Key takeaways
- Ordinance 6851 renamed the residential zones. R-5 is now SR-4 and R-3.5 is now SR-2.
- Front yards are 20 feet in SR-1 through LDR-1 (30 or 35 in the large lot zones), rear yards 20 or 25 feet, and side yards 5 feet each, 10 to 20 feet combined by zone.
- A house may reach 30 feet to a flat roof or 35 feet to a pitched ridge from average existing grade, and no facade may exceed 40 feet.
- For one house, floor area ratio is 0.5 up to 10,000 square feet of lot and 0.3 on the rest.
- Ordinances 6930 to 6932 were adopted 7 to 0 on 28 July 2026 per draft minutes. The copies read are unsigned, so the city’s current code controls.
Short answer: on a lot at the minimum size of SR-2 to SR-4 (7,200 to 10,000 square feet), the Land Use Code lets a single house cover 35 or 40 percent of the lot, rise 30 to 35 feet above average existing grade, sit 20 feet from the street and hold floor area of up to half the lot. Which numbers apply depends on your zone, and every residential zone was renamed in 2025. A lake lot, a steep slope or large trees bring more rules on top.
The sources for this page were read on 15 November 2026: the city’s zoning, setbacks, height and site plan pages, the Legistar copy of Ordinance 6851, unsigned agenda copies of Ordinances 6894, 6906, 6930, 6931 and 6932, the city’s 2025 middle housing environmental determination packet, and Council summary minutes, which Legistar lists as Draft. Bellevue’s code site sits behind a bot check and was not bypassed, so the codified Land Use Code (LUC) was not read. Confirm any figure with the city. Piper Cole designs and administers construction; I do not build. Permit steps are in the Bellevue building permit guide.
Bellevue’s residential zones, renamed in 2025
Ordinance 6851 amended LUC 20.10.020 to rename every residential district: Large Lot (LL), Suburban (SR), Low Density (LDR) and Medium Density (MDR). The old names counted units per acre, and Chart 20.20.010 still carries that row. The city’s 2025 draft table in its determination packet (file 25-103771-AD) pairs each new name with its old one, and Section 66 of the Ordinance 6851 copy directs the Land Use District Map to be updated to the new names. The city’s own setbacks page still uses R-5 for its example, and plats and older permits use the R names.
| New zone | Old name | Minimum lot | Minimum width |
|---|---|---|---|
| LL-1 | R-1 | 35,000 sq ft | 100 ft |
| LL-2 | R-1.8 | 20,000 sq ft | 90 ft |
| SR-1 | R-2.5 | 13,500 sq ft | 80 ft |
| SR-2 | R-3.5 | 10,000 sq ft | 70 ft |
| SR-3 | R-4 | 8,500 sq ft | 65 ft |
| SR-4 | R-5 | 7,200 sq ft | 60 ft |
| LDR-1 | R-7.5 | 4,700 sq ft | 50 ft |
Source: Chart 20.20.010 in the Legistar copy of Ordinance 6851 (signature lines blank). Minimum depth is 150 feet in LL-1 and 80 feet in the others. Denser districts are not covered here.
Finding your zone
The city’s setbacks page tells owners to confirm the zone with a land use planner or the public mapping tools, and the city’s open data site lists a Zoning dataset described as “Boundaries of Bellevue’s various zoning areas.” For a written answer, the city’s page on the current zoning status of a property describes a letter requested through MyBuildingPermit (activity type Preapplication Services, scope of work Zoning Verification). That page lists the project type as Multifamily Residential or Nonresidential, so ask which entry a house uses. The Land Use desk is 425-452-4188.
Pull the recorded plat too: the city says plat conditions “will sometimes require additional setbacks.”
Setbacks by zone
| Zone | Front | Rear | Each side | Both sides together |
|---|---|---|---|---|
| LL-1 | 35 ft | 25 ft | 5 ft | 20 ft |
| LL-2 | 30 ft | 25 ft | 5 ft | 15 ft |
| SR-1 and SR-2 | 20 ft | 25 ft | 5 ft | 15 ft |
| SR-3 and SR-4 | 20 ft | 20 ft | 5 ft | 15 ft |
| LDR-1 | 20 ft | 20 ft | 5 ft | 10 ft |
Source: Chart 20.20.010 in Ordinance 6851. The unsigned copy of Ordinance 6931 (adopted 7 to 0 on 28 July 2026 per draft minutes) re-adopts the rear and side rows with the same values.
