What a Kirkland architect can design on your lot is largely set before the first sketch: yards on four sides, a floor area cap that counts the garage, a lot coverage cap that counts the driveway, a height limit measured from average building elevation and, on a lake lot, a shoreline setback. On the worked lot below (12,500 square feet, zone RS 12.5) floor area caps a new house at 4,375 square feet while coverage has 2,200 to spare. My first basic feasibility check is free and very quick, usually about a day: send me the address and what you are thinking of building. An in depth analysis is $1,500, takes 2 to 3 weeks and goes further. My practice is based in Kirkland, Washington; I design and administer construction and do not build.
Key takeaways
- Four limits size a Kirkland house: yards, floor area ratio, lot coverage and height. On my worked lot the floor area cap (12,500 x 0.35 = 4,375 square feet) binds well before coverage (6,250 allowed, 4,050 used). These figures are from a 2022 planning packet draft; the city’s current code controls.
- The city’s review goals, updated 15 September 2026, are 4 weeks for a regular first review of a new house (7 in a shoreline area) and 10 business days per revision: about 8 weeks with two revisions (11 in a shoreline area). The city says actual times vary.
- Kirkland asks for 50 tree credits per acre on a new house: 12,500 / 43,560 x 50 = 14.35, so 14 credits. Keeping one 20 inch native conifer is worth 9 (6 x 1.5).
- A Lake Washington lot adds a shoreline setback measured from the water. In the R-L (B) environment it is 30 percent of the average parcel depth, never under 30 feet or over 60.
Who this page is for
This page is for an owner or buyer of a Kirkland house or lot who is choosing a residential architect in Kirkland and wants to know, before paying for design, what the city lets the project be. Each source was read on 5 November 2026: City of Kirkland pages and PDFs, Ecology’s hosted shoreline program and the state’s RCW site. The city’s online code site sits behind a bot check and was not used. The yard, floor area and coverage figures come from the draft density table in a City Planning Commission packet dated August 18, 2022 (it proposes code amendments; the adopted version was not read), and the text of KZC 95.30, 95.34, 115.42, 115.90, 115.115 and 162.35 comes from Ordinance O-4905, signed June 17, 2025; later changes, if any, are unread. The table is from 2022, so the city’s current code controls; confirm each number with Planning at 425 587 3600. This is general information, not legal advice. Washington’s architect licensing chapter does not reach design work on a residential building of up to and including four dwelling units (RCW 18.08.410(5)), so hiring an architect is your choice.
Request your free feasibility check
Send me the address, whether you are thinking of a remodel, an addition or a new house, and what you want from it. I will reply to you personally.
Prefer to talk? Call 425 753 6452 or message David on WhatsApp.

Free feasibility check
Planning a custom home or a remodel of $750,000 or more?
Send me the address and a few lines about what you want. The first feasibility check is free and usually takes about a day.
Kirkland architect: the permit path
The city describes the path on its single family and duplex permit page. Here it is for a new house.
| Step | What the city says | What it means for a new house |
|---|---|---|
| 1. Research | Look up tax and permit history and the zoning district; maps.kirklandwa.gov has zoning, topography and permit history. | The city’s own records for any address. |
| 2. Pre-submittal conference | Optional for single family, booked through MyBuildingPermit.com at least 10 business days ahead; single family meetings run Tuesday and Thursday at 2 p.m. | The city says it may be useful. |
| 3. Application | Applications go in online through MyBuildingPermit.com. The checklist asks for a plan set at 1/8 inch scale: site plan, survey, architectural and structural drawings, energy sheets, and a geotechnical report on soft soils or landslide or seismic hazard. | The site plan carries yards, coverage and floor area calculations, average building elevation and the tree plan (site plan guide). |
| 4. Other permits | Demolition is a separate permit. On new construction the building permit covers electrical, mechanical and plumbing work; a fire sprinkler system needs its own permit. | A teardown means two permits; if a rodent baiting program is required it can take 2 to 6 weeks. |
| 5. Review | New construction, regular: 4 weeks first review, 10 business days per revision. Shoreline, Goat Hill or Holmes Point: 7 weeks. Demolition: 15 business days first review (goals, updated 9.15.2026). | 4 weeks + 2 x 10 business days (4 weeks) = 8 weeks of goals; in a shoreline area 7 + 4 = 11 weeks. |
Footnotes say a SEPA determination or third party structural review adds time. The goals table also lists a High Performing Building review with a first review goal of 10 business days; regular times apply if SEPA, Shoreline, Goat Hill or Holmes Point applies. The city says actual times vary. For the wider picture see my Kirkland building permit guide and Kirkland permit fee guide.
