Key takeaways
- In Newcastle, Washington’s R-4 and R-6 zones a house can be 30 feet tall with 35 percent building coverage, 40 percent impervious surface and yards of 10 feet front, 20 rear and 5 each side.
- There is no floor area cap. On a 10,000 square foot R-4 lot the roof can cover 3,500 square feet, but the 4,000 square foot impervious limit usually binds first.
- Ordinance 2026-683 (February 2026) widened stream buffers, set Lake Boren at 110 feet and added a 10 foot setback from every buffer. A steep slope buffer is at least 10 feet with a geotechnical report, 50 without.
Short answer: in Newcastle, Washington’s R-4 and R-6 zones, the code lets you build up to 30 feet tall, 10 feet from the street, 20 feet from the rear line and at least 5 feet from each side line. Roof can cover 35 percent of the lot, and roof plus driveway, walks and patios 40 percent. If the lot has a steep slope, an old coal mine, a stream, a wetland or large trees, those rules usually decide the design before the zone does.
This is the City of Newcastle in King County, between Bellevue, Renton and Issaquah, not Newcastle, Oklahoma or Newcastle upon Tyne. My work here is on my Newcastle architect page; the neighbors are in my Bellevue, Issaquah and Redmond guides.
The city’s code host blocks automated readers, and I did not get around that. Figures come from the city’s own copies of Ordinance 2025-671 (June 17, 2025) and Ordinance 2026-683 (February 17, 2026), its April 8, 2026 fee schedule and city pages, read October 13, 2026; a mirror is labelled. Confirm every number with the city.
Newcastle’s residential zones and the zoning map
Title 18 of the Newcastle Municipal Code (NMC) is the zoning code. R-1, R-4 and R-6 are the single-family zones; R-12 and R-24 are multifamily. Base density is 1 home per acre in R-1, 4 in R-4 and 6 in R-6. An R-1 lot under 15,000 square feet follows the R-4 standards (footnote 7).
| Zone | New lot minimum | Front / side / rear yard | Building / hard surface / impervious | Height |
|---|---|---|---|---|
| R-1 (1 home per acre) | 40,000 sq ft, 100 ft wide | 30 ft / 10 ft / 25 ft | 15% / 20% / 20% | 30 ft |
| R-4 (4 homes per acre) | 7,500 sq ft, 60 ft wide | 10 ft / 5 ft, 15 ft total / 20 ft | 35% / 45% / 40% | 30 ft |
| R-6 (6 homes per acre) | 6,000 sq ft, 50 ft wide | 10 ft / 5 ft, 15 ft total / 20 ft | 35% / 45% / 40% | 30 ft |
Source: NMC 18.12.030(A), Ordinances 2025-671 and 2026-683.
Finding your zone. The code refers to the city’s adopted zoning map (table footnote 4); a mirror of chapter 18.04 says the official copy is on file with the city clerk. The Codes and Plans page links no stand-alone map and I did not confirm a zoning layer in its Maps and Data portal. Ask Community Development to confirm your zone in writing.
Yards, coverage and height by zone
- Side yards total at least 15 feet, with no interior side yard under 5 feet and no street side yard under 10 (footnote 12). With an ADU on the lot, the footnote says side setbacks add to 10 feet for the ADU only; confirm how the city applies that.
- Garage. A garage or carport needs 20 feet of driveway to the street line (footnote 8), though the house can stand 10 feet back.
- Projections (NMC 18.12.160). Eaves reach 18 inches into side and rear yards and 24 into the front. Uncovered decks and patios no higher than 18 inches may reach 15 feet into the rear yard, leaving 5 feet to the line (20 minus 15). Covered porches may reach 5 feet into the front yard, leaving 5 (10 minus 5).
Height is 30 feet in R-1, R-4 and R-6. The city draws the smallest rectangle around the building, averages the ground elevations at the midpoints of its four sides, and measures from that average to a flat roof’s highest point or to the mean height between eaves and ridge on a pitched roof. With midpoints at 108, 96, 102 and 102 feet the average is 102 (408 divided by 4). Eaves 22 feet and a ridge 36 feet above that give a mean of 29 ((22 plus 36) divided by 2), which passes (footnote 23).