A setback is measured from the property line. For a street that is the interior edge of the right of way, and the city warns that “Typically, your property line is several feet from the road improvements.” A corner lot on two public streets needs a front setback along each, and the city says to keep at least 10 feet from a right of way, access easement or private road. Relief is a variance under LUC 20.30G, which must meet “very specific criteria.”
- Minor building elements (eaves, decks, porches, balconies, bay windows, chimneys) 30 inches or more above grade may extend into a setback by 20 percent of the setback or 18 inches, whichever is greater: on a 20 foot front setback, 4 feet (20 x 0.20). Lower elements may go anywhere in it.
- Heat pumps are not minor building elements, and the city’s page says the same of retaining walls and rockeries 30 inches or taller.
On walls, the city’s permit FAQ says a retaining wall or rockery “over 30 inches high must not be located within any required setback.” The setbacks page draws the line at 30 inches or taller. The unsigned copy of Ordinance 6930 (adopted 7 to 0 on 28 July 2026 per draft minutes) amends LUC 20.20.025.D so that such walls “may extend into setbacks … provided, that the existing grade change is such that no feasible alternative to location or height exists.” The 6930 copy words it as walls “30 inches or greater in height.” A wall of exactly 30 inches is a question for the city. The city’s permit FAQ also says a permit is required for retaining walls over four feet high, measured from the bottom of the footing to the top of the wall, or any wall supporting a surcharge load.

Free feasibility check
Planning a custom home or a remodel of $750,000 or more?
Send me the address and a few lines about what you want. The first feasibility check is free and usually takes about a day.
Height limit for a house
Chart note (44) sets a house at 30 feet “measured from the average elevation of the existing grade around the building to the highest point of a flat roof, or 35 feet to the ridge of a pitched roof.” Per the city’s height page, a roof pitched under 2:12 counts as flat, several roof sections are measured to the highest ridge, and chimneys, antennas, stacks and flagpoles are left out. The unsigned copy of Ordinance 6931 adds LUC 20.20.525.D: a building “may exceed the maximum building height by at least 48 inches and up to the maximum amount necessary to accommodate roof-mounted solar energy panels.”
Average existing grade is the mean of ground elevations read at points every 10 feet around the footprint on a plan with 2 foot contours; subtract it from the roof elevation. A second test applies to new houses and additions: note (45) caps any facade at 40 feet from existing grade at the wall to the ridge or flat roof. Full subdivision and planned unit development lots are exempt; the city says short plat lots are not.
| Test | Arithmetic | Result |
|---|---|---|
| Pitched roof, average existing grade 100.0 ft, ridge at 135.0 ft | 135.0 to 100.0 = 35.0 | At the 35 ft limit: passes |
| Flat roof at 131.0 ft on the same lot | 131.0 to 100.0 = 31.0 | Over the 30 ft limit: fails |
| Same ridge, ground at the downhill wall is 94.0 ft | 135.0 to 94.0 = 41.0 | Over the 40 ft facade limit: fails |
Shoreline lots have their own height section, LUC 20.25E.017.B, listed on the city’s height page and not read for this page.
Lot coverage, impervious surface and greenscape
| Zones | Lot coverage by structures | Impervious surface | Alternative impervious | Hard surface |
|---|---|---|---|---|
| LL-1 to SR-3 | 35% | 45% | 50% | 75% |
| SR-4 and LDR-1 | 40% | 55% | 55% | 80% |
Source: Chart 20.20.010 in Ordinance 6851. The note that governs the alternative impervious row (note 48) was not in the copy read, so ask the city whether your lot qualifies.
Note (37) calls the three limits “independent limitations.” Structures count inside impervious surface unless an exception in LUC 20.20.460 applies, and impervious surface counts inside hard surface, with exceptions in LUC 20.20.425. Per the city’s site plan page, coverage counts all primary and accessory structures and decks more than 30 inches above finished grade, against a lot area that excludes critical areas and stream buffers (habitat for species of local importance and coal mine hazard areas are not subtracted). Another line on that page says the area excludes “all critical areas and their related primary setback areas,” so ask the city which applies to your lot.
Greenscape is separate: at least 50 percent of the front yard setback in these zones, imposed under note (40) whenever a permit, approval or review is required. Front yards legally established before 1 January 2008 that fall short are not nonconforming. The definition, in LUC 20.50.022, was not read.