What a Kirkland home architect checks first
Kirkland’s low density zones are RS, RSX and RSA; in RS and RSX the number is the minimum lot size in thousands of square feet, so RS 12.5 means 12,500. The city’s Zoning Code FAQ says to read the yards across the density table row and the height in its last column. The four limits that size a house:
| Limit | What the source says | On the worked lot |
|---|---|---|
| Yards (KZC 15.30, 2022 packet draft) | RS detached house: front 20 feet, rear 10, sides 5 with the two sides totaling at least 15. RSX needs 5 on each side. Corner lots and lots with two street fronts have special rules. Bay windows, chimneys and eaves may project 18 inches into a yard, but bay windows and chimneys no closer than 4 feet to a property line (KZC 115.115(3)(d)). | Width 100 minus 15 = 85; depth 125 minus 30 = 95; 85 x 95 = 8,075 square feet of envelope |
| Floor area ratio (packet note DD-12, KZC 115.42) | 35 percent of lot size in RS 12.5, 50 percent in RS 8.5 and 7.2, 20 percent in RS 35. In the former Houghton area the city checklist says to ask a planner whether FAR calculations apply. It counts the area inside the exterior walls on every level, attached garage included. It leaves out attic area under 5 feet of ceiling, floor area with a ceiling under 6 feet above finished grade, uncovered decks, and porches open on three sides. A ceiling over 16 feet counts the floor twice. | 12,500 x 0.35 = 4,375 square feet |
| Lot coverage (KZC 115.90) | 50 percent in RS. It counts every structure and all hardscape, so the driveway, walk and patio count with the roof. Pavers 10 by 10 inches or smaller, grassed grid pavers and artificial turf count half, up to 10 percent of the lot. | 12,500 x 0.50 = 6,250 square feet |
| Height | Measured above average building elevation, a formula in KZC 115.59. The copy of the table that was read is cut off at the height column. A June 10, 2022 city staff memo lists the neighboring RS 8.5 zone as “25-foot max height”. | I give no RS 12.5 figure; ask Planning for it |
Worked lot: a new house on 12,500 square feet
I worked one hypothetical lot, not a real property or a client’s: 100 feet wide and 125 deep, 12,500 square feet (100 x 125), flat, zone RS 12.5, no shoreline or critical area. The new house is two stories with an attached garage: a 50 by 50 foot footprint of 2,500 square feet, garage included, and an upper floor of 1,875 square feet. The driveway is 20 by 45 feet (900 square feet), the front walk 150 and the rear patio 500.
| Step | Arithmetic | Result |
|---|---|---|
| Floor area cap | 12,500 x 0.35 | 4,375 sq ft |
| Floor area counted | 2,500 + 1,875, no exemption taken | 4,375 sq ft, at the cap |
| Coverage cap | 12,500 x 0.50 | 6,250 sq ft |
| Coverage used | 2,500 + 900 + 150 + 500 | 4,050 sq ft |
| Coverage left | 6,250 minus 4,050 | 2,200 sq ft |
| Envelope check | 50 x 50 = 2,500 inside 85 x 95 = 8,075 | Fits |
Floor area decides this lot. Four design choices move the count. A 20 by 20 foot great room with an 18 foot ceiling counts as 800 square feet (2 x 400), leaving 3,575 (4,375 minus 800) for the rest of the house. The code gives one exemption of 100 square feet for a house with an internal staircase or a ceiling over 16 feet (KZC 115.42(1)(g)); this two story house has a staircase, so it may take 100 off the count (4,275 counted), but it is not applied here, and how it combines with the doubling is a question for a planner. KZC 115.42(4) adds five percent F.A.R. if two of three design elements are used: 4 in 12 peaked ridges, side yards of at least 7.5 feet, or an upper floor cut by 15 percent of the ground floor (2,500 x 0.15 = 375; this upper floor is 625 smaller, so it meets that one). The text does not say if five percent means 5 points of lot size (625 square feet) or 5 percent of the cap (219). A basement with its ceiling under 6 feet above finished grade, measured outside the building, does not count; one that rises higher does.
