Woodinville remodels
Whole house remodel architect in Woodinville, WA
What decides a whole house remodel inside the City of Woodinville, where King County takes over, what the city says review takes, what design costs, and what to ask any architect before you sign.
On this page
- City of Woodinville or King County: settle this first
- The percentage tests that decide a whole house remodel
- Roof coverage and shoreline surface: two worked lots
- Streams, slopes, floodplain and trees
- What the city publishes about review time
- What changes the cost and the schedule
- What to ask any architect before you sign
- How the work runs, in order
- Questions
Key takeaways
- A legally nonconforming Woodinville house keeps its nonconforming features, such as a short side yard, only until a remodel removes more than 50 percent of the exterior wall framing, by length (WMC 21.14.050, 21.11A.200).
- On the Sammamish River and Little Bear Creek the wall line is 60 percent, and a remodel costing 50 percent or more of replacement cost can pull a nonconforming site entirely under shoreline rules (WMC 21.73.080).
- The city’s FAQ lists 2 to 5 weeks of review for a single family addition or alteration. The code’s outer limit for a construction permit is 120 days from the completeness decision (WMC 21.80.210).
- My fee for design and permit is fixed, about $10,000 to $200,000, set by project budget and location. The first feasibility check is free and takes about a day.
- Piper Cole Architects is based in Kirkland. It designs and administers construction. It does not build.
Short answer: I design whole house remodels in Woodinville for a fixed fee, about $10,000 to $200,000 depending on the project budget and location, and the first feasibility check is free and takes about a day. Before you pay for drawings, your architect should settle whether your parcel is inside the City of Woodinville at all, whether the house is legally nonconforming and how much wall framing your plan removes, and whether the lot touches the Sammamish River, Little Bear Creek, a stream, a wetland, a steep slope or the floodplain.
This page is for a Woodinville owner with a remodel budget of $750,000 or more who is comparing architects. Piper Cole designs and administers construction on your behalf and does not build. City rules come from the Woodinville Municipal Code (WMC), current through Ordinance 811 (August 4, 2026), and the city’s own FAQ and permit pages, read on 19 October 2026. County rules come from King County Code Title 21A, updated September 9, 2026. Confirm any number with the city. Zoning tables, setbacks and tree credits are in my Woodinville zoning and permit guide; this page covers what decides a remodel.
City of Woodinville or King County: settle this first
Not every Woodinville address is in the city. The city’s own FAQ says a property with a Woodinville mailing address may sit in unincorporated Snohomish County or unincorporated King County. Inside the city, the Building Official decides your permit under WMC Title 21. I read nothing from Snohomish County. The county side differs:
| Question | City of Woodinville (WMC) | Unincorporated King County (K.C.C. 21A) |
|---|---|---|
| Remodeling a house that breaks a current rule | Allowed if the work adds no nonconformance and no new bulk or area to the parts that cause it. Protection ends on substantial destruction (21.14.050). | Reviewed through code compliance review if it does not expand the nonconformance (21A.32.055). Expansion of area, impervious surface or height can be approved up to 10 percent, cumulatively (21A.32.065). I found no wall framing percentage. |
The percentage tests and permit clocks below are the city’s. After a fire or other casualty, the city can let a rebuild keep its nonconformance if a complete application comes within 3 years (21.14.050(6)); the county’s window is 12 months (21A.32.045).
The percentage tests that decide a whole house remodel
Woodinville’s code uses several percentage tests, and each measures something different. A plan can clear one and fail another.
| Test | What is measured | The line | What happens past it |
|---|---|---|---|
| Nonconforming house (WMC 21.11A.200, 21.14.050) | Exterior wall framing removed, by horizontal length | More than 50 percent | Nonconformance is lost. Later work must bring the whole structure to current rules. |
| Same test on the shoreline (WMC 21.70.228, 21.73.080) | Exterior walls by length, framing and foundations counted | More than 60 percent | Same result, under the shoreline master program. |
| Nonconforming shoreline site (WMC 21.73.080(6)) | Construction cost against replacement cost, or share of the site altered outside building footprints | 50 percent or more of either | The entire site must comply with the shoreline program. |
| Native growth protection area (WMC 21.51.050(5)) | Substantial improvement: cost against market value | 50 percent or more | Where the lot has them and the city applies the rule to a remodel, wetlands, wetland buffers and most habitat areas go into a recorded protected tract. |
| Flood hazard area (WMC 21.53.050, 21.53.140) | Substantial improvement: cost against market value | 50 percent or more | Where a base flood elevation is mapped, the lowest floor, basement included, sits at least 1 foot above it. |
The nonconforming tests apply only to a house that was lawful when built and later fell out of step with the code, and the owner must prove that (WMC 21.14.030). The code does not say how the city finds market value; for the shoreline test it defines replacement cost as square footage times local building cost per square foot, or a similar method (21.70.227). The shoreline cost test counts construction costs until 24 months after the permit is finalized, without taxes or permit fees (WMC 21.70.228). That rule also says reconstruction, which the code defines by replacement cost, so ask which test applies.