Floor area ratio: how big the house can be
LUC 20.20.390 is new with Ordinance 6851. It applies to new houses, middle housing, detached ADUs and additions that increase an existing detached house by 20 percent or more. The unsigned copy of Ordinance 6931 rewrites that test as a 20 percent or greater increase “in the square feet of gross floor area permitted under the original approval.” Table 20.20.390.B.1 sets the ratio by the number of units on the lot; footnote 2 splits one house on a lot over 10,000 square feet into 0.5 on the first 10,000 and 0.3 on the rest.
| Lot size (taken as net area) | Arithmetic for one house | Maximum floor area |
|---|---|---|
| 8,500 sq ft | 8,500 x 0.5 | 4,250 sq ft |
| 10,000 sq ft | 10,000 x 0.5 | 5,000 sq ft |
| 13,500 sq ft | 5,000 + (3,500 x 0.3) | 6,050 sq ft |
| 20,000 sq ft | 5,000 + (10,000 x 0.3) | 8,000 sq ft |
| 35,000 sq ft | 5,000 + (25,000 x 0.3) | 12,500 sq ft |
The definition divides gross floor area by “net on-site land area,” a term that was not read, so these figures use the full lot size. Gross floor area is measured inside the finished wall surface and includes “the floor area of the ground floor plus that of any additional stories of all buildings on the lot, including accessory structures.” Spaces 18 feet or more in height count twice. Partially exposed lower levels less than 5 feet above finished grade, unfinished nonhabitable attics, carports, porches and decks are excluded. A garage is not on that list.
One lot, worked step by step
Take an SR-4 lot (the old R-5) that is 60 feet wide and 125 feet deep, so 7,500 square feet (60 x 125). It clears the SR-4 minimums of 7,200 square feet, 60 feet of width and 80 feet of depth. Assume no critical area, plat building line or easement.
| Question | Arithmetic | Answer |
|---|---|---|
| Depth left after front and rear yards | 125 to 20, 20 | 85 ft |
| Width left after side yards (5 ft minimum each, 15 ft together) | 60 to 15 | 45 ft |
| Yard envelope | 45 x 85 | 3,825 sq ft |
| Lot coverage cap, 40 percent | 7,500 x 0.40 | 3,000 sq ft |
| Floor area cap, FAR 0.5 | 7,500 x 0.5 | 3,750 sq ft, every story and the garage included |
| Impervious cap, 55 percent | 7,500 x 0.55 | 4,125 sq ft |
| Hard surface cap, 80 percent | 7,500 x 0.80 | 6,000 sq ft |
| Greenscape in the front yard setback | (60 x 20) x 0.50 | 600 sq ft |
| Highest ridge above average existing grade | limit from note (44) | 35 ft, and 40 ft at any one facade |
A one-story house at the coverage cap covers 3,000 square feet and holds 3,000 of the 3,750 square feet allowed, so coverage binds first. A two-story house with equal floors reaches the floor area cap at 1,875 square feet per floor (3,750 / 2), so floor area binds. At a 3,000 square foot footprint, 1,125 square feet of impervious allowance remains for driveway and walks (4,125 to 3,000).
Garages, ADUs and more than one unit
In the Ordinance 6851 copy, LUC 20.20.125 limits detached accessory structures on lots under 20,000 square feet to 15 feet in height except as the section provides. Under LUC 20.20.120, up to two ADUs are allowed per lot, each up to 1,200 square feet unless the Director approves more. An attached ADU follows the house’s height and setbacks and is exempt from floor area ratio. A detached ADU is limited to 24 feet (28 over an existing accessory structure), follows the middle housing dimensions of LUC 20.20.538 and counts in floor area ratio. The full rules are in Bellevue ADU rules.
In the Ordinance 6851 copy, middle housing (LUC 20.20.538, which Ordinance 6931 also amends) allows up to four units per lot, six near major transit or a growth center, with its own yards, height and coverage. See middle housing on the Eastside.
If your house does not meet today’s numbers
A house built under earlier yard rules may not meet today’s numbers. The unsigned copy of Ordinance 6906 (adopted 7 to 0 on 17 March 2026 per minutes Legistar lists as Draft) moves the nonconforming rules into LUC 20.20.561. For LL-1 through LDR-1, as that copy prints it:
- Routine maintenance and like-for-like repair of windows, doors, roofing or cladding are allowed.
- Alterations must conform to the applicable development regulations, so new work is tested against the numbers on this page.