How big a house the rules allow: a worked lot
The density table lists floor area ratio as N/A in R-1, R-4 and R-6, so house size comes from three limits. Building coverage is roof area, ignoring eaves of 18 inches or less. Impervious surface is roofs, walkways, patios, driveways and other hard ground; porous and grid pavers count at 50 percent. Hard surface adds permeable pavement and vegetated roofs. Footnote 5 lets impervious surface rise to the hard surface limit only where permeable surfaces are infeasible.
| Limit on an 80 by 125 foot R-4 lot (10,000 sq ft) | Rule | Arithmetic | Result |
|---|---|---|---|
| Building width between side yards | Side yards total at least 15 ft | 80 to 15 | 65 ft |
| Building depth between front and rear yards | 10 ft front, 20 ft rear | 125 to 10, 20 | 95 ft |
| Building coverage | 35% | 10,000 x 0.35 | 3,500 sq ft |
| Impervious surface | 40% | 10,000 x 0.40 | 4,000 sq ft |
| Hard surface, where permeable surfaces are infeasible | 45% | 10,000 x 0.45 | 4,500 sq ft |
| Left for driveway, walks and patio if the roof covers 3,500 | Impervious cap less roof | 4,000 to 3,500 | 500 sq ft |
The envelope is 6,175 square feet (65 x 95), but coverage stops the roof at 3,500, and a full 3,500 footprint leaves 500 square feet of impervious surface for everything else. A more usual plan, a 2,600 square foot footprint, a 450 square foot driveway (18 x 25) and 700 square feet of walks and patio, totals 3,750 square feet (37.5 percent), with 250 to spare. Two stories on that footprint is 5,200 square feet above grade (2,600 x 2), plus any basement; zoning sets no cap.
Free feasibility check
Planning a custom home or a remodel of $750,000 or more?
Send me the address and a few lines about what you want. The first feasibility check is free and usually takes about a day.
Steep slopes, landslides and coal mine hazards
Critical areas are chapter 18.24, rewritten by Ordinance 2026-683. A site with a critical area, a buffer or a building setback needs a critical area report unless the city waives it (NMC 18.24.110), and you must disclose critical areas within 300 feet (18.24.090). The city says only a qualified professional’s survey confirms one on your lot.
- Steep slopes are 40 percent or steeper with at least 10 feet of vertical change. The city sets the buffer from a geotechnical engineer’s or geologist’s report, never under 10 feet; with no report it is 50 feet. Buffers cannot be averaged, and removing vegetation is prohibited unless part of an approved alteration or temporary at the toe (NMC 18.24.300). Add the 10 foot building setback of 2026 (NMC 18.24.180(B)): at least 20 feet from the slope edge with a report (10 plus 10), 60 without (50 plus 10).
- Landslide hazard areas include land steeper than 15 percent with silt and clay soils and seepage, and ground that has moved since the last ice age. The buffer is 50 feet if no geotechnical report is filed (NMC 18.24.270).
- Coal mine hazard areas. Land over old workings is declassified (typically deeper than 300 feet), moderate (typically 0 to 300 feet) or severe (typically 0 to 150 feet, or where openings and sinkholes exist). Nothing may be altered until the city accepts a hazard assessment by a professional engineer. Moderate areas allow building when structural risk is minimized; severe areas allow a short list, such as a building under 4,000 square feet with no living quarters, unless a mitigation plan supports more (NMC 18.24.200 to 18.24.208).
A reasonable use exception exists if the rules would deny all reasonable economic use of the lot; the 2026 fee is $8,058. See my sloped lot guide.
Streams, wetlands, Lake Boren and the shoreline
The 2026 update set stream buffers, measured from the ordinary high water mark, at 200 feet for Type S, 150 for Type F, 100 for Type Np and Type Ns, and 110 for Lake Boren. The old table had 100, 50 and 25 for F, Np and Ns, so a seasonal Ns stream went from 25 feet to 100. With the 10 foot setback, an Ns stream puts the house 110 feet back (100 plus 10) and Lake Boren, on the stream table’s number, puts it 120 feet from the water (110 plus 10). The same ordinance says Lake Boren is a wetland rated by city consultants and tells owners to ask the city for its category and buffer widths, so get that in writing. Wetland buffers depend on category, habitat score and land use intensity, set by a qualified wetland professional (NMC 18.24.315).
Lake Washington. Nothing I read shows Lake Washington frontage in Newcastle, and the waterfront chapter, 18.17, covers docks and piers on Lake Boren only (mirror copy). Lake Boren covers 16.20 acres per the Washington Department of Fish and Wildlife, and the state Shoreline Management Act leaves out shorelines on lakes under 20 acres (RCW 90.58.030(2)(e)(iii)). I found no Newcastle shoreline program for it, so the city’s buffer and dock rules appear to govern; confirm with the city. For lakefront sites see my waterfront architect page.
