.

Free feasibility check
Planning a custom home or a remodel of $750,000 or more?
Send me the address and a few lines about what you want. The first feasibility check is free and usually takes about a day.
Home addition Kirkland: the limits that size it
Kirkland’s low density zones are RS, RSX and RSA; the number after RS or RSX is the minimum lot size in thousands of square feet, so RS 8.5 means 8,500. Find your zone on maps.kirklandwa.gov. Four limits size a ground level addition.
| Limit | What the source says | On the worked lot |
|---|---|---|
| Yards (KZC 15.30, 2022 planning packet) | For a detached house in RS: front 20 feet, rear 10, each side at least 5 and the two sides at least 15 together. RSX and RSA need 5 on each side with no combined total. Corner lots have special rules. | Width 80 minus 15 = 65; depth 110 minus 30 = 80; 65 x 80 = 5,200 square feet of envelope |
| Floor area ratio (2022 packet, KZC 115.42) | 50 percent of lot size in RS 8.5, 35 percent in the 12.5 zones, 20 percent in the 35 zones. It counts the area inside the exterior walls on every level, an attached garage included, and a carport by its roof area. It leaves out an attic under 5 feet of ceiling height, floor area with a ceiling under 6 feet above finished grade, uncovered decks, and covered decks, porches and walkways open on at least three sides or half their perimeter. A ceiling over 16 feet counts a room twice. The city checklist says to ask a planner whether FAR applies in Houghton. | 8,800 x 0.5 = 4,400 square feet |
| Lot coverage (2022 packet, KZC 115.90) | 50 percent in RS and RSX. It counts all structures and any other hardscape, so the driveway, walks and patio count with the roof. Pavers 10 by 10 inches or smaller, grassed modular grid, open grid decking and artificial turf count half; the discount is capped at 10 percent of the lot. | 8,800 x 0.5 = 4,400 square feet |
| Height (KZC 5.10.045, per the city’s handout) | Measured above average building elevation, a weighted average of the ground before development. The limit is in the table’s last column, cut off in my copy, so I give no height figure. | Ask the city for the limit |
Worked lot: how big can a ground level addition be
I worked one hypothetical lot, not a real property and not a client’s: 80 feet wide and 110 deep, 8,800 square feet (80 x 110), flat, zone RS 8.5, no shoreline or critical area. The house is one story, 50 by 40 feet, 2,000 square feet with its garage, set 25 feet back from the front line, no basement. The driveway is 16 by 40 feet (640 square feet), the front walk 120 and the rear patio 300.
| Step | Arithmetic | Result |
|---|---|---|
| Floor area cap | 8,800 x 0.5 | 4,400 sq ft |
| Floor area left | 4,400 minus 2,000 | 2,400 sq ft |
| Coverage cap | 8,800 x 0.5 | 4,400 sq ft |
| Coverage now | 2,000 + 640 + 120 + 300 | 3,060 sq ft |
| Coverage left | 4,400 minus 3,060 | 1,340 sq ft |
| Depth behind the house | (110 minus 10) minus (25 + 40) | 35 feet |
| Full width addition by depth | 50 x 35 | 1,750 sq ft, over the 1,340 left |
Coverage decides. The addition can be 50 feet wide by 26.8 deep (1,340 / 50), leaving 8.2 feet (35 minus 26.8) unused. Floor area is far from its cap: 2,000 + 1,340 = 3,340, which is 1,060 under 4,400. A new 300 square foot patio shrinks the addition to 1,040 (1,340 minus 300). In pavers 10 inches square or smaller it counts half, 150 (300 x 0.5), inside the 880 cap (8,800 x 0.10), so the addition can be 1,190.
A bump out is a small addition, and its wall is subject to the yards like any other. Take a different house whose rear wall stands 14 feet from the rear line, where the yard is 10. A bump out can go 4 feet deep (14 minus 10); 6 feet would put the wall 2 feet inside the yard. KZC 115.115(3)(d) lets a bay window, chimney or eave project up to 18 inches into a yard, with chimneys and bay windows no closer than 4 feet to a property line, and caps those elements, eaves and cornices aside, at 25 percent of the facade length (50 x 0.25 = 12.5 feet).

When the old house sits inside today’s yards
Say the worked house’s left wall stands 4 feet from a side line where RS wants 5. KZC 162.35(7), as printed in Ordinance O-4905, says that structurally altering a roof or exterior wall that misses the height or required yard standards means it must be brought into conformance; repair or maintenance of structural members is excepted. Whether opening that wall to join an addition counts is a question for a planner, in writing. If it does, the wall steps in 1 foot (5 minus 4). Any other nonconformance must be corrected under KZC 162.35(13) when 12 months of work on that improvement, or one that supports it, costs more than 50 percent of its replacement cost.