The arithmetic on a plain house: a 40 by 60 foot house has 200 feet of exterior wall (2 x (40 + 60)). Fifty percent is 100 feet, so a plan that takes out more than 100 feet of framing ends the protection. On the shoreline the line is 120 feet (200 x 0.6). Partial removal counts as if the whole wall along that length came out, and swapping a window or door counts only if beams or struts come out. A $750,000 scope reaches 50 percent when the house’s replacement cost or market value is $1,500,000 or less ($750,000 divided by 0.5). These are illustrations, not rulings. The permit valuation is a third number: the code has the applicant estimate it, design work included (WMC 21.62.060(2)).

Roof coverage and shoreline surface: two worked lots
An R-6 lot, 8,000 square feet. The city caps building coverage, the horizontal surface of roof areas covering structures (WMC 21.11A.030), and requires a minimum share of landscaping. For an R-6 lot of 5,000 to 9,999 square feet, Table 21.32.050(1) allows 50 percent roof and requires 25 percent landscaping: 4,000 square feet of roof (8,000 x 0.50) and 2,000 of landscaping (8,000 x 0.25). If the house, garage and covered entry already total 3,300 square feet of roof, an addition has 700 (4,000 to 3,300), before setbacks and other limits, which may cap it sooner. That leaves 2,000 square feet (8,000 to 4,000, 2,000) for driveway and terraces, and pervious pavement does not count as landscaping.
A river lot, 100 by 200 feet. On the Sammamish River and Little Bear Creek, shoreline jurisdiction reaches 200 feet landward of the ordinary high water mark, and further where a floodway, floodplain or associated wetland extends it (WMC 21.70.050). Impervious surface is capped on the lot area inside it (21.74.020). The first 100 feet landward is the Conservancy environment. Beyond it the city’s map assigns Residential, Urban Conservancy or Urban General (21.71.030 to 21.71.080). Take a lot whose 100 foot side fronts the water, with all of it inside jurisdiction and Residential beyond the first 100 feet. Each part takes its own percentage, and the total may be spread across the lot if the Conservancy part stays within its own limit (21.74.020(3)).
| River | Conservancy part, 10,000 sq ft | Residential part, 10,000 sq ft | Total allowed |
|---|---|---|---|
| Sammamish River | 10,000 x 0.15 = 1,500 sq ft | 10,000 x 0.50 = 5,000 sq ft | 6,500 sq ft |
| Little Bear Creek | 10,000 x 0.15 = 1,500 sq ft | 10,000 x 0.30 = 3,000 sq ft | 4,500 sq ft |
A detached house is a prohibited use in the Conservancy and Urban Conservancy environments and permitted in Residential and Urban General (WMC 21.72.030). If yours stands in a prohibited one, the shoreline rule for nonconforming uses says floor area and every other element may not be expanded, except through an unclassified use approval (21.73.080(4)(b)). I found no published reading of how the city applies that to a remodel, so ask before design. My shoreline exemption guide covers the permit path.
Streams, slopes, floodplain and trees
Critical areas. The city’s map is a guide, and a site investigation decides what is on your lot (WMC 21.51.030(3)). A remodel of an existing structure needs no critical area review if it adds no footprint in the critical area or buffer, intrudes no further and adds no significant risk (21.51.040(6)). A building stays at least 10 feet from a riparian zone or wetland and its buffer unless the director reduces it (21.51.050(3)), and development in an erosion or landslide hazard area needs a geotechnical report (21.51.110(4)). If the job needs a critical area or shoreline decision first, the city treats an earlier building application as incomplete unless you choose consolidated review or the director waives the rule (21.80.035, 21.80.040).
Trees. A project that needs a construction permit also needs a tree permit, unless the remodel removes no trees, does not alter or expand the footprint and has tree protection in place (WMC 21.50.030(1)(g), 21.50.050(1)). The arborist report covers trees within 50 feet of the construction limits and any neighbor’s trees whose canopy overhangs them (21.50.050(2)). Heritage and specimen trees may not be removed except under the city’s Heritage Tree Program (21.50.020(4)).