The permit set carries a height table and average building elevation figures. The Survey Policy adds a height verification form at the underfloor or slab insulation inspection, and a licensed surveyor’s height survey at roof sheathing if the building is within one foot of the maximum.
Trees, drainage and the street
Under KZC 95.30 a tree retention plan is required for a building, demolition or land surface modification permit, unless the permit is an addition or remodel under 50 percent of the existing footprint with no work in the critical root zone of regulated trees. No tree may come out before the plan is approved, and the city does not require retention that would cut allowed floor area or coverage.
For replanting, KZC 95.34 sets 50 tree credits per acre on single family lots: on the worked lot 12,500 / 43,560 = 0.287, times 50 = 14.35, rounded to 14. A retained 20 inch native conifer is worth 6 credits, times 1.5 for a native conifer, which is 9. That leaves 5 credits (14 minus 9), or five new trees worth one credit each; the minimum for one credit is a 6 foot conifer or a 2 inch caliper broadleaf tree.
Public Works adds three items on the checklist. A drainage plan, an erosion control plan and a construction stormwater plan are required at 500 square feet or more of new or replaced impervious surface, and a drainage report may be required at 2,000 or more; the worked lot has 4,050 square feet of roof and paving (2,500 + 900 + 150 + 500), over both lines. A right-of-way improvements plan by a licensed civil engineer is required for every new single family house; it covers items such as sidewalks, curbs, planter strips and street trees. A sprinkler system is required at 5,000 square feet of gross floor area as the Kirkland Municipal Code defines it; ask the Fire Department how a basement counts.

Lake Washington lots and slopes, in brief
Land within 200 feet of the ordinary high water mark of Lake Washington is shoreline jurisdiction, and the program in KZC 83 sets its own numbers. The copy read was the Ecology-hosted copy (approved September 21, 2020, current through Ordinance 4781; later changes unread). The setback is measured landward from the water and depends on your lot’s shoreline environment. In R-L (A) it is the average of your two neighbors’ setbacks, never under 15 feet. For R-L (B) it is 30 percent of the average parcel depth, not less than 30 feet and not required to be more than 60. Environments C through J use other percentages. On a lot with a 140 foot average parcel depth in R-L (B) that is 42 feet (140 x 0.30); at 90 feet of depth, 27 rounds up to the 30 foot minimum; at 250, 75 is held to the 60 foot cap. The shoreline chart also gives 50 percent coverage and 30 feet above average building elevation for single family; where the zone’s own height limit is lower, the lower one applies. My Kirkland waterfront page and the shoreline exemption guide cover the lake.
The city’s site plan guide asks for any slope of 15 percent or more and for creeks, streams, ponds or wetlands within 100 feet of the lot, and the checklist asks for a geotechnical report on or within 25 feet of a regulated slope. The city’s critical area chapters were not read, so a lot with either needs its own check.
If you are keeping the house
The same limits apply to a remodel or addition, with one more rule. KZC 162.35(7), as printed in Ordinance O-4905, says structurally altering a roof or exterior wall that does not meet the height or required yard standards means it must be brought into conformance; repair or maintenance of structural members is excepted. Ask a planner, in writing, whether your plan triggers it. My pages on each project type: whole house remodels, additions, second floors, custom homes and backyard cottages. My Kirkland zoning guide covers the zones.