Trees and clearing
Tree retention in chapter 18.16 applies to new development: a change of occupancy or a substantial improvement, meaning work costing 50 percent or more of the structure’s market value. As I read it, a rebuild is over that line. At a $750,000 budget the line is crossed on any structure with a market value of $1,500,000 or less (750,000 divided by 0.5).
- Retention. Keep 25 percent of the mature trees in the lot interior, outside critical areas and buffers. A mature tree is 8 inches across for evergreens or 12 for deciduous trees, measured 4 feet above grade. With 20 mature trees you keep 5 (20 x 0.25). A certified arborist prepares the retention plan with the building permit, and a 6 foot fence goes 2 feet outside the drip line (NMC 18.16.130 to 18.16.160).
- Replacement. If the required trees cannot be kept, or 10 or more significant trees come out, removed trees are replaced at 2 inches of new trunk for each inch removed, in 2 inch trees, at least 70 percent conifer: a 10 inch tree means 20 inches, or ten trees (NMC 18.16.170).
- Clearing permit. Clearing 2,500 square feet or removing 10 or more significant trees needs a clearing and grading permit (NMC 17.07.040). The city says up to 9 can come out of private property not under permit review, but not from critical areas.
Remodel, rebuild or tear down
As far as I can read, Newcastle uses no remodel cost percentage to end a nonconforming house’s protection, unlike Clyde Hill or Bellevue; see when a remodel counts as a new house. Its 50 percent test applies to damage and demolition. Two rules matter.
- Zoning nonconformance (chapter 18.32, read on a mirror that already shows Ordinance 2026-689, which I did not read). You may modify a nonconforming improvement if the change does not increase its area, height or degree of nonconformity. A damaged or demolished one can be rebuilt only if the nonconformance does not grow, the permit application comes within 12 months, and the loss stays under 50 percent of assessed or appraised value, with an exception for fire or natural disaster. That suggests a teardown of a house sitting in a yard brings a new house under today’s rules, but it rests on the mirror alone, so confirm with the city.
- Critical areas (NMC 18.24.055, new in 2026). An addition to or voluntary replacement of a nonconforming house must go outside the critical area and buffer where possible. For stream and wetland buffers a house may go up, with a one-time footprint addition of up to 500 square feet in an already improved area, reaching no closer to the water than today. The old exemption for 250 square feet on a house built before incorporation was struck, and for steep slopes I found no addition allowance, so ask early. An administrative variance (fee $3,168) cannot cut the setback below 5 feet.
ADUs and middle housing
NMC 18.31.030, as adopted in June 2025, allows up to two ADUs with a house, attached or detached, of 300 to 1,000 square feet (the director may allow more for one on a single floor), at up to 30 feet attached or 24 detached, with one parking space each except within half a mile of a major transit stop. See my Washington ADU guide. Chapter 18.19 also allows two units per lot by right on lots zoned mainly for housing, including duplexes and cottage housing, with standards no stricter than for a detached house, but not on critical area portions or lots created by splitting a single residential lot.
The building permit: who reviews it, where you apply, what the city charges
Community Development’s Building division reviews permits and inspects projects, and the building code is Title 15 of the NMC. The Permit Center page now sends applicants to the city’s OpenGov portal, where single-family permits moved from MyBuildingPermit.com in June 2026.
Who reviews. City staff do. You also reimburse the city for consultants it hires when staff cannot do the review, structural engineering among them, with a deposit and a 10 percent overhead charge. I found no published review time for house permits, so I quote none.
| Charge | 2026 amount | Where it sits in the schedule |
|---|---|---|
| Plan review, inspection, building pre-application meeting | $173 per hour, or cost if greater | Schedule 3, Building Fees |
| Demolition permit | $829, or cost if greater | Schedule 3 |
| Transportation impact fee, single family detached house | $11,046 per unit | Schedule 4 |
| Parks and trails impact fee | $2,019 per bedroom | Schedule 4 |
The building permit fee itself sits in NMC 15.05.109 on the blocked code host, so I have not calculated it. If the per bedroom parks fee applies to a house, a four bedroom replacement is $19,122 in transportation and parks fees (11,046 plus 4 x 2,019) before any credit for the house you remove; I could not read Title 16 to confirm either point, so ask. The schedule also lists 4.0 percent fees for MyBuildingPermit.com and card payments; ask whether the first still applies after the move to OpenGov. Energy rules are in my energy code guide and teardown steps in my demolition guide.