Land within 200 feet of Lake Washington’s ordinary high water mark is shoreline jurisdiction, with a setback of its own. In the shoreline program as Ecology approved it on September 21, 2020 (Ecology-hosted copy of KZC 83, current through Ordinance 4781) I read that a detached house built before December 1, 2006 may be enlarged inside the shoreline setback without a variance, by a footprint of up to 10 percent of its gross floor area, no farther toward the water, with a restoration plan and a first check of whether KZC 83.380 allows a reduced setback: 2,000 x 0.10 = 200 square feet. I did not read the current chapter, which controls. My Kirkland waterfront page covers the lake.
Kirkland addition permit: what the city asks to see
The city says a building permit is required to construct or modify a building, applied for online through MyBuildingPermit.com. A pre-submittal conference is optional (city process page). Here is what its documents ask of the worked addition.
| Item | What the city’s document says | On the worked addition |
|---|---|---|
| Site plan and calculations (site plan guide) | Property lines, easements, distances from every building to every property line, topography at 2 foot contours, and lot coverage in subtotals for buildings, driveways and walkways. Floor area by structure and floor. | Coverage 2,000 + 1,340 + 1,060 (640 + 120 + 300) = 4,400. Floor area 2,000 + 1,340 = 3,340. |
| Survey (Survey Policy, 2015) | A boundary survey and a 2 foot contour topographic survey, stamped by a licensed surveyor. The boundary survey has a narrower exception (structure 2 feet inside assumed setbacks, fenced line, no dispute). The topographic survey is waived on an essentially level lot (no more than 2 feet of grade change between corners), or if the footprint changes under 25 percent with the addition under the roofline and not on lower ground, or if the design is 2 feet or more under the height limit. | 1,340 / 2,000 = 67 percent, over 25, so the footprint exception fails. This lot is flat, so the level lot exception would waive the topographic survey; a sloped lot would not. |
| Height (ABE handout, height form) | For an addition the average building elevation covers the entire structure; the checklist asks for it when the roof line changes or the addition sits on lower ground. A height table goes in with the permit, a verification form goes to the inspector at the underfloor or slab insulation inspection, and a surveyor’s height survey is due at roof sheathing if the building is within 1 foot of the limit. | The handout’s example works to 103.80 (18,060.5 / 174). |
| Trees (KZC 95.30(1)) | A tree retention plan is required unless the addition is under 50 percent of the existing footprint and nothing is built in the critical root zone of regulated trees. No tree comes out before the plan is approved. | 2,000 x 0.50 = 1,000; 1,340 is over, so a plan is needed. |
| Drainage (checklist) | A drainage plan, an erosion control plan and a construction stormwater plan at 500 square feet or more of new or replaced impervious surface. A drainage report may be required at 2,000 or more. | New 1,340. With the 640 driveway repaved, 1,980; with the 120 walk too, 2,100. |
| Street, fire, sewer, slope, rodents (checklist) | A right-of-way improvements plan by a licensed civil engineer for single family additions valued over $200,000, by the city’s Building Valuation Data Table. A sprinkler system at 5,000 square feet of gross floor area; the Fire Department checks hydrants and access when area is added. A sewer certificate if on septic and a bedroom is added. A geotechnical report on or within 25 feet of a regulated slope. A rodent abatement declaration for exterior work; a baiting program, if required, can take 2 to 6 weeks. | I did not read the valuation table; ask the city to value the addition. 2,000 + 1,340 = 3,340, under 5,000 as a rough stand-in. |
| Review (goals, 9.15.2026) | Single family addition, regular: first review 4 weeks, then 10 business days per revision. Fast Track (10 business days) is for additions up to 50 percent of existing area, with other tests (city page). | 1,340 / 2,000 = 67 percent, so regular. Two revisions add 20 business days (10 x 2), about 8 weeks of goals in all. |
The permit set starts from the house as it stands; see my existing conditions page, and my Kirkland permit fee guide for city charges.
What size of addition reaches $750,000
My smallest project is $750,000. At the planning range for additions, $350 to $650 per square foot, an addition reaches that between 1,154 square feet (750,000 / 650 = 1,153.8) and 2,143 (750,000 / 350 = 2,142.9). A 1,000 square foot addition is $350,000 to $650,000 (1,000 x 350 and 1,000 x 650), below my minimum. On the worked lot the largest ground level addition is 1,340 square feet, $469,000 to $871,000 (1,340 x 350 and 1,340 x 650), reaching $750,000 only at about $560 per square foot (750,000 / 1,340 = 559.7). Beyond that, the paths are a second floor or an addition paired with a remodel. These are planning ranges, not quotes.