What to send me
The address or parcel number is enough to start. It helps to add:
- A remodel, an addition or a new house, and the changes you want.
- Any survey, existing drawings or permit history you already have.
- Whether the lot touches Lake Washington, has a slope, or has a stream or wetland nearby.
- Whether you are buying, and when your inspection period ends.
How it works with me
The first basic feasibility check is free and very quick, usually about a day. If you want more, an in depth analysis is $1,500, takes 2 to 3 weeks and goes further than the first check. If you go ahead, my fee for design and permit is fixed and agreed before design starts. Design to permit submission typically takes 2 to 4 months. After the permit I administer construction for you; I do not build.
I have been an architect since 1996, and I am a member of the AIA (since 1992) and NCARB (since 1996).
Before you draw
Ask for the free first check
Send me the address through the request form above, or call or message me on WhatsApp. The first basic feasibility check is free and very quick, usually about a day.
Questions
How do I choose a Kirkland architect for a remodel or a new house?
Ask for your lot’s numbers before design: yards, floor area ratio, lot coverage, height, shoreline setback and tree credits. Ask how the fee is set and who administers construction. My fee is fixed and agreed before design starts, and I administer construction; I do not build. Washington’s architect licensing chapter exempts design work on a residential building of up to and including four dwelling units (RCW 18.08.410(5)), so the choice is yours.
What does a residential architect in Kirkland check before design starts?
The zone and its yards, the floor area and coverage caps, the height limit, any shoreline setback, slopes, streams or wetlands, and the trees. My first basic feasibility check is free and very quick, usually about a day. An in depth analysis is $1,500, takes 2 to 3 weeks and goes further.
How big a house can I build on my Kirkland lot?
It depends on the zone. In RS 12.5 floor area is capped at 35 percent of the lot and coverage at 50 percent, so a 12,500 square foot lot allows 4,375 square feet of floor area, garage included, and 6,250 of coverage. In RS 8.5 floor area is 50 percent. Those caps are from a draft table in the city’s 2022 planning packet, and the counting rules from KZC 115.42 and 115.90 as printed in Ordinance O-4905; the city’s current code controls, so confirm with Planning at 425 587 3600.
How long does the City of Kirkland take to review a new house permit?
The city’s goals, updated 15 September 2026, are 4 weeks for a regular first review of new single family construction, 7 weeks in a shoreline, Goat Hill or Holmes Point area, and 10 business days for each revision. Two revisions on a regular review make about 8 weeks (4 weeks plus 20 business days); in a shoreline area, 11. SEPA and third party structural review add time, and the city says actual times vary.
Do I need a survey for a Kirkland building permit?
Usually. The city’s Survey Policy (2015) requires a boundary survey and a topographic survey with two foot contours for new structures and additions, signed by a Washington licensed surveyor, with exceptions. The topographic survey is waived on an essentially level lot, with no grade change over two feet between corners, or when the design is two feet or more under the maximum height.
How does a Lake Washington lot change what I can build in Kirkland?
A shoreline setback is measured landward from the water, and in the R-L (B) environment it is 30 percent of the average parcel depth, not under 30 feet or over 60. A 140 foot average depth gives 42 feet. The shoreline chart also sets 50 percent coverage and 30 feet above average building elevation for single family, and the lower of that and the zone’s height limit applies. The first review goal is 7 weeks. The 2020 Ecology-hosted program was read, not later changes.
How do trees affect a new house in Kirkland?
A tree retention plan is required for a building, demolition or land surface modification permit unless the work is a small addition or remodel with nothing in the critical root zone. For replanting the city asks for 50 tree credits per acre, so a 12,500 square foot lot needs 14. A retained 20 inch native conifer is worth 9. No tree may be removed before the plan is approved.
What does the feasibility check cost, and do you build?
The first basic feasibility check is free and very quick, usually about a day. An in depth analysis is $1,500 over 2 to 3 weeks. If you go ahead, I quote a fixed fee for design and permit, agreed before design starts. Piper Cole Architects designs and administers construction. We do not build.