- The proportional standards apply “when the value of alterations … exceed the replacement value of all primary structures located on the site,” and improvements are then required to the extent necessary to bring the structure or site into full compliance.
- Alterations in the preceding three years count as one, and a cost estimator acceptable to the Director sets the value. Fire prevention, accessibility, seismic retrofit and onsite stormwater work are excluded.
The critical areas code controls in a conflict, and shoreline nonconformity follows LUC 20.25E. The copy defines replacement value of a structure as “the amount it would cost to replace it, minus deferred maintenance”; the codified text was not read.
Trees, critical areas and lake lots
The city’s trees page says the minimum tree density in LUC 20.20.900 applies to “construction of new buildings and homes, alterations and additions to existing structures, and general alteration of land, including changes to lot coverage and parking areas.” The unsigned copy of Ordinance 6932 (adopted 7 to 0 on 28 July 2026 per draft minutes) amends a provision that names two alteration cases: lot coverage changed by more than 20 percent of the existing coverage, and impervious surface added above 20 percent of the existing amount. Its credit table for one dwelling unit per lot is 5 credits per 1,000 square feet of tree canopy site area in LL-1 and LL-2, 2 in SR-1 to SR-4, and 1 in all other districts.
A retained tree earns credits by diameter, from 2 for 6 to 10 inches up to 10 for 24 inches or larger; alders, cottonwoods and trees on a property line earn half. Seattle has a separate tree code: Seattle tree ordinance guide.
Critical areas (LUC 20.25H, the subject of Ordinance 6894, read in an unsigned copy) include streams, wetlands and geologic hazard areas. Steep slopes are slopes of 40 percent or more with at least 10 feet of rise over more than 1,000 square feet. A proposal that avoids a critical area and its buffer is reviewed through the underlying permit; development within them also needs a Critical Areas Land Use Permit. The tree section does not apply inside a critical area or buffer, where Part 20.25H governs.
Lake lots add the Shoreline Overlay District: the city says such properties “have additional requirements for structures located near Lake Washington, Lake Sammamish, Lower Kelsey Creek, and Phantom Lake” under LUC 20.25E. Shoreline setback and impervious figures are not repeated here because that code text was not read. See lakefront design on Lake Washington.
What changed in 2025 and 2026
| Ordinance | What it did for a house | Status in the sources read |
|---|---|---|
| 6851 | Renamed zones; added floor area ratio, ADU and middle housing rules | 7 to 0 on 24 June 2025 per summary minutes (Legistar lists Draft); signature lines blank |
| 6894 | Critical areas rewrite; also amends LUC 20.20.538.A | Unsigned copy; effective 1 January 2026 by its clause; adoption not re-verified |
| 6906 | Nonconforming rules moved to LUC 20.20.561 | 7 to 0 on 17 March 2026 per Draft minutes; unsigned copy |
| 6930 | Clean-up, including walls in setbacks (20.20.025.D) | 7 to 0 on 28 July 2026 per Draft minutes; unsigned copy |
| 6931 | Addition test for floor area ratio; solar height allowance; ADU wording | Same; effective five days after publication, date not read |
| 6932 | Tree credit table and alteration trigger | Same; effective five days after publication, date not read |
| 6935 | Corrects text from Ordinances 6931 and 6933 | On the 8 September 2026 agenda; adoption not verified |
| 6947 | Parking rules | On the 17 November 2026 agenda; not adopted as of 15 November |
Where to start
Zoning is checked from the site plan. The city asks for a sheet at least 18 by 24 inches showing labeled setbacks, contours at 2 foot intervals on the NAVD 88 datum, every tree with species and diameter, top and bottom elevations of retaining walls and rockeries, critical areas and buffers, floor area ratio, coverage and impervious totals, and a height table from points no more than 10 feet apart. Permit types and fees are in the permit guide and fee page. A sensible order:
- Confirm the zone and read the recorded plat for building setback lines.
- Order a survey with existing contours, which the height average and site plan need. See existing conditions drawings.
- Mark critical areas, buffers, easements and trees, then test the yard envelope, coverage, floor area ratio and height as in the example.
Before you design
Send me the address
Tell me the address and what you want to build. The basic feasibility check is free and usually takes about a day; the in-depth analysis is $1,500 and takes 2 to 3 weeks.
Questions
What is the zoning code in Bellevue, WA?