Before you design
Find out what your Newcastle lot will carry
Send me the address and what you have in mind. I have been an architect since 1996. My feasibility check is free and takes about a day; an in-depth analysis is $1,500 and takes 2 to 3 weeks. I design and administer construction and I do not build. My fee for design and permit is fixed, about $10,000 to $200,000 by project budget and location.
Questions
What is the zoning code in Newcastle, Washington?
Newcastle, Washington, in King County, zones land under Title 18 of the Newcastle Municipal Code. Chapter 18.12 holds the density and dimension tables, chapter 18.24 the critical areas rules and chapter 18.16 landscaping and tree retention. Ordinance 2025-671 rewrote chapter 18.12 and added chapter 18.19 for middle housing in June 2025, and Ordinance 2026-683 updated critical areas in February 2026. Confirm current text with the city.
How do I find the Newcastle, WA zoning map?
The code refers to the city’s adopted zoning map, and a third-party mirror of chapter 18.04 says the official copy is on file with the city clerk. The city’s Codes and Plans page does not link a stand-alone map, and its Property Information page points to the King County Parcel Viewer and iMap and to its own Maps and Data portal. Ask Community Development to confirm your zone in writing before you design.
What are the setbacks in Newcastle’s R-4 and R-6 zones?
In both zones the front setback is 10 feet, the rear 20 feet and the interior side yards at least 5 feet with a combined total of 15 feet, and a street side yard is 10 feet. A garage needs 20 feet of driveway in front of it. A 10 foot setback from any critical area buffer applies on top. Source: NMC 18.12.030, as of October 2026.
How tall can a house be in Newcastle?
A house in R-1, R-4 or R-6 can be 30 feet tall. The city measures from the average finished grade, found by averaging the ground at the midpoint of the four sides of the smallest rectangle around the house, to the top of a flat roof or the mean height between eaves and ridge of a pitched roof. Chimneys, stairs and mechanical screens up to 10 feet above the limit are excluded. Detached ADUs are limited to 24 feet.
How much of my Newcastle lot can I cover?
In R-4 and R-6 the roof may cover 35 percent of the lot, impervious surface may reach 40 percent and hard surface 45 percent. On a 10,000 square foot lot that is 3,500, 4,000 and 4,500 square feet. R-1 allows 15 percent coverage and 20 percent impervious surface, but an R-1 lot under 15,000 square feet follows the R-4 numbers. There is no floor area cap for houses.
Do steep slopes or old coal mines stop me from building in Newcastle?
They add studies and limits rather than an automatic ban. A steep slope buffer is at least 10 feet if a geotechnical report supports it and 50 feet if not, with a further 10 foot building setback. Land over old coal workings needs a hazard assessment by a professional engineer before any alteration, and severe areas allow only a short list of buildings unless a mitigation plan supports more. Check NMC 18.24.200 to 18.24.208 and 18.24.300.
Do I need a permit to remove trees in Newcastle?
You need a clearing and grading permit to clear 2,500 square feet of contiguous land or remove 10 or more significant trees (NMC 17.07.040). The city says up to 9 significant trees can be removed from private property not under permit review without one, but not in critical areas, native growth protection easements or trees marked for retention on a plat. As I read the code, a rebuild or a remodel costing half or more of the structure’s value must also keep 25 percent of mature trees.
How do I apply for a building permit in Newcastle, and who reviews it?
The City of Newcastle takes permit applications through its OpenGov portal; the Permit Center is permit@newcastlewa.gov or 425-386-4103. City Building division staff review and inspect. Under the April 2026 fee schedule the applicant also reimburses the city for outside consultants when staff cannot do the review, and plan review is billed at $173 per hour or cost if greater. I found no published review time, so ask at pre-application.
Can I build an ADU or a duplex on my Newcastle lot?
Yes, subject to the lot. NMC 18.31.030 allows up to two ADUs of 300 to 1,000 square feet with one parking space each, and chapter 18.19 allows two units per lot on lots zoned mainly for housing, though not on the critical area portion of the lot or a lot created by a lot split. ADUs count toward your impervious and floor area limits, and the transportation impact fee is $3,125 for an ADU of 450 square feet or less and $5,523 above that.
Authoritative sources
Regulatory requirements referenced in this guide are set by the official agencies below. Rules change, always confirm current requirements with the source: