Home / Resources / Clyde Hill remodels
Clyde Hill remodels
Whole house remodel architect in Clyde Hill, Washington
What a Clyde Hill remodel runs into at the city, which reviews belong to the city and which to other agencies, what the city publishes about time and fees, and what to ask any architect before you sign.
On this page
- The $493,000 line a $750,000 remodel crosses
- The envelope: 1953 ground, side yards and the 30 degree line
- What the city does and what other agencies do
- Review time and city fees, as published
- What changes the cost and the schedule
- What to ask any architect before you sign
- How the work runs, in order
- Questions
Key takeaways
- A $750,000 remodel is very likely above Clyde Hill’s 2026 substantial remodel line of $493,000. Past it, every structure on the lot must meet current setbacks, height, coverage and drainage rules.
- No part of a structure may rise more than 25 feet above the lot’s ground as it was in March 1953, and on lots under 15,000 square feet a 30 degree line limits each side.
- The city says a complete application is generally decided within 15 to 45 working days. Bellevue handles fire, water and sewer reviews.
- I quote a fixed fee for design and permit, about $10,000 to $200,000 by budget and location. The first feasibility check is free and takes about a day.
- Piper Cole Architects is based in Kirkland. It designs and administers construction. It does not build.
Short answer: if you own a house in Clyde Hill, Washington and plan a remodel of $750,000 or more, hire an architect who first tests the project against the city’s substantial remodel line, because at that budget you will very likely cross it. Past the line, every structure on the lot must meet today’s setbacks, height and coverage and the current drainage rules, and keeping anything that does not fit may take a variance. I am David Meade of Piper Cole Architects in Kirkland. I quote a fixed fee for design and permit, about $10,000 to $200,000 depending on the project budget and location, and the first feasibility check is free and takes about a day.
This page is for a Clyde Hill owner with a remodel budget of $750,000 or more who is choosing an architect. Residential remodels at that size are the work I most want, and $750,000 is the smallest project budget I take. I administer construction for you and do not build. The rules below come from the City of Clyde Hill’s own handouts, guide and fee schedule, read on 15 October 2026. The city’s code host blocks automated readers, so for code sections the handouts do not print (CHMC 17.38, 17.60 and the variance test) I used a third-party copy of the code that may lag the official text. Confirm any number with the city. My Clyde Hill permit guide has the full envelope.
The $493,000 line a $750,000 remodel crosses
Clyde Hill’s main test is a dollar amount, not a share of the house’s value or a length of wall. The city’s Residential Zoning Rules handout, last modified April 16, 2026, says the 2026 substantial remodel threshold value is $493,000. The building official sets a project’s value when you submit, counting all labor, materials, overhead and profit, finish work and building systems. That list does not mention design or permit fees, so test your construction value, not your total budget: at $750,000 all in, construction would have to fall under about 66 percent of it ($493,000 / $750,000 = 0.657) to stay below the line. Projects within two years are added together, and the figure changes each January. Arithmetic: $750,000 / $493,000 = 1.52, so a $750,000 construction value is about 52 percent over the line.
| What crossing it triggers | What the city says | What it means for the design |
|---|---|---|
| Current zoning for the whole lot | Existing structures must be brought into compliance with setback, height and lot coverage rules. In some cases that may mean asking for a variance to keep a nonconforming structure. | Draw today’s yards, height plane and coverage over your survey and list what sits outside them. A house that already fits loses nothing. |
| Current drainage rules | The property must comply with the city’s storm water regulations, including connection to its storm water system. The guide lists a drainage or detention system as required. | A civil engineer joins early. The drainage guidelines add a soils report at 2,000 to 5,000 square feet of new or replaced hard surface. |
| Extra items on the way to a permit | A parking plan, with a $250 cash deposit due before the permit issues; a meeting with the City Arborist before you submit; and generally a water and sewer availability certificate from Bellevue. | Book the arborist meeting first, since the city requires it before you submit. |
| A variance, to keep a nonconforming part | The hearing examiner decides. The 2026 fee schedule lists $1,500 plus the city’s outside consultant costs. The code asks for exceptional circumstances such as a narrow, shallow or odd shaped lot, or its topography. | A last resort. I design to the envelope first. |
Below the line, a legally nonconforming house may be altered where the work does not increase the nonconformity or is needed to meet code (CHMC 17.60.020). Demolishing 75 percent of the building’s fair market value during a remodel also brings the whole property under current rules (CHMC 17.60.030). My threshold comparison sets Clyde Hill beside other cities, and remodel or tear down and rebuild covers the choice.