Bellevue’s zoning code is the Land Use Code, Title 20 of the city code. Residential yards, height, lot coverage and minimum lot size are in Chart 20.20.010, and house size is capped by floor area ratio in LUC 20.20.390. Ordinance 6851, adopted 7 to 0 on 24 June 2025 per summary minutes that Legistar lists as Draft, renamed the residential zones LL-1, LL-2, SR-1 to SR-4, LDR-1 to LDR-3, MDR-1 and MDR-2. The code site was not readable for this page, so confirm current text with the city.
What are the setback requirements in Bellevue?
In Chart 20.20.010 as adopted by Ordinance 6851 the front setback is 20 feet in SR-1 through LDR-1, 35 feet in LL-1 and 30 feet in LL-2. The rear setback is 25 feet in LL-1 through SR-2 and 20 feet in SR-3 and denser zones. Each side is 5 feet, and both sides together are 20 feet in LL-1, 15 feet in LL-2 through SR-4, and 10 feet in LDR-1. The city’s setbacks page says to keep at least 10 feet from a right of way, access easement or private road, and plat conditions can add more.
What is the height limit for a house in Bellevue?
In LL-1 through LDR-1 a house may be 30 feet to the top of a flat roof or 35 feet to the ridge of a pitched roof, measured from the average existing grade around the building. A roof pitched under 2:12 counts as flat. A second test limits any single facade of a new house or addition to 40 feet from existing grade at the wall to the ridge or flat roof, except on lots created by a full subdivision or planned unit development.
What is R-5 or R-3.5 zoning in Bellevue now?
Ordinance 6851 renamed R-5 as SR-4 and R-3.5 as SR-2; the old number is the units per acre row of the chart. SR-4 needs a lot of at least 7,200 square feet and 60 feet wide, with 20 foot front and rear yards, 5 foot sides totaling 15 feet, lot coverage up to 40 percent, impervious surface up to 55 percent and floor area up to 0.5 of the lot. SR-2 needs 10,000 square feet and 70 feet, with a 25 foot rear yard and 35 percent coverage.
How big a house can I build on my lot in Bellevue?
For one house, floor area ratio is 0.5 on a lot of 10,000 square feet or less. On a larger lot, 0.5 applies to the first 10,000 square feet and 0.3 to the rest, so a 20,000 square foot lot allows 8,000 square feet. Floor area counts every story and every building on the lot, counts spaces 18 feet or taller twice, and excludes carports, porches, decks, unfinished attics and partially exposed lower levels less than 5 feet above finished grade. It is divided by net on-site land area, a term that was not read. Coverage, yards and height also apply.
How much of my lot can I cover in Bellevue?
Chart 20.20.010 caps lot coverage by structures at 35 percent in LL-1 through SR-3 and 40 percent in SR-4 and LDR-1. It separately caps impervious surface at 45 or 55 percent and hard surface at 75 or 80 percent. The city counts primary and accessory structures and decks more than 30 inches above finished grade, against a lot area that excludes critical areas and stream buffers. On a 7,500 square foot SR-4 lot, 40 percent is 3,000 square feet.
Where do I find the Bellevue zoning map or my zone?
The city’s setbacks page points owners to the public mapping tools, and the city’s open data site lists a Zoning dataset. For a written answer, the city describes a zoning verification letter requested through MyBuildingPermit, and the Land Use desk is 425-452-4188. Older plats and permits use the R names, which translate through the table on this page.
Can I put a retaining wall in a setback in Bellevue?
The city’s permit FAQ says a retaining wall or rockery over 30 inches high must not be located within any required setback, and its setbacks page says walls and rockeries 30 inches or taller are not minor building elements. The unsigned copy of Ordinance 6930, adopted 7 to 0 on 28 July 2026 per draft minutes, lets one (worded as 30 inches or greater in height) extend into a setback only where the existing grade change leaves no feasible alternative to location or height. Ask the city about a wall at exactly 30 inches.
Did Bellevue change its zoning in 2025 and 2026?
Yes. Ordinance 6851 in June 2025 renamed the zones, added the floor area ratio cap and set rules for ADUs and middle housing. An unsigned copy of Ordinance 6894, a critical areas rewrite, sets 1 January 2026 as its effective date, and its adoption was not re-verified. Ordinance 6906 moved the nonconforming rules, adopted 7 to 0 on 17 March 2026 per draft minutes. Ordinances 6930 to 6932 were adopted 7 to 0 on 28 July 2026 per draft minutes and touch retaining walls, the addition test for floor area ratio and tree credits. The copies read were unsigned, so check the codified text.