Key takeaways
- Below 75 percent of the King County assessed improvement value, a remodel of a nonconforming house gets a Level 1 administrative review. At 75 percent or more it is reviewed as new development of the site (IMC 18.214.070). A demolished house must meet current code.
- The owner must prove the house was legal when built (18.214.030), and every change must reduce the nonconformity as far as practical and feasible.
- The city’s Target Review Times handout, last updated April 2026, sets 4 weeks for a first review of a single family building permit, then 3 weeks, then 1 week.
- My fee for design and permit is fixed, about $10,000 to $200,000, set by project budget and location. The first feasibility check is free and takes about a day.
- Piper Cole Architects is based in Kirkland. It designs and administers construction. It does not build.
Short answer: I design whole house remodels in Issaquah for a fixed fee, about $10,000 to $200,000 depending on the project budget and location, and the first feasibility check is free and takes about a day. Before you pay for drawings, your architect should say which Issaquah rules will decide the job: whether the house is legally nonconforming and where your scope sits against the city’s 75 percent line, whether the lot has a steep slope, big trees or the lake shoreline, and, in the Highlands, an architectural committee that signs off before the city sees the plans.
This page is for an Issaquah owner with a remodel budget of $750,000 or more who is comparing architects, including in Issaquah Highlands, Talus and on the Lake Sammamish shoreline. Piper Cole designs and administers construction on your behalf. It does not build, so the builder you hire answers to you and to the drawings. The rules come from Title 18 of the Issaquah Municipal Code (IMC) as adopted in the city’s ordinances, and from the city’s own permit pages and PDFs, read on 15 October 2026. The city’s online code site was not readable to me, so I cite the adopted ordinances, not the live code. Confirm with the city. My Issaquah zoning and permit guide has the rest of the zoning rules, and my Issaquah page says where I work.
What Issaquah’s code does to a remodel
Many Issaquah houses were built under older rules and now sit inside a setback. That is legal, and the code calls it nonconforming. Issaquah sets no wall count and no flat dollar line. It sets a review track by cost against the county’s value of your building, and approval tests that apply on either track.
| Rule | What the code says | What it does to a remodel |
|---|---|---|
| Review track (IMC 18.214.070.B) | Remodel or alteration costs under 75 percent of the latest King County tax assessed improvement value: Level 1 review. At 75 percent or more: the review process for new development of the site. | Level 1 is administrative, with no public notice or comment period (IMC 18.204.030). The city’s table lists building permits as Level 1, so ask what the 75 percent track means for your permits. Size the scope against the line before design starts. |
| Approval tests (18.214.070.C, 18.214.100) | The change must reduce the nonconformity to the fullest extent practical and feasible, and the site must meet current parking, sign and landscaping rules. A single family house may be expanded so long as the nonconforming part is not increased. | For a wall in the side setback, ask the city early how it applies the first test. |
| Proof it was legal (18.214.030) | The owner must show the house is legally nonconforming, or the city may require compliance. | Ask your architect to pull permit history and surveys at the start. |
| Demolition (18.214.050, .060) | A demolished structure must be replaced in conformance. A single family house damaged by accident or nature may be rebuilt regardless of value, without more nonconformity, if complete applications come within one year. | A teardown does not keep a setback. I weigh it in remodel or tear down. |
Sources: Ordinance 3013 (IMC 18.204 and 18.214, effective June 1, 2023), from the city’s document center. Chapter 18.214 is cited as adopted. The city’s online code was not readable to me, so I could not check its current text. I searched for a later ordinance amending 18.214 and found none, but I cannot rule one out. In the Highlands and Talus, IMC 18.214.140 exempts certain nonconformities, including density and floor area, created by the 2023 Form and Intensity chapter for plats approved before it, so ask whether it covers your house.
At a $750,000 scope, the 75 percent line is reached when the assessed improvement value is $1,000,000 or less ($750,000 divided by 0.75). The improvement value is the building part of the county’s assessment, not the land. The code says “remodel or alteration costs,” and I do not assume your whole budget counts. That is an illustration, not a ruling. My threshold comparison sets Issaquah beside other Eastside cities.