The envelope: 1953 ground, side yards and the 30 degree line
Height is measured from original grade, which the code defines as the lot’s ground when the city incorporated in March 1953 (CHMC 17.04.330). No part of a structure may exceed 25 feet above it (CHMC 17.16.020), and the city’s handout says each and every point on a structure must comply. Fill added since 1953 raises nothing, and the city’s guide says height limits are strictly enforced.
A property needs an original grade determination only once, and if the house was built or remodeled after 1953 one is likely on file. If the structures largely predate 1953, you apply in person with a current survey ($250 in the 2026 fee schedule). It comes before design.
| Lot size | Side yards | 30 degree rule above 12 feet | Example width |
|---|---|---|---|
| 15,000 sq ft or larger | 15 feet on each side | No | 100 foot lot: 70 feet of house (100 to 30). |
| Over 10,000, under 15,000 sq ft | 10 feet on each side | Yes | 90 foot lot: 70 feet (90 to 20), upper floor stepped in. |
| 10,000 sq ft or smaller | 15 feet in total, at least 5 on either side | Yes | 70 foot lot: 55 feet (70 to 15), upper floor stepped in. |
Source: CHMC 17.16.050 and the city’s Residential Zoning Rules handout. Example widths are my arithmetic on made-up lots.
Front and rear yards are 30 and 35 feet, measured to the eave or outermost part of the building, so overhangs count (CHMC 17.04.420). On lots under 15,000 square feet you start at the side setback line, draw a 12 foot vertical line, then a line angling away at 30 degrees, and no part of the structure, gutters included, may cross it. The wording does not say which reference the 30 degrees is measured from, so I confirm my reading with the city.
Structural coverage is capped at 30 percent of the lot and impervious coverage at 60 percent, measured to the outermost projection, gutters and light fixtures included (CHMC 17.16.080). On an invented 12,000 square foot lot that is 3,600 square feet of structure (12,000 x 0.30) and 7,200 of hard surface (12,000 x 0.60). I found no floor area ratio in the R-1 chapter, so coverage, height and the side lines decide how much house you get.
Views, trees, design review and hours. The city’s view law, CHMC 17.38, deals with trees, not houses. A tree owner has a defense if the other owner’s own substantial remodel or rebuild created or worsened the obstruction. I found no design review step for a single house in Title 17 or the city’s handouts, though the city reviews the landscape plan, for plants only. Construction hours are 7 a.m. to 6 p.m. on weekdays and 10 a.m. to 4 p.m. on weekends and holidays.
What the city does and what other agencies do
Clyde Hill is a city of about 3,000 people, and it hands several reviews to others. Its Building Department reviews and issues the permits, and it may use outside consultants for plan review at actual cost plus $80.
| Who | What they handle on a remodel | What it means for you |
|---|---|---|
| City of Clyde Hill, Building Department | Zoning, building and mechanical permits, drainage and detention, demolition, grading and right-of-way permits, inspections, the City Arborist’s reviews, and SEPA when soil moved exceeds 100 cubic yards. | You sign a notarized Assignment of Agency form so your architect can act for you. |
| City of Bellevue (fire, water, sewer) | A sprinkler determination stamped on two plan sets before you submit, the sprinkler permit if required, and the water and sewer availability certificates. | The city’s guide says remodels may require sprinklers and gives no size line, so the answer comes from Bellevue. |
| Washington Labor and Industries, and King County Environmental Health | Electrical permits (state) and plumbing and gas piping permits (county). | You or your builder apply. The city does not issue these. |
Source: the city’s Building Project Guide, section F, and Permits page. The guide is labeled last modified 1/24/2024, and the city says the code controls over it.
Review time and city fees, as published
The city’s Building Project Guide says approval or denial of a complete application should generally come within 15 to 45 working days, and that major projects such as certain residences may take longer. More than 100 cubic yards of soil imported and exported in total adds SEPA review, generally three to four weeks, and no permit issues until it finishes. At five working days a week, 15 to 45 working days is 3 to 9 weeks. The fee schedule also lists an expedited plan review at double the permit review fee, review guaranteed within two weeks; ask whether it is open to a project this size. I found no published report of actual completed times, so these are the city’s goals.