How it works with me
First comes the free basic feasibility check, very quick, usually about a day. If you want more, an in depth analysis is $1,500, takes 2 to 3 weeks and goes further. Then I quote a fixed fee for design and permit, set by project budget and location, about $10,000 to $200,000 depending on scope. Design to permit submission typically takes 2 to 4 months. After the permit I administer construction; I do not build.
I have been an architect since 1996, and I am a member of the AIA (since 1992) and NCARB (since 1996). The Carr residence was featured in Above The Lake and Lux magazines.
Before you draw
Ask for the free first check
Send me the address and what you are considering through the request form above, or call or message me on WhatsApp. The first basic feasibility check is free and very quick, usually about a day.
Questions
Do I need a permit for a home addition in Kirkland?
Yes. The city says building permits are required to construct or modify a building, and applications are submitted online through MyBuildingPermit.com. Electrical work needs its own permit, and so do mechanical and plumbing work unless they are included in the building permit. A pre-submittal conference is optional. My first basic feasibility check is free and usually takes about a day.
How big can a home addition be in Kirkland?
Two caps size it: floor area ratio and lot coverage. In the RS 8.5 zone floor area is 50 percent of the lot and coverage is 50 percent, and coverage counts the driveway, walks and patio with the roof. On an 8,800 square foot lot with a 2,000 square foot house and 1,060 square feet of paving, floor area allows 2,400 more (4,400 minus 2,000) and coverage allows 1,340 (4,400 minus 3,060), so coverage decides. Source: the city’s 2022 planning packet table and KZC 115.42 and 115.90 as printed in Ordinance O-4905; the city’s current code controls, so confirm with the city.
How close to the property line can I build a Kirkland addition?
For a detached house in RS the yards are 20 feet in front, 10 at the rear, and at least 5 on each side with the two sides adding up to at least 15. In RSX the sides are 5 each with no combined total. Corner lots and lots with two street fronts have special rules. A bay window, chimney or eave may project 18 inches into a yard, and chimneys and bay windows may come no closer than 4 feet to a property line (KZC 115.115). These yard figures are from the 2022 planning packet; the city’s current code controls, so confirm them for your zone.
Does my old house have to meet today’s yards if I add on?
Not automatically, but touching a nonconforming wall can trigger it. Under KZC 162.35(7), as printed in Ordinance O-4905, structurally altering a roof or exterior wall that does not meet the height or required yard standards means that part must be brought into conformance, with repair and maintenance of structural members excepted. Other nonconformances must be corrected when 12 months of work on that improvement costs more than 50 percent of its replacement cost (KZC 162.35(13)). Ask a planner in writing how the city reads your plan.
Will I need a survey for a Kirkland addition?
Usually. The city’s Survey Policy (2015) requires a boundary survey and a topographic survey with 2 foot contours for additions, stamped by a licensed surveyor, with exceptions. The topographic survey is waived on an essentially level lot, or if the footprint changes under 25 percent, the addition stays under the existing roofline and is not on lower ground, or the design is at least 2 feet under the height limit. An addition of 1,340 square feet on a 2,000 square foot footprint is 67 percent, so the 25 percent exception does not apply.
How long does the city take to review a Kirkland addition permit?
The city’s goals, updated 15 September 2026, are 4 weeks for the first review of a regular single family addition and 10 business days for each revision before issuance. Fast Track, 10 business days, is for additions up to 50 percent of existing area, among other tests. Two revisions on a regular review are about 8 weeks of goals (4 weeks plus 20 business days). The city says actual times vary. Design to permit submission typically takes me 2 to 4 months.
How much does a home addition in Kirkland cost, and where does it reach your minimum?
I use a planning range of $350 to $650 per square foot for additions, which is not a quote. My smallest project is $750,000, which an addition reaches between 1,154 square feet (750,000 / 650) and 2,143 (750,000 / 350). A 1,000 square foot addition is $350,000 to $650,000. My fixed fee for design and permit is about $10,000 to $200,000, depending on scope.
Does Washington require an architect for a home addition, and do you build it?
Washington’s architect licensing law does not stop anyone from doing design work for a residential building of up to four dwelling units (RCW 18.08.410(5)), so an architect is your choice. Piper Cole Architects designs the addition and administers construction for you; we do not build.
What does the feasibility check cost?
The first basic feasibility check is free and very quick, usually about a day. An in depth analysis is $1,500, takes 2 to 3 weeks and goes further. If you go ahead, I quote a fixed fee for design and permit, set by project budget and location.