SF-E, SF-S and SF-SL: the numbers a remodel meets
The table lists no floor area ratio for these zones. The envelope is the yards, the height and a cap on hard surface (IMC Table 18.404.090(A), restated in 2025 by Ordinance 3088).
| Zone | Minimum lot | Front, side, rear yards | Max impervious | Base height |
|---|---|---|---|---|
| SF-E, Estates | 35,000 sq ft | 30 ft, 15 ft, 30 ft | 30 percent | 30 ft |
| SF-S, Suburban | 9,600 sq ft | 20 ft, 8 ft, 10 ft | 40 percent | 30 ft |
| SF-SL, Small Lot | 6,000 sq ft | 10 ft, 6 ft, 20 ft | 50 percent | 30 ft |
Impervious surface counts the footprint plus driveway, patios, decks, porches and pools, so an addition and a new terrace draw from one budget. On a 9,600 square foot SF-S lot the cap is 3,840 square feet (9,600 x 0.40). Height is measured from average grade, taken from spot elevations every 10 feet around the footprint (IMC 18.404.040 and 18.404.050). Highlands and Talus have their own tables.
Free feasibility check
Planning a custom home or a remodel of $750,000 or more?
Send me the address and a few lines about what you want. The first feasibility check is free and usually takes about a day.
Slopes, trees, the lake and the Highlands
Slopes and soils. Slopes of 40 percent or more carry a 50 foot buffer from the top and toe. A critical areas study can cut it to 10 feet, but an occupied building must stay 25 feet from the top or toe, plus a 15 foot building setback from the buffer edge (IMC 18.802.130 and 18.802.450). Ground disturbance on slopes of 15 percent or more with 10 feet of rise falls under the forested hillside chapter, which generally caps cuts, fills and retaining walls at 10 feet (18.810.090 and .100). The city’s Soils Report Requirements handout (September 2023) requires a soils report for structures needing a building permit, with exceptions such as single story room additions the Building Official approves in advance. Ask whether your scope needs one.
Trees. The tree code changed effective October 14, 2025 (Ordinance 3114). A significant tree is 6 inches or more at breast height (8 for alder and cottonwood). Redevelopment that expands the footprint or impervious area must keep 35 percent of the total diameter of significant trees in the developable area, and construction stays 5 feet outside a protected tree’s drip line. See my guide to building around big trees.
Lake Sammamish. Shoreline jurisdiction reaches 200 feet landward of the ordinary high water mark. The program sets a 35 foot buffer and a 15 foot building setback. An existing legal house may be expanded without a variance if the work stays landward of both, and new impervious area above 500 square feet in five years requires equal buffer planting. The council adopted Ecology’s edits as Ordinance 3089 on April 21, 2025, and Ecology’s final approval letter is dated May 12, 2025, with an effective date 14 days later. The program also says nonconforming development in shoreline jurisdiction is subject to it in addition to IMC 18.214. See my shoreline exemption guide.
Design review. I found no city design review step for a detached house in SF-E, SF-S or SF-SL. The Highlands differ. IMC 18.706.030 says that before any permit submittal the owner must show Architectural Review Committee (ARC) approval where the ARC has purview, and the city’s packet asks for the ARC stamp on the site plan and elevations. IMC 18.708 applies Talus standards to all Talus properties, and I could not tell how they apply to a remodel. The association’s guidelines were blocked to my reader, so ask it how long its review takes and plan that round first.
How long Issaquah review takes, in the city’s own numbers
The city publishes target review times in weeks, last updated April 2026. The clock starts when permit fees are paid, and fees are invoiced after the submittal is deemed sufficient.
| Permit type | First review | Second review | Third and later |
|---|---|---|---|
| Single family residential building permit | 4 weeks | 3 weeks | 1 week |
| Deferred submittals and revisions | 2 weeks | 2 weeks | 2 weeks |
| Tree permit | 2 weeks | 1 week | 1 week |
| Shoreline exemption | 3 weeks | 2 weeks | 1 week |
| Shoreline permit (substantial, variance, conditional use) | 5 weeks | 4 weeks | 2 weeks |
Source: City of Issaquah, Target Review Timelines, last updated April 2026. The handout does not split remodels from new houses, and the city links it from its new construction and addition page. Three rounds on the building row come to 8 weeks (4 + 3 + 1), before the days you spend answering. I found no report of how long completed residential permits actually took, so I plan on the targets plus a revision round or two. The whole calendar is in how long a whole house remodel takes.