What the city publishes about review time
The city’s permitting FAQ lists current turnaround times. It is undated and does not say whether a range is one round or the whole review.
| Permit | City FAQ, time to review |
|---|---|
| Building, single family addition or alteration | 2 to 5 weeks |
| Building, single family new | 4 to 7 weeks |
| Demolition | 0 to 4 weeks |
| Land use permits | Generally 120 days from the completeness letter to a decision |
The code sets its own clocks in calendar days, counted from the completeness decision and stopped while the city waits on you (WMC 21.80.210).
| Decision type (WMC 21.80.050) | Code clock | Examples in the city’s table |
|---|---|---|
| Type 1 | 65 days | Building permit, critical area determination or alteration, tree removal permit, shoreline exemption, flood improvement permit |
| Type 2 | 100 days | Shoreline substantial development permit |
| Type 3 | 170 days | Variance, shoreline variance, shoreline conditional use permit |
| Any construction permit | No more than 120 days | The outer limit, building permits included |
Staff must send a completeness notice within 28 days of accepting an application, or it counts as complete on day 29 (WMC 21.80.100). After a correction notice you have 90 days to answer, with extensions of up to 90 days each at the director’s discretion, or the application is void, and once the city approves you have 90 days to pick the permit up, with one extension of up to 90 (21.80.230). A permit is valid for 24 months, with one extension of up to 12 if work has not stopped (21.62.085). Construction time depends on scope, so ask each builder for a written schedule.
Applications go through the city’s online Permit Portal. The city issues the permit online once it has your contractor’s Washington license and a Woodinville business license. A pre-application meeting is optional and held Wednesdays at 9 and 10 am; the city says it flags fatal flaws. Plan review is usually 65 percent of the building permit fee, per the FAQ. I could not read the 2026 fee schedule, so I give no total. City fees sit outside my fee.
What changes the cost and the schedule
| Item | Planning figure | What moves it |
|---|---|---|
| Design and permit fee | Fixed fee, about $10,000 to $200,000 | Project budget and location. |
| Whole house renovation | $300 to $550 per sq ft | Condition of the structure, how much of the plan changes, new systems, site access. |
| Additions | $350 to $650 per sq ft | New foundation, roof and envelope, and the soils and slope conditions. |
| Design to permit submission | Typically 2 to 4 months | Survey, existing conditions, engineering and your decisions. |
| City review | See the tables above | Permit type, completeness of the first submission, comments, and any decision that must come first. |
Planning ranges from Piper Cole, before design fees, permits, sales tax and contingency. They are not quotes. At those ranges, $750,000 of construction renovates roughly 1,364 to 2,500 sq ft ($750,000 divided by $550, and by $300). The million dollar remodel guide shows where the money goes. Here, a nonconforming wall, river frontage, a buffer, a floodplain line or a tree report can add scope or time, and opening walls may bring a structural engineer.
What to ask any architect before you sign
- Is my parcel inside the City of Woodinville, and how will you confirm it?
- Is my house legally nonconforming, and how many feet of exterior wall does your plan remove? A good answer gives a number against 50 percent.
- Does any part of my lot sit in shoreline jurisdiction, a buffer, a steep slope or the floodplain? Ask which cost tests apply.
- Will I need a tree permit and an arborist report?
- Is the fee fixed, and is it set before drawings start? Ask what happens if the budget moves.
- What sits outside the fee? A surveyor, structural, geotechnical and civil engineers, an arborist and the city’s permit fees are the usual items.
- Which permits come first, and can they be filed together? Ask about consolidated review.
- Do you administer construction, and do you build? I administer for you and do not build, so the person judging the work is not doing it.
How the work runs, in order
| Step | Typical time | What you get |
|---|---|---|
| Free feasibility check | About a day | Whether the plan fits the lot, the code and the budget at a basic level. |
| In-depth analysis, if you want it | $1,500, 2 to 3 weeks | A deeper look at zoning, code and budget. |
| Design to permit submission | Typically 2 to 4 months | Drawings, engineering and the permit set, filed on the city’s Permit Portal. |
| City review | See the review tables | Comments, revisions and an issued permit. |
| Bidding and construction | Set by scope and builder | Builder pricing, a contract, and my administration of construction on your behalf. |
I have worked as an architect since 1996, I am an AIA member since 1992 and an NCARB member since 1996, and I take on 20 to 30 projects a year. I have won three Masonry Excellence Awards, for commercial projects. The Carr residence was featured in Above The Lake and Lux magazines. My office is in Kirkland, and the remodels I take on start at $750,000.