With my 2 to 4 months of design to submission, that is roughly 3 to 6 months from design start to an approval (2 months plus 3 weeks is about 2.7; 4 months plus 9 weeks is about 6.1). It is arithmetic on goals and leaves out SEPA, revision rounds and payment of fees before issuance.
| City fee line, 2026 schedule | Arithmetic at a $750,000 value | Amount |
|---|---|---|
| Building permit fee, Table 1, over $50,000 | $849 for the first $50,000, plus $9 for each additional $1,000: 700 x $9 = $6,300, and $849 + $6,300 | $7,149 |
| Plan review fee | 65 percent of the permit fee: $7,149 x 0.65 | $4,646.85 |
| The two lines together | $7,149 + $4,646.85 | $11,795.85 |
Source: Exhibit A to the city’s Master Fee Resolution, as posted on the city’s Fees page, Building Permit Fee Schedule Table 1. The value is a worked example, not a quote. The table is untidy: its top tier ends “to and including $50,000”, and the tier below it reaches $864 at $50,000 ($514 + 25 x $14) while the top tier starts at $849. I read the top tier as $9 for each $1,000 above $50,000, and the city computes the real fee.
Other charges sit beside those lines: a $25 technology fee, a state fee whose amount is not in the schedule, mechanical permits ($80 to issue plus unit fees), the pre-application conference, required above $50,000 ($154 for the first hour, $100 credited to plan check if a complete application follows within 60 days), a final inspection fee of $200 plus $107 an hour of staff time, $250 for original grade and $250 for SEPA. Electrical, plumbing and Bellevue’s reviews carry their own fees. The building official sets the final value.
Permits are valid for one year from issuance, says the city’s Permits page. The code may attach conditions to that year, such as finishing the exterior and a charge to renew, but the code host blocked me today, so ask the city for the current text of CHMC 15.04.060 before you plan a schedule around it. My remodel timeline guide covers the phases.
What changes the cost and the schedule
| Item | Planning figure or fact | What moves it |
|---|---|---|
| Design and permit fee | Fixed fee, about $10,000 to $200,000 | Project budget and location. |
| Whole house renovation | $300 to $550 per sq ft | Condition of the structure, how much of the plan changes, new systems, site access. |
| Construction | Priced by a builder on finished drawings | Scope and site. Ask each builder for a written schedule. |
Cost ranges are planning ranges from Piper Cole. They are not quotes.
At those ranges, $750,000 of construction renovates roughly 1,364 to 2,500 sq ft ($750,000 / $550, and $750,000 / $300). Clyde Hill items that can add scope: the drainage or detention system, special inspections and structural observations, a surveyor’s certificate after framing, and a variance hearing. See my structural engineer guide and energy code guide, and my teardown and rebuild page if the numbers point to a new house.

What to ask any architect before you sign
- Will my project count as a substantial remodel, and who sets the value?
- Which parts of my house sit outside today’s side yards, 25 foot plane or 30 degree line, and what is the plan for each?
- Is the fee fixed, and is it set before drawings start? Ask what sits outside it: surveyor, engineers, arborist and the city’s fees.
- Who designs the drainage or detention system, and when? Required at a substantial remodel, it can change the site plan.
- How will you schedule the project against the permit’s one year term, and what happens if the work runs past it?
- Do you build, and will you administer construction? I administer for you and do not build.
How the work runs, in order
| Step | Typical time | What you get |
|---|---|---|
| Free feasibility check | About a day | A very quick read on whether the plan fits the lot, the rules and your budget. |
| In-depth analysis, if you want it | $1,500, 2 to 3 weeks | A deeper look at the remodel line, original grade, side lines, drainage and cost before full design. |
| Design to permit submission | Typically 2 to 4 months | Drawings, engineering coordination and the permit set. |
| City review | See the review section above | Comments, revisions and an issued permit. |
| Bidding and construction | Set by scope and builder | Bids on the same drawings, then my administration of construction. |
I have worked as an architect since 1996. I am an AIA member since 1992 and an NCARB member since 1996, and I take on 20 to 30 projects a year. I have won three Masonry Excellence Awards, for commercial projects, and the Carr residence was featured in Above The Lake and Lux magazines.
Before you design
Find out what your Clyde Hill house will carry
Send me the address and what you want to change. The first feasibility check is free and takes about a day, and I will say whether the $1,500 in-depth analysis is worth doing next.