Applications go through MyBuildingPermit.com. The city’s remodel permit covers interior remodels, and an addition goes through its new construction and addition permit. For that permit a pre-submittal meeting may be required, and the city’s packet (August 2023) lists a geotechnical report and review letter, a stormwater report, stamped structural calculations and an energy code worksheet. Its packets say that if an architect or engineer prepares the plans, every sheet and calculation must be stamped.
What the city charges. Fees are set by the city and sit outside my fee. For an interior remodel, the city points to its Tenant Improvement Fee Schedule (updated January 1, 2026), which lists a building permit fee read from a valuation chart (updated November 20, 2025) and a plan check fee of 65 percent of it. Here is that part at a $750,000 valuation.
| Line | Arithmetic | Amount |
|---|---|---|
| Building permit fee | $4,496.87 + 250 x $6.74 (the $500,001 to $1,000,000 line) | $6,181.87 |
| Plan check fee | $6,181.87 x 0.65 | $4,018.22 |
| Subtotal | $6,181.87 + $4,018.22 | $10,200.09 |
Mechanical and plumbing permit fees, fire fees, a technology surcharge, a state surcharge and any outside or hourly review fees come on top, and electrical permits come from the state. The Tenant Improvement schedule lists impact fees only for a change of occupancy. The technology surcharge is 6 percent under IMC 3.66.020 as amended by Ordinance 3075, effective January 1, 2025, even though the city’s remodel page still says 5 percent. The state fee for a residential only building permit is $6.50 under Table D of Ordinance 3138, while the Tenant Improvement schedule lists $25. The chart’s lines also do not chain exactly: the $100,001 to $500,000 line reaches $4,617.06 at $500,000, while the next starts at $4,496.87. The city’s pages do not say how a remodel’s valuation is set, so ask for an estimate on your scope in writing. My Seattle, Bellevue and Kirkland fee guides show how I work a schedule, though each city’s table is its own.
What changes the cost and the schedule
| Item | Planning figure | What moves it |
|---|---|---|
| Design and permit fee | Fixed fee, about $10,000 to $200,000 | Project budget and location. The agreed scope is the scope the fee covers. |
| Whole house renovation | $300 to $550 per sq ft | Condition of the structure, how much of the plan changes, new systems, site access. |
| Additions | $350 to $650 per sq ft | New foundation, roof and envelope, and the soils and slope conditions. |
| Design to permit submission | Typically 2 to 4 months | Survey, existing conditions, engineering and your decisions. |
| City review | See the table above | Permit type, completeness of the first submission, comments. |
Planning ranges from Piper Cole, before design fees, permits, sales tax and contingency. They are not quotes. At those ranges, $750,000 of construction renovates roughly 1,364 to 2,500 sq ft ($750,000 divided by $550, and by $300). The million dollar remodel guide shows where the money goes. On an Issaquah house, a nonconforming wall, a hillside, trees, the shoreline buffer and the Highlands committee round can each add scope or time. Opening walls may also bring a structural engineer; see when a remodel needs one.

What to ask any architect before you sign
- Is my house nonconforming, and how will you show it was legal when built? The answer should name IMC 18.214 and the records you will pull.
- Where does my scope sit against the 75 percent line? A good answer uses the assessed improvement value for my parcel and says which costs the city counts.
- Do I need a soils report, a critical areas study or a tree permit? Ask what each adds in time and consultants.
- Am I in the Highlands, Talus or the shoreline area? That decides who reviews first.
- Is the fee fixed, and is it set before drawings start? Ask whether it is fixed or a percentage of construction cost, and what happens if the budget moves.
- What sits outside the fee? A surveyor, structural, geotechnical and civil engineers, an arborist and the city’s permit fees are the usual items.
- How many correction rounds did your last Issaquah jobs take?
- Do you administer construction, and do you build? I administer for you and do not build, so the person judging the work is not doing it.
How the work runs, in order
| Step | Typical time | What you get |
|---|---|---|
| Free feasibility check | About a day | Whether the plan fits the lot, the code and the budget at a basic level. |
| In-depth analysis, if you want it | $1,500, 2 to 3 weeks | A deeper look at zoning, code and budget. Ask what it covers on an Issaquah lot, such as the 75 percent line, slopes, trees and the shoreline. |
| Design to permit submission | Typically 2 to 4 months | Drawings, engineering and the permit set, filed on MyBuildingPermit.com. In the Highlands, the committee stamp comes first. |
| City review | See the review table | Comments, revisions and an issued permit. |
| Bidding and construction | Set by scope and builder | Builder pricing, a contract, and my administration of construction on your behalf. Ask each builder for a written schedule. |
I have worked as an architect since 1996, I am an AIA member since 1992 and an NCARB member since 1996, and I take on 20 to 30 projects a year. I have won three Masonry Excellence Awards, for commercial projects. The Carr residence was featured in Above The Lake and Lux magazines. My office is in Kirkland, and the remodels I take on start at $750,000.
Before you design
Find out what your Issaquah house will carry
Send me the address and what you want to change. The first feasibility check is free and takes about a day.
Questions
How much does an architect cost for a whole house remodel in Issaquah?
I quote a fixed fee for design and permit, set by the project budget and location, typically about $10,000 to $200,000 depending on scope. The first feasibility check is free and takes about a day. An in-depth analysis is $1,500 and takes 2 to 3 weeks. Ask any firm whether its fee is fixed and what sits inside it. City permit fees are separate and are set by the City of Issaquah.
Do I need an architect to remodel my house in Issaquah?
Not by law. RCW 18.08.410(5) exempts design work for a residential building of up to and including four dwelling units from the architect licensing requirement. The city does require drawings, and its packets say that if an architect or engineer prepares the plans, every sheet and calculation must be stamped. An architect prepares those drawings, coordinates the engineers and surveyor, and answers the city’s comments.
Will my Issaquah remodel be treated like a new house?
Only if the house is legally nonconforming and the work is large. Under IMC 18.214.070, a remodel that costs less than 75 percent of the latest King County assessed improvement value goes through a Level 1 review, and at 75 percent or more it goes through the review process for new development of the site. Either way the change must reduce the nonconformity as far as practical and feasible. A demolished house must meet current code. Confirm with the city.
How long does Issaquah take to review a remodel permit?
The city’s Target Review Times handout, last updated April 2026, sets 4 weeks for the first review of a single family building permit, 3 weeks for the second and 1 week for later rounds. The clock starts when permit fees are paid, and each figure is one review round. These are targets. I did not find a published report of how long completed residential permits actually took.
Can I remodel a house on Lake Sammamish?
Usually yes, if it was legally built. Shoreline jurisdiction reaches 200 feet landward of the ordinary high water mark, with a 35 foot buffer and a 15 foot building setback. An existing legal house may be modified or expanded without a shoreline variance if the work stays landward of the buffer and setback, and new impervious area above 500 square feet in five years requires equal buffer planting. Ecology gave final approval to the program amendment (Ordinance 3089) on May 12, 2025. Check with the city for how it applies to your lot.
Do I need design review in the Issaquah Highlands or Talus?
In the Highlands, IMC 18.706.030 says that before submitting any permit you must show Architectural Review Committee approval where the committee has purview, or show that it is inactive, and the city’s packet asks for the committee’s stamp on the site plan and elevations. Talus has its own development standards under IMC 18.708. I found no city design review step for a detached house in the SF-E, SF-S or SF-SL zones. Confirm with the city and the association.
Can I build on or near a steep slope in Issaquah?
Near one, yes, with limits. A steep slope hazard area is 40 percent or steeper. It carries a 50 foot buffer from the top and toe that a critical areas study can reduce to 10 feet, an occupied building must stay at least 25 feet from the top or toe, and a 15 foot building setback applies from the buffer edge. Lesser slopes of 15 percent or more with 10 feet of rise fall under the forested hillside chapter. Source: IMC 18.802.130, 18.802.450 and 18.810, as of October 2026.
How much house can $750,000 renovate?
At the planning range of $300 to $550 per square foot for a whole house renovation, $750,000 of construction covers roughly 1,364 to 2,500 square feet. That excludes design fees, permits, sales tax and contingency.
Does Piper Cole build the project?
No. Piper Cole designs the project and administers construction on your behalf, and it does not build. You contract with the builder, and I work for you